PM Chapter 7 Part One
PM Chapter 7 Part One
PM Chapter 7 Part One
Project
Management
Part one
Contents
Examples.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Three main goals for any project:
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Defining and Organizing Projects
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Constructing Project Networks
• 1-Defining the Work Breakdown Structure (WBS)
• 2- Diagramming the Network
• Developing the Project Schedule
• Analyzing Cost-Time Trade-offs
• Assessing and Analyzing Risks
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
• Work Breakdown Structure
– A statement of all work that has to be completed.
• Activity
– The smallest unit of work effort consuming both time and
resources that the project manager can schedule and
control.
– EXAMPLES?
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Work Breakdown Structure
Figure 7.1 Work Breakdown Structure for the St. John’s Hospital Project
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Diagramming the Network (1 of 2)
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Diagramming the Network (2 of 2)
• Precedence relationship:
– A relationship that determines a sequence for
undertaking activities; it specifies that one activity
cannot start until a preceding activity has been
completed.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.1 (1 of 2)
Immediate Activity
Activity Predecessors Times (wks) Responsibility
B. Select site and survey Start 9 Taylor
Finish K 0 blank
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.1 (2 of 2)
Figure 7.2 network:
Immediate Predecessor
A —
B —
C A
D B
E B
F A
G C
H D
I A
J E,G,H
K F,I,J
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Application 7.1 (1 of 2)
The following information is known about a project
Immediate
Activity Activity Time (days) Predecessor(s)
A 7 —
B 2 A
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Application 7.1 (2 of 2)
Immediate
Activity Activity Time (days) Predecessor(s)
A 7 —
B 2 A
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Developing the Project Schedule
• Path
– The sequence of activities between a project’s start
and finish.
• Critical Path –
– The sequence of activities between a project’s start and
finish that takes the longest time to complete.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Issue to consider:
• Identify the start and finish times for each activity for a
project schedule.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.
Example 7.2 (1 of 5)
Paths are the sequence of activities between a
project’s start and finish.
Copyright © 2016, 2013, 2010 Pearson Education, Inc. All Rights Reserved.