A project is a complex process which involves various activities and huge data.
Hence SAP Project Systems (PS) is specifically designed to provide comprehensive Project
Management functionality to SAP Customers.
Project systems serves as a useful tool to effectively manage functional and technical
aspects of various ongoing projects of an organization, it helps in Planning, Organizing,
Budgeting, Management of services and other sales processes involved in the project.
Before you Run any project, it is necessary to describe the project goals and structures for
project activities to be carried out in a timely manner, A clear project Structure provides a
basis for successful project planning, monitoring and control.
SAP project Systems is highly Integrable solution. Which integrates with Finance, HR, and
various Logistics Modules to manage Large and complex projects such as construction,
production service, investment projects in all types of industries.
Project
Systems
WBS
Elements
Networks
Work
Centres
PS Organizational Structure
At the highest level of SAP PS, projects are defined and then structured into an
organizational form that maps to the specific project.
1. Work Breakdown Structure: The project is first broken down into work breakdown
structures (WBS) which map to specific project deliverables.
2. Networks: Each WBS can then be broken down into networks of activities. A network can
be thought of as a list of tasks organized into a process flow with specific timing.
3. Activities: Activities are the key tasks to be completed. These activities map to internal
activities, external activities, cost activities and materials components.
Building Construction
Floor 1 Floor 2
Electricity
Painting Activities
Settlement
Settlement
Project Elements
Configuration Steps in project systems
7. Network
8. Activity
15. Budgeting
18. Change the Field Status group G010 for Field Status Variant TML (T. Code OBC4)
22. Post the Cost to the WBS element Through (T. Code F-02)
23. Display the Cost at Project Level (T. Code CJI3)
25. Post the Pending Cost (Rs.100000) to the WBS element (T. Code F-02)
In this step, you specify how a project number is coded for editing. You can maintain the
following parameters for editing the project number
the length of the key for project coding. You can assign up to five places for the key.
an indicator specifying whether the key must have this exact length or whether it can
also be shorter
special characters to enter WBS elements faster
an indicator specifying whether only coded project numbers can be used to create
projects
SAP Recommendation, Avoid the following special characters: *,+,? and %. These special
characters are used for specific functions in the system.
A project coding mask is used to create a structure for the project IDs. A coding mask helps
in displaying complex project IDs. For example, it can help in indicating the level of the WBS
element in the overall project hierarchy
X for alphanumeric characters
0 for numeric characters
special characters to organize the project numbers
Example
You enter the following mask for key "Z": /000-XXX-000/XXXX
The project number Z453SKS555ELEK is edited to Z/453-SKS-555/ELEK.
TCODE-OPSJ
As below give the project ID, Coding Mask, Coding Description and sav
Third step: Create Project Type for WBS Element
Create project types for project structure elements. Project types are used to group projects
based on a certain category, for example:
Capital-investment projects
Customer projects
Development projects
Here click on new entries, give any Alphanumeric or Numeric code as project type, Give the
description and save
The project profile contains default values and other control parameters such as the
planning method for dates and costs.
The project profile contains default values and other control parameters such as the
planning profiles, Budget profiles, costs, dates Etc
The data that you enter in the project profile will be copied into a project in its project
definition or in the WBS elements which can later be overwritten.
Examples
To carry out cost planning you must specify a planning profile.
To carry out financial budgeting you must specify a financial planning profile .
Go to organisation tab in the same screen and mention all the below details as in below
screen and save
Fifth step: Specify Persons Responsible for WBS Elements
A network can represent the sequence of activities in a project or the sequence of a single
activity within a project. You can graphically display various structural elements of a project
and their interdependencies in the Project System.
During the life of a project, networks are used as a basis for planning, analysing, controlling,
and monitoring schedules, dates, and resources. (Such as personnel, machines, PRTs,
materials, documents, and drawings).
The essential components of a network are:
Activities
Relationships
Activities
The most important data describing an activity in the Project System is:
Work centre in which the activity is to be carried out
Duration of the activity
Start and finish dates for the activity
Resources required to carry out the activity
Texts and documents describing the activity
Relationships
There is usually a reason for a specific sequence of activities in a network. For example,
there may be technical dependencies between individual activities. These dependencies are
represented by relationships in which one activity is the predecessor or the successor of
another activity.
The relationship type specifies how the individual activities are linked with each other:
Finish - Start (FS) Relationship
Relationship between the finish of one activity and the start of its successor.
Start - Start (SS) Relationship
Relationship between the start of one activity and the start of its successor.
Finish - Finish (FF) Relationship
Relationship between the finish of one activity and the finish of its successor.
Start - Finish (SF) Relationship
Here source cost elements will be defined from where cost will flow & receiving elements will also
be defined to where costs will be settled while doing settlement.
Personal Cost
The source cost element for Personal Cost would be like salary, allowances & other expenses
towards employees. There would be "N" no of cost elements, so cost element group can be assigned
to Source.
Material Cost
The source cost elements would be Purchase goods, freight, etc., whichever are having link with
Material.
Receiving Cost Element:
Settlement Cost element can be single or multiple based on the structure, client is following.
After selecting Assignments tab click on new entries, fill the assignment field and text, then
select the line and click on source
Until the source is assigned the overlapping indicator will be yellow. After assigning the
source elements the indicator will turn green
After selecting the source tab, select the range of cost elements, or cost elements groups
can be assigned here and then click on back button
Now select the settlement cost element tab and select settlement receiver, here receiver
category can be Asset or cost centre or order or WBS etc, here since we are settling all the
costs to AUC Asset, we have selected the settlement receiver as FXA (Asset) and save
Tenth step: Maintain settlement profile
In a project, you collect cost and revenues temporarily and they must settle as part of period
end processing. You need a settlement profile stored in project profile or network type,
which determines whether settlement is required, allowed, or blocked.
You can use the settlement profile to define the following for actual costs −
Full Settlement
Can be settled
Not to be settled
As per the settings in the settlement profile, there is a need to settle the costs of an object in
full before that object is achieved in the system.
Availability control
Project System Costs Budget Maintain Budget Profiles
TCODE-OPS9
Click on new entries
Give profile name and text
Select the number of past and future years you want to maintain the budget
Mention exchange rate type
Select activation type
Maintain budget currency and save
Tolerance Limits are set for defining what actions are to be taken when the Budget is
overrun. Example: Warning will be shown if the Budget Exceeds 70% of Budget available.
Warning with mail to the Person responsible when the Budget Exceeds 90% of Budget
available. Hard stop Error will be shown if the Budget Exceeds 100% of Budget available.
Different Budget Profiles can have different Tolerance settings
in this screen
Give project description
Select person responsible
Applicant no
Factory calendar
Time unit
Organisation information
In the same tab select the PE and Account Assignment tick marks and save
Note: The advantage of above setting is for the purpose of planning system will consider the
only elements which are ticked as PE and while making the posting, system will allow the
postings to only those WBS elements which are ticked for account assignment.
Then maintain the budget for each project hierarchy and press enter
Select s/05-001-E1 hierarchy
Click on annual overview
In this step specify the budget amount to be released for each hierarchy
Here I have released only for floor 1, after completion of first floor we can release for
2nd floor
Go to edit menu in same screen and click on total up and then save
Step eighteen: Change the Field Status group G010 for Field Status Variant TML
TCODE-OBC4
In the additional account assignment tab for WBS element mark optional entry and save
Step nineteen: Create Asset class for(AUC)
In this step we need to create AUC Asset class where we need to settle all the costs
IMGfinancial AccountingAsset Accountingorg structureAsset classesDefine Asset
class
TCODE-OAOA
Click on new entries
Give description, Account determination, screen layout rule, number range
Select no AUC settlement and save
In the General tab give the description and click on time dependent tab