HT39
HT39
Testing Procedures
September 11, 2010
SEPTEMBER 2010 2
Overview
SEPTEMBER 2010 3
System Start-up
• General Considerations
– All parties involved should have a representative present for start-up.
– All start-up info should be logged and signed off by appropriate parties.
– All test equipment used for start-up testing should be in good repair and
CALIBRATED!
– Have all appropriate drawings, specifications, and instruction sheets on-hand for
reference.
f
• Mechanical Inspection
– Inspect all insulation and weatherproofing. (Wet insulation is Bad!)
– Inspect all junction box, connection box and sensor connections
– Verify sensors are in appropriate locations
– Verify all circuits have been properly grounded
– Verify all circuits are connected in proper panel locations
– Verify proper circuit breakers are in place
– Verify all circuit lengths are within manufacturers specified limits
– Verify all proper safety warnings are in place
– Verify all end seal, splice/tee locations are marked on lagging
SEPTEMBER 2010 4
System Start-up
• Electrical Tests
– Insulation Resistance (Megger)
• Before tracing pipes
• After installing terminations
• Before Insulating pipes
• Aft Insulating
After I l ti pipes
i
• Before Energizing System
– Circuit Voltage
– Initial Current
• Note ambient temp and pipe temp
– Stabilized Current (15 minutes of operation)
• Note ambient temp and pipe temp
SEPTEMBER 2010 5
Documentation
SEPTEMBER 2010 6
Megger Test
SEPTEMBER 2010 7
Megger Test
Open Cover
SEPTEMBER 2010 8
Megger Test
T t lead
Test l d position
iti R
Result
lt > 50M
50Mohm
h
SEPTEMBER 2010 9
Cold Resistance Test
SEPTEMBER 2010 10
Cold Resistance Test
Result = 2.2Kohms
Open Cover
Read Result
SEPTEMBER 2010 13
Stabilized Current Test
Watts = Current * Voltage
Compare
p calculated result to output
p chart at temp
p
SEPTEMBER 2010 14
End of Circuit Voltage Test
SEPTEMBER 2010 15
End of Circuit Voltage Test
SEPTEMBER 2010 16
End of Circuit Voltage Test
Result = 120Vac
SEPTEMBER 2010 17
Maintenance
• General Considerations
– All personnel should be qualified and trained to perform maintenance
work.
– All test equipment used should be in good repair and calibrated.
– All inspection and test results should be documented on circuit
maintenance
i t log.
l
– Freeze Protection should be checked prior to cold weather each year
as a minimum.
– Process Lines should be checked as the p process requires.
q
• Mechanical Inspections
– Follow same p
procedure as system
y start-up
p
• Electrical Inspections
– Follow same procedure as system start-up
SEPTEMBER 2010 18