8th Sem Synopsis
8th Sem Synopsis
8th Sem Synopsis
On
Submitted in partial fulfillment of the requirements for the award of the degree of
Bachelor of Technology in
Civil Engineering
8th Semester
Jan-June, 2024
ACKNOWLEDGEMENT
It was a great experience working in the Sewage Treatment Plant, Hisar department under the
guidance of very encouraging and enthusiastic people.
From the bottom of my heart, we would like to thank our project guides Mr. DEEPAK
VERMA SIR & Mr. VISHWAS MALIK SIR for helping us a lot and sharing their
experience in completing the project. For me, it was a unique experience to be a part of it and
to study an interesting topic, PERFORMANCE OF SEWAGE TREATMENT PLANT. We
also thank all the people who work on the site for helping me in completing my project. With
their patience and openness, they created an enjoyable working environment. I owe my
indebtedness to all those who helped us directly and indirectly in
the accomplishment of this work.
I would also like to thank the Executive Engineers for giving us a great opportunity
to do our project within the organisation.
INDEX
Acknowledgement i
1. Introduction 01
• Sewerage-general consideration
• Historical Background
• Importance of Sewer System
• Site for Sewage Treatment Plants
2. Problem Statement 03
7. Tests Results 29
8. Recommendations 30
9. Conclusion 31
10. References 32
INTRODUCTION
SEWERAGE-GENERAL CONSIDERATION
DEFINITION
SEWAGE TREATMENT
Sewage can be treated at the place where it is created, which is called a "decentralised" system
or "on-site' system. Alternatively, sewage can be transported by a network of sewer pipes and
pump stations to a municipal treatment plant, which is called a "centralised" system.
REUSE
Industrial end users procure treated sewage from the municipalities, further treat it and reuse it
for non-potable applications such as boiler feed water and cooling towers in a power plant. For
instance, Chennai's Water Board supplies 45 MLD of treated water to companies such as
Madras refineries and Madras Fertilizers. Wastewater is being treated and recycled within
residential compounds for applications such as landscaping/watering plants. Constructed
wetlands fed by wastewater provide both treatment and habitats for flora and fauna. An
example of reuse combined with the treatment of sewage is the East Kolkata Wetlands in India.
These wetlands contain nutrients which sustain fish farming and agriculture.
The basic sewer system was used for the removal of waste in ancient Mesopotamia, where
vertical shafts carried the waste away into cesspools. Similar systems existed in the Indus
Valley Civilization in modern-day India and ancient Crete and Greece. Modern sewer systems
were first built in the mid-nineteenth century as a reaction to the exacerbation of sanitary
conditions brought on by heavy industrialization and urbanization. Due to the contaminated
water supply, the Metropolitan Commission of Sewers appointed Sir Joseph Bazalgette to
construct a vast underground sewage system for the safe removal of waste One of the first
attempts at diverting sewage for use as a fertilizer in the farm was made by the cotton mill
owner James Smith in the 1840s. The idea was officially adopted by the Health of Towns
Commission, and various schemes were trailed by different municipalities over the next 50
years.
The sewage system has a very important role in our lives as it protects both our health and the
environment. Water scarcity is a major problem that is faced all across the world. Above this
major part of the water is being polluted because of human activities. The polluted and
untreated water causes abundant waterborne diseases which further results in a huge climatic
change. Also because of improper use of water and lack of wastewater treatment, the problem
of sewage water will further increase pollution and even cause huge havoc in society. It will
even damage the environmental ecology and might also increase the death rate. Thus it is very
important to establish proper sewer systems and treatment plants to have proper control over
the maintenance of the sewage water. The main purpose of a sewer system is to maintain such
environments that will not affect public health in general. Thus the sewer system aims at the
creation of such conditions of living which will not result in serious outbreak of epidemic in
other words, it is a preventive measure for the preservation of the health of the community in
general and individuals in particular.
The following are the 10 important points in any public sanitation project:
1. Financial aspect
2. Population
3. Present methods of disposal
4. Quality of sewage
5. Rainfall
6. Rate of sewage
7. Source of sewage
8. Topography of the area
9. Treatment methods
10. Trends of town development
The following are the points to be considered at the time of its final selection;
1. The available foundation soil should be good for various sewage treatment units to rest
firmly on the ground and thus, to grant structural stability to them.
2. The general slope of the site should neither be too steep nor too flat. It will assist in
placing various treatment units at such levels that the sewage may flow from one unit to
the other by gravity only.
3. The general slope of the site should be the lowest level area of the town or city so that
the sewage from the entire town or city can be collected and conveyed by gravity only.
4. The location of the site should be appropriate concerning the method of sewage
treatment to be adopted for the project.
5. The location of the site should be such that enough area is available nearby when it
becomes necessary in future to expand the existing project.
6. The proximity of the water course near the site or enough wasteland for irrigation will
be considered an advantage.
7. The site should be safe from floods all the time.
8. The site should be situated on the leeward side of the wind so that undesirable odours
will be prevented from entering the town or city.
9. The site should not be, as far as possible, far away from the city or town.
Sewage treatment generally includes three stages, called primary, secondary and tertiary
treatment.
• In primary treatment, the larger solids from sewage are removed during the treatment
process. The more complex compounds are broken up and converted into simpler
compounds by decomposition. The primary treatment includes screens, grit chambers,
detritus tanks, skimming tanks and sedimentation tanks with or without the use of
chemicals. Some treatment plants have a bypass arrangement after the primary
treatment unit.
• Secondary treatment removes dissolved and suspended biological matter. Secondary
treatment is typically performed by indigenous, water-borne microorganisms in a
managed habitat. Secondary treatment may require a separation process to remove the
microorganisms from the treated water before discharge or tertiary treatment.
• Tertiary treatment is sometimes defined as anything more than primary and secondary
treatment to allow ejection into a highly sensitive or fragile ecosystem (estuaries, low-
flow rivers, coral reefs...). Treated water is sometimes disinfected chemically or
physically before discharge into streams, rivers, bays, lagoons or wetlands, or it can be
used for the irrigation of a golf course, green way or park.
The selection of a particular type of treatment depends upon the techno-economic feasibility of
the process selected for the treatment. The techno-economic feasibility can be attributed to the
following parameters.
There are various treatment options available for the treatment of sewage
water. Various treatment options that are considered for techno-economic evaluation are as
under;
i. Screening
ii. De-gritting
iii. Sedimentation
iv. Sludge digestion
v. Biological Oxidation using aerated lagoons
vi. Sludge drying
The activated sludge is mixed with raw or partially treated sewage. The sewage is given the
usual primary treatments in the activated sludge process. When activated sludge is mixed
properly with sewage containing ample or sufficient quantity of oxygen, the micro-organisms
present in the activated sludge multiply rapidly.
As a result of the phenomena, the following effects take place;
After such precipitate settles down, the effluent which is obtained is clear and sparkling. The
effluents contain a very low amount of organic matter and it is generally not given any further
treatment except chlorination in some cases. A portion of settled sludge is sent for recirculation
and the remaining part is sent to the sludge digestion tanks. The digestion sludge is harmless
and it does not produce any Nuisance.
i. Aeration Tank containing microorganisms in suspension in which the reaction takes place.
ii. Activated sludge recirculation system to maintain sufficient microorganisms in the Aeration
Tank.
iii. Excess Sludge wasting and disposal facilities.
iv. Aeration system to transfer oxygen.
v. Secondary Settling tank to separate and thicken activated sludge.
vi. Gas Digester for gas production and Gas holder for gas storage.
i. Inlet Chambers
ii. Fine screens
iii. Detritor tank
iv. Primary clarifier
v. Aeration tank
vi. Secondary clarifier
vii. Sludge Pumping Station
viii. Filtration Pumping Station
ix. Digester, and
x. Sludge Drying Beds
The development of the Up-flow Anaerobic Sludge Blankets (UASB) reactor dates back to the
early 1970's. Pre-sedimentation, anaerobic wastewater treatment and final sedimentation
including sludge stabilisation are essentially combined in one reactor making it the most
attractive high-rate wastewater treatment option. It produces high-value by-products viz.
• Treated wastewater is usable for gardening purposes or pisciculture after a sample post-
treatment.
• Methane-enriched biogas having high calorific value is converted into a usable energy
resource like heat energy, electricity etc..., and,
• Mineralised excess sludge produced in the UASB reactor for its usage as manure for
agriculture purposes.
UASB initially was developed for the anaerobic treatment of Industrial waste water with
moderate to high COD and BOD concentrations. The basic idea is flocculent or granular sludge
developed in the reactor depending on the waste water characteristics and operational
parameters will tend to settle under gravity when applying moderate upward velocities in the
reactor. In this way no separate sedimentation basin is necessary. Anaerobic bacteria are
developed in the reactor and are kept in the biological reaction compartments for sufficient
time. Organic compounds present in the wastewater are absorbed by the sludge particles in the
reaction zone during its passage through the sludge bed. Organic compounds thereafter get
aerobically biodegraded converting it into methane-enriched biogas and a small part into the
new bacterial mass. Biomass consists of Methane CH4, Carbon Dioxide CO2, Hydrogen H2,
Hydrogen Sulphide H2S and traces of Ammonia NH4 and Nitrogen N2. The biogas can be used
as an energy source and for this reason is collected in gas collectors. A gas, liquid and solids
separator (GLSS) is provided below the gas collectors to provide an opportunity for the sludge
particles to which biogas bubbles are attached to lose biogas and settle back into the reaction
compartments. In between two gas collectors, a settling zone is provided where virtually no gas
bubbles are present in the liquid. The sludge particles carried along with the wastewater flow
are settled in the settling zone and slide down into the biological reaction zone. Wastewater
enters the UASB reactor from the bottom and travels through the reactor in an upward
direction. To ensure sufficient contact between the incoming wastewater and the anaerobic
bacterial mass present in the reactor, the wastewater is fed uniformly all over the bottom of the
reactor. Further mixing in the reaction zone is achieved by the production of the biogas
travelling in the upward direction, the settling velocity of the sludge particles and the density
currents in the sludge mass.
With proper seed material available at the time of the Start-up of the UASB reactor, the
microbial population is developed within three months. Proper care is taken while designing the
UASB reactor to absorb estimated shock loads in terms of hydraulic and organic contents in the
wastewater. The reactor has the following zones;
UASB alone cannot achieve desired results in terms of effluent discharge standards pre-
described for BOD and TSS hence a simple post-treatment in the form of a Facultative type of
Aerated Lagoon is considered after UASB reactors.
d. Facultative Type of Aerated Lagoon:
This is the simplest of all four alternatives chosen for comparison. In this process, primary
treatment consists of only screening and de-gritting. All BOD and Suspended removal is
carried out in a facultative aerated lagoon. A land requirement is higher in this method when
compared to other options. The process consists of the following steps;
• Screening
• De-gritting
• Biological Oxidation in multi-celled aerated lagoon
1. INLET:
The wastewater enters the STP through the inlet pipe having a dimension of 1800mm. The
influent wastewater enters the STP through the inlet. As the capacity of the STP is limited to
30MLD the excess water which enters the inlet is diverted through the by-pass sewer.
2. COARSE SCREEN:
The main purpose of the screens is to remove the floating matter of comparatively large size. If
such materials are not removed, they choke up the small pipes or affect seriously the working
of sewage pumps. Thus the main idea of providing screens is to prevent the pumps and other
equipment from possible damage due to the floating matter of sewage. Coarse screens of 20mm
clear openings are provided ahead of the main pumping station to protect the pumps from
malfunctioning. These screens are arranged below the ground level and are mechanically
cleaned. Standby facility for 50% of the flow is provided for the screening operation. The
coarse screens are also known as the racks, it also reduces the organic load to some extent. This
is of rectangular cross-sectional area having 6m height and 1m width. The thickness of the rods
is 10mm with a clear opening of 20mm c/c. the coarse screen also includes a conveyor belt
which cleans the floating particles from the screen mechanically. The conveyor belt has
dimensions of 6m in length and 1m wide with a thickness of 8mm, which rotates at a speed of
20rps.
The wastewater entering which enters through the inlet under the gravity flow is pumped into
the inlet chamber using the Main Pumping Station. The MPS generally consist of 11
submersible pumps which raise the wastewater along with the sewage to the inlet chamber. A
single raising pump having a pipe of 800 mm with a non-return valve is also provided to feed
the sewage to the inlet of the STP.
4. INLET CHAMBERS:
An inlet chamber is provided ahead of the fine screens to receive the sewage from the main
pumping station via the raising main. The inlet chamber is 3.4m in length and 2.15m in width
with a depth of 7.5m.
5. FINE SCREENS:
Screening is an essential step in sewage treatment to remove large-size floating particles like
wooden pieces, rags, plastics, tobacco pouches, etc, which otherwise damage pumps and
interface with the satisfactory operation of various treatment units. The screen channel consists
of an interface with the satisfactory operation of various treatment units. The screen channel
consists of bars placed across the channel to trap the floating particles. The spacing of the bars
is kept depending upon the type of the degree of treatment required. The plant consists of three
fine screens (2 working and 1 standby) which are run through the hydraulic system. These fine
screens are generally made of stainless steel and have a perforated opening of 6mm with the
thickness of the plates being 1mm. The fine screens also consist of a conveyor similar to the
coarse screen which conveys the collected particles to other places.
6. DETRITOR TANK:
The purpose of the detritor tank is the same as that of a grit chamber. In fact, a detritor tank
may be considered a grit chamber having such velocities of flow that an appreciable amount of
organic matter also settles down at its bottom along with the grit particles. The detritor tank is
generally rectangular. The sides of the detritor tanks are vertical and they are tapered at the
bottom to collect the detritus. The screened sewage flows through a detritor tank consisting of a
mechanical grit removal system. Grit in sewage consists of coarse particles of sand, ash and
clinkers, egg shells and many inert materials organic in nature. Grit is a non-putrescible
substance and has a higher hydraulic subsidence valve than organic substances.
The development of the Up-flow anaerobic Sludge Blanket Reactor (UASB) dates back to the
early 1970s. Pre-sedimentation, anaerobic wastewater and final sedimentation including sludge
stabilisation are essentially combined in one reactor making it the most attractive high-rate
wastewater treatment option. It produces high-value by-products viz.,
• Treated wastewater is useable for agriculture and gardening purposes or pisciculture after a
simple post-treatment.
• Methane enriched with a high calorific value is converted into a usable energy resource like
heat energy or electricity etc... and
• Mineralised excess sludge produced in UASB for its usage as manure for agriculture
purposes.
The UASB process was initially developed for the anaerobic treatment of industrial wastewater
with moderate COD and BOD concentrations. The basic idea is that flocculent or granular
sludge developed in the reactor depending on the wastewater characteristics and operational
parameters will tend to settle under gravity when applying moderate upward velocities in the
reactor. In this way no sedimentation basis is necessary. Anaerobic bacteria are developed in
the reactor and are kept in the biological reaction compartment for sufficient time. Organic
compounds present in the wastewater are absorbed by the sludge particles in the reaction zone
during its passage through the sludge bed. Organic compounds thereafter get anaerobically
biodegraded converting it into methane-enriched biogas and a small part into the new bacterial
mass. Biomass consists of Methane CH4, Carbon Dioxide CO2, Hydrogen H2, Hydrogen
Sulphide H2S and traces of Ammonia NH4 and Nitrogen N2. A gas, liquid and solids separator
(GLSS) is provided below the gas collectors to provide an opportunity for the sludge particles
to which biogas bubbles are attached to lose biogas and settle back into the reaction
compartments. In between two gas collectors, a settling zone is provided where virtually no gas
bubbles are present in the liquid. The sludge particles carried along with the wastewater flow
are settled in the settling zone and slide down into the biological reaction zone. Wastewater
enters the UASB reactor from the bottom and travels through the reactor in an upward
direction. To ensure sufficient contact between the incoming wastewater and the anaerobic
bacterial mass present in the reactor, the wastewater is fed uniformly all over the bottom of the
reactor. Further mixing in the reaction zone is achieved by the production of the biogas
travelling in the upward direction, the settling velocity of the sludge particles and the density
currents in the sludge mass.
The plant consists of 4 UASB reactor units which are further provided with 12 feed inlet boxes
in each reactor. These feed inlet boxes are further connected to 12 outlet boxes of 90mm
diameter. The gas produced in the UASB is collected in Gas Holders through pipes.
A sludge station is provided for the transfer of sludge. A sludge sump is a concrete tank
adequate to hold sludge wasted from two reactors in a day. Sludge pumps are provided to pump
the sludge from the reactors to the sludge drying beds. The sludge pumping station is provided
with 100% stand-by pumping capacity in case of failure or maintenance of operating pumps. A
250mm size LDPE sheet is spread over the floor of the drying beds to prevent the seepage of
the filtrate into the ground as the ground water table is found at a higher level in this area. A
150mm thick layer of gravel having a size of 30-50mm is spread over the brick lining which is
followed by a 150mm thick layer of gravel having a size of 12-30mm on the top of this layer of
gravel a 225mm thick layer of sand having 0.30-0.75mm size is laid. When wet sludge is
spread on the top of the bed major portion of water drains off in a few hours after which drying
of sludge commences by evaporation. The dried sludge is then carried away in trucks for
disposal to sanitary landfills for use as manure on agricultural lands.
This filtrate is collected in an open-jointed GSW pipe with having 200mm diameter. The
filtrate that is drained off is disposed of to the sump well of the Main Pumping Station via a
200mm diameter GSW gravity pipeline. There are 12 drying beds installed in the plant for
drying sludge.
9. GAS HOLDER:
Three floating-type gas holders will be provided floating in a concrete tank with a holding
capacity of six hours of biogas production. It will be provided with an inlet, gas outlet, water
drain, pressure and vacuum relief values arrangements.
Biogas generated in the UASB reactor is stored in the gas holder. This biogas is utilised for the
generation of electricity using a dual-fuel genset. Biogas blowers are also provided to boost the
pressure of biogas to 0.4 to 0.6 kg/cm. before it is fed into the engines. Provisions for pressure
measurement, gas flow measurements, hydrogen sulphide scrubbers and biogas blowers are
provided to the biogas utilisation system before it is fed to biogas engineers.
POST-TREATMENT
The design of a proper -treatment system is important for the success of any project involving
an anaerobic step. Post-treatment required is given in various forms to meet effluent discharge
standards. To meet the inland water discharge standards of BOD and suspended solids,
polishing of the UASB effluents to further remove the residual BOD & TSS will be required.
The flow from the UASB reactors will be treated in a facultative type of aerated lagoon of 1.5
days hydraulic retention time to provide aeration and settlement of suspended solids for further
treatment of the effluent from UASB reactors. In facultative aerated lagoon water treatment,
some solids leave along with the effluent stream and some settle down in the lagoon since
aeration power is sufficient for oxygenation and not for keeping solids in suspension. The
lower part of the lagoon is anaerobic while the upper layer is aerobic. The oxygen demand of
the bacteria is met by surface aeration and algae photosynthesis, but it is not met when the latter
is active. The water environment is aerobic during the day but turns out to be anaerobic during
the night. Biodegradation of the bacteria is due to facultative bacteria, which can operate under
both aerobic and anaerobic conditions.
2. POLISHING POND:
Polishing is the tertiary effluent wastewater treatment stage before the wastewater can
eventually be discharged into natural water bodies. The polishing process involves the removal
of remaining suspended solids and biological oxygen demand (BOD) that may be left after
secondary effluent treatment. This helps in making the water more hygienic and
environmentally safe before release. During this time, sedimentation of non - degradable and
degraded suspended particles at the bottom of the pond is facilitated naturally. Further aquatic
plants, invertebrates and weed-eating fish are introduced in the polishing pond to absorb and
consume any remaining particulate matter.
3. CHLORINATION SYSTEM:
A chlorination system has been given in the design to meet the fecal coli form standards In case
the treated water from the FAL, does not meet the fecal discharge standards. The Chlorination
system includes mainly three units namely the Chlorine house, mixing tank and chlorine
contact tank. It is done to control the odour by the prevention of the formation of hydrogen
sulphide that is being produced. It controls the possible fly nuisance due to sewage and
prevents the spread of the epidemic.
4. CHLORINE HOUSE:
The Chlorine house is provided in the plant to supply the chlorine to the treated water. It
incorporates a vacuum-type gaseous chlorinator along with all accessories and the required
number of chlorine toners.
The chlorine mix tank is provided with a slow-speed mechanical mixer to mix, the chlorine
solution with the treated effluent of FAL. From the chlorine mix tank water will flow to the
chlorine contact tank. The quantity of chlorine mixed is 2mg/lit. For 30 MLD of waste water 60
kg of chlorine is mixed. The chlorine mixing tank has an area of 20.82m2. with a depth of 2.0m
In the chlorine contact tank, actual disinfection of treated wastewater will take place by keeping
water in contact with chlorine. The main purpose of the chlorine contact tank is to keep the
chlorine in contact with the water so that the disinfectant may complete its work the area of the
chlorine mixing tank is 249.84m2. with a depth of 2.5m.
Techno-economic evaluation of various options for the utilisation of sludge and bio-gas has
been done to select the most suitable alternative.
SLUDGE UTILISATION;
• LANDFILLING:
Sludge can be finally disposed of in a landfill, which is the most common method of
solid waste disposal in India. Sludge disposal in this manner requires additional
yearly operation and maintenance costs in terms of staff and vehicles for loading,
unloading and transportation.
• SLUDGE AS A MANURE:
Sludge produced from the UASB reactor will be digested sludge and rich in nutrients
9(N, P, K) which are beneficial for plant growth. Digested sludge from sewage
treatment plants is now acceptable to local farmers to be used as manure in the field.
By selling the sludge at a nominal rate, the department can generate yearly revenue
which will help in the operation and maintenance of the plant. Keeping in view the
above two options use of sludge as manure is found the most techno-economical
alternative.
BIOGAS UTILISATION;
The various alternatives available for the disposal of biogas generated in the plant are;
• FLARING:
Biogas generated from the UASB reactor can be directly flared to the sky in a
controlled manner.
• AS A COOLING GAS:
Bio-gas can be used as a fuel for electricity generation which can be utilised in the
plant itself. The use of biogas for power generation fulfils the power requirements of
the plant partially depending upon the quantity of biogas generated which reduces
the external power requirement and makes the system self-sustainable. Keeping in
view the various options available, utilisation of biogas for power generation seems
the most suitable alternative and hence adopted in the present scheme.
TREATMENT PROCESS DESIGN
1. DESIGN DISCHARGE
2. TREATMENT SCHEME
The natural ground level of the treatment site is undulating with a medium slope towards North
9(i.e. River Musi). Various units of STP will be constructed at different levels using the
existing ground slope.
a) INLET SUMP
A main raising of 800mm diameter for a total length of 75.0 m is provided to convey the
wastewater to the inlet chamber at the STP site where the sewage is further treated in a screen
channel, detritor tank, UASB, FAL and chlorination unit.
3. DETRITOR TANK
5. DIVISIONAL BOX – 1
Overflow weirs of the same weir lengths are provided for equal division of incoming flow. The
crest of the overflow weirs is provided at the same level to ensure equal division.
6. DIVISIONAL BOX – 2
Overflow weirs of the same weir lengths are provided for equal division of incoming flow. The
crest of the overflow weirs is provided at the same level to ensure equal division.
7. DISTRIBUTION BOX
Overflow weirs of the same weir lengths are provided for equal division of incoming flow. The
crest of the overflow, weirs is provided at the same level to ensure equal division.
The crest of the V-notch is provided at the same level to ensure the distribution of the flow.
9. UASB REACTOR
A pump discharges excess sludge produced from two reactors from the sump to sludge drying
beds within 61 minutes.
The treatment efficiency of various parameters in the UASB reactor and the Facultative
type of the aerated lagoon are tabulated below
SR. PARAMETER INFLUENT UASB UASB FAL FAL
NO. VALUE % % % EFFL.
REMOVAL EFFLUENT REMOVAL VALUE
VALUE
1 BOD 400 60 160 60 22.5
2 TSS 350 75 8.50 60 350
3 Fecal coli 3 x 105 80 60000 * *
form
Fecal coli form removal efficiency in the UASB reactor is based on existing plant performance
in India. For achieving discharge standards for fecal coli forms the chlorination system is
provided after FAL.
METHODOLOGY & TESTS CONDUCTED IN THE LABORATORY
The following materials and methods were used in the fulfilment of the major project work;
• Interacted with HMWSSB authorities to seek permission to complete our project in one of their
sewage treatment plants.
• Site visit to the Hisar STP and understanding the different concepts and engineering aspects
used for the treatment of the sewage water.
• Learning and observation of the functions and processes of different units under the guidance
of the STP in charge.
• Demonstration by laboratory staff, on different techniques for sampling and analysis of various
characteristics of sewage water according to their standards.
• Carried out different laboratory analyses to determine different parameters of the sewage water
(BOD, COD, TSS, pH, sulphides, DO, alkalinity etc...)
• Both instrumental and chemical analyses were performed to determine the parameters of the
sewage water.
The methods and types of equipment used for the analysis of the parameters are stated below;
I. pH Value:
The determination of the quantity of dissolved oxygen present in the sewage water is
determined by using DO meter. Simultaneously DO meter also displays the temperature
of the sample. DO meter is provided with a probe which consists of KCl solution and
membrane's filter paper. It includes a magnet inside a box on which the sample is placed
for testing. For determining the DO present in the waste water a sample of waste water is
taken in a borosilicate glass along with a stirrer and is placed on the DO meter. After that
the probe is placed on the top of the borosil glass and the data is analyzed. As the DO
meter consists of a magnet it stirs the sample and measures the amount of dissolved
oxygen present in the water.
Generally, the test is conducted for the influent sewage water and the treated water.
As per the standards, the DO limits for the influent and effluent are as follows
For influent DO = 0
For effluent DO > 4 mg/lit as per the design
III. Sulphides:
For influent, the colour changes to light blue and for effluent, it changes to light pink. The
limit of sulphides in influent varies from 0.50 - 1.00 mg/lit and for effluent it varies from
0.10 - 0.20 mg/lit. After the above steps are performed the glass cell consisting of the
sample is placed in the spectrometer and the results are recorded.
The above-described procedure is the same for effluent and influent wastewater.
Total Suspended Solids (TSS) are the dry-weight of suspended particles that are not
dissolved in a sample of water that can be trapped by a filter. It is a water quality
parameter used to assess the quality of a specimen of any type of water. The
determination of total suspended solids (TSS) present in the sewage water is also
conducted using a spectrophotometer. The process of determining the TSS in sewage
water is similar to that of the process used for the determination of sulphides. After
calibrating the Spectro photo meter with distilled water, a sample of sewage water is
taken in a 20mm glass cell and placed in the Spectro Photo Meter.
The limit of the total suspended solids present in sewage water is as follows:
For effluent sewage water the amount of TSS should be less than 50 mg/lit
For influent sewage water, TSS varies from 300mg/lit - 500 mg/lit
Chemical Oxygen Demand (COD) is defined as the amount of oxygen required for the
decomposition of organic matter present in sewage water and the oxidation of inorganic
chemicals. The amount of COD present in the sewage water is determined using
Digestor. COD measures organic matter by using a chemical oxidant. A strong enough
oxidant must be used to react with virtually all organic material in the sample. Most COD
tests use potassium dichromate as the oxidant. Potassium dichromate is a hexavalent
chromium salt that is bright orange and is a very strong oxidant. Once dichromate
oxidises a substance it is converted to a trivalent form of chromium, which is a dull green
color. Digestion is performed on the samples with a set amount of the oxidant, sulfuric
acid, and heat (150). The digestion typically takes 2 hours to complete.
The test is performed as given below: An acid reagent (A) of 1.5 ml and digestion
solution (B) of 2 ml is added to 5 ml of sample water.
Acid reagent (A) includes sulphuric acid and silver sulphate. Digestion solution (B)
includes sulphuric acid, mercuric sulphate and potassium dichromate. Three glass tubes
of 16mm diameter are taken in which 1.5 ml of acid reagent (A) and 2 ml of digestion
solution (B) are added.
Glass tube 1
1.5ml- acid reagent (A) + 2ml -digestion solution (B) + 2ml of distilled water.
Glass tube 2
1.5ml- acid reagent (A) + 2ml -digestion solution (B) + 2ml of influent sample.
Glass tube 3
1.5ml- acid reagent (A) + 2ml digestion solution (B) + 2ml of effluent sample
The test tubes are then placed in the digestor and are heated for two hours at a
temperature of 150°C.
The results are thus recorded and the amount of COD is determined.
BOTTLE A BOTTLE B
After preparing the sample as given above bottle A is placed in the DO meter and the
quantity of DO is determined which is considered as initial DO. The bottle B is placed in
an incubator at 27°C for 3 days or 5 days at 20°C. After placing the bottle B in the
incubator the quantity of DO present in bottle B is determined and considered as the final
DO.
The same procedure can be used for determining the BOD present in influent
BOTTLE A BOTTLE B
5 ml water sample
5 ml water sample
Alkalinity can be defined as the ability of water to neutralise acid or to absorb hydrogen
ions. It is the sum of all acid-neutralizing bases. In municipal wastewater, the factors that
contribute to alkalinity include the type of dissolved inorganic and organic compounds
present in the water and the amount of suspended organic matter in the water. To
determine the alkalinity of sewage water, the following procedure is followed in the
plant.
A 250 ml of distilled water is taken in a measuring jar to which 7ml constant H2S04 of 1
Normality is added. In another measuring jar having 250 ml of distilled water 5 ml of the
above solution is added thus making the solution 0.02 Normality. 50 ml of sewage water
sample is taken in a conical flask and 2 drops of phenolphthalein and 2 drops of methyl
orange are added which changes the colour of the sample to light yellow.
The above-prepared HSO4 of 0.02 normality is filled in the burette. The water sample is
then titrated with the HSO4 solution filled in the burette until the colour of the water
sample changes from light yellow to light pink. When the colour of the sample is changed
titration is stopped the value of the burette reading is recorded and alkalinity is calculated
using the formula;
Mg/lit 251.25
BOD (INFLUENT)
Mg/lit 27.25
BOD (EFFLUENT)
Mg/lit 570
COD (INFLUENT)
Mg/lit 190
COD (EFFLUENT)
Mg/lit 389
TSS (INFLUENT)
Mg/lit <25
TSS (EFFLUENT) 20
Mg/lit 0.21
DO (INFLUENT)
Mg/lit 3.83
DO (EFFLUENT)
Mg/lit 400
ALKALINITY (INFLUENT)
Mg/lit 340
ALKALINITY (EFFLUENT)
RECOMMENDATIONS
The following recommendations are made for the STP Hisar based on its performance and
other aspects. Though the STP is proposed and designed on a modular basis for the years 2011
and 2005, the Treatment plants are working with good efficiency and give good results.
However, as only 18 acres of the available land are being used and the excess wastewater is left
untreated, it is recommended that the plant capacity be further increased by increasing the units
which can help treat more amount of wastewater.
The methane gas which is generated during the treatment of waste water is not sufficient for the
generation of electricity and hence the gas is burned/flared in the flaring system. This is
because no strong raw sewage water is entering the plant. the production of the gas can be
increased by conduction bench scale and pilot student on co-treatment of wastewater. If it is
found to be successful, selected industries may be allowed to discharge their high-strength
organic sewage into the sewer after the removal of toxic components in the pre-treatment of the
wastewater in their factory premises. With the increase in the production of gas, the gas can be
used for the production of electricity which can be further used for the running of the plant.
As the sewage water after the treatment is again discharged into the river Musi, alternatively
the water can be made to divert into the agricultural land for the growth of plants.
With the four different types of processes for the treatment of the sewage water, it was found
that the UASB followed by the Facultative Aerated lagoon has advantages compared to other
techniques in all aspects. It was found that UASB+ FAL is the techno-economical and best
suited for the treatment of the sewage water that enters the plant. Further using this method
about 75% of BOD is removed resulting in the production of methane gas which is further
useful for the production of electricity and also for cooking gas. The main advantage of this
process is it almost runs through mechanical systems, and less manpower is required. Looking
at the cost comparison and other factors influencing the treatment process it has been decided
to adopt the sewage treatment scheme consisting of UASB and Facultative Aerated lagoons.
The facultative aerated lagoon system is suited for municipal and industrial wastewater of low
to medium strength, but in FAL water treatment, some solids leave along with the effluent
stream and 50-60% of BOD is removed in this treatment. The construction vision is not only
limited to the beauty of the residential/industrial plans but is also environmentally friendly.
This visit gave us knowledge about the purification of sewage water on a large scale. We came
to know about the importance of the purification of water which was carried out at the plant
under various processes. Proper design, engineering, operation and maintenance are imperative
for the successful and satisfactory performance of the treatment plant. Every unit in the plant
performed at its optimal and most efficient design for the overall satisfaction of the treatment
plant. Every unit in the plant is directly or indirectly related to other units.
REFERENCES