Lab 3
Lab 3
SEM 2 2022/23
LAB 3
1. Construct a project network for the following project. The project is completed when activities F
and G are both complete.
Activity A B C D E F G
Immediate
Predecesso ___ ___ A A C, B C, B D, E
r
2. Consider the following project network and activity times (in weeks).
C H
A
Start D F Finish
E G
Activity A B C D E F G H
Time 5 3 7 6 7 3 10 8
c. Can activity D be delayed without delaying the entire project? If so, by how many
weeks?
d. Can activity D be delayed without delaying the entire project? If so, by how many
weeks?
a. Compute the expected activity completion times and the variance for each activity.
b. An analyst determined that the critical path consists of activities B-D-F. Compute the
expected project completion time and the variance.
4. Suppose that the following estimates of activity times (in weeks) were provided for the network
shown in Question 2.
b. Within 22 weeks?
c. Within 25 weeks?
5. Consider the following project network and activity times (in days).
C E
A
Start Finish
D F G
Activity A B C D E F G
Time 3 2 5 5 6 2 2
a. Find the critical path and the expected project completion time.
(i) Formulate a linear programming model that can be used to assist with the
crashing decisions.
(iii) What is the total project cost for the 12-day completion time?