TECHNICAL DELIVERY CONDITIONS FOR CARBON
STEEL PLATE A 516/ SA 516
QUALITY ASSURANCE AND CONTROL
TDC NO:
REV. 00
EEPC/AC01W1/TDC/PC/343/I/0002
Page 1 of 1
PROJECT: M/s 1 X 25 TPH WHRB BOILER, UNITED KINGDOM
Date: 14.03.2024
Carbon Steel Plate
Grade, Size & Quantity As per PO.
Name of Product Carbon Steel Plate
Specification SA-516
Specification for General
SA-20
Requirements
Code ASME Sec II Part A, Latest Edition
Delivery Condition Normalized Condition
Chemical Composition As per Material Specification
Mechanical Requirements As per Material Specification
The steel shall be killed and shall conform to the fine austenitic grain size requirement of
Manufacturing
specification A20/A20M.
Heat Treatment Furnace Normalized
Impact Testing Not Required
NDT UT Shall be carried out in accordance with SA 578 Level B
Plates shall be free of injurious defects and imperfections. It should have a workmanlike
Quality
finish. No repair by welding is allowed.
Dimension Tolerance As per Clause 14 of SA-20.
Yes Required. As per Clause 19 of SA-20. Form IV with EN 10204 Type 3.1 Certificate
Material Test Certificate required. Plate manufacturer shall have quality system certified by agencies accredited by
UKAS.
Yes Required. As per Clause 13 of SA-20. As a minimum the following must be marked.
1. Material Specification & Grade, Type and Class, NDE.
Markings 2. Heat Number & Plate Number.
3. Name or mark of the manufacturer.
4. Heat Treatment.
No Special Packing, but material shall be supplied without any damage during
Packing
transportation.
Material shall be supplied with original Manufacturer's Test report. Inspection shall be
Inspection requirement
done at your place by our Inspector.
End use of material Material shall be used for Steam Drum Construction in accordance with EN 12952.
Finish

Description Name Department Signature with Date

Prepared by A. Kalaiyarasan QA&C

Checked by J. Pavulraj QA&C

Reviewed by S.Rameshkumar ENGINEERING

Approved by B.K. Sahu QA&C