Model - Cyk: Installation and Commissioning Guidelines
Model - Cyk: Installation and Commissioning Guidelines
Model - Cyk: Installation and Commissioning Guidelines
82-CL1 (611)
MODEL – CYK
INSTALLATION AND COMMISSIONING GUIDELINES
*TO: _______________________________________ JOB NAME: _______________________________
_______________________________________ LOCATION: _______________________________
_______________________________________ CUSTOMER ORDER NO. _____________________
The initial site inspection should include, but not be lim- Economizer
ited to, the following components. Record and docu- Economizer Bypass Valve (LCV-117).......................
ment any deficiencies.
Subcooler Valve (LCV-114)......................................
Compressor Components Economizer Liquid Outlet Valve (LCV-116)..............
Compressor Body..................................................... Economizer Flash Gas Valve (PCV-116)..................
Oil System Piping..................................................... Economizer to Low Stage Compressor
Oil Return System.................................................... Vent Line (PCV-117).................................................
GENERAL REQUIREMENTS FOR UNIT 3. If the unit was shipped form 7 (split shells) assem-
INSTALLATION ble shells, and interconnecting economizer liquid
line piping and inter-stage vapor piping.
1. Floor or mounting pads must be level and capable
of supporting the unit weight. 4. Install the refrigerant relief valve piping.
2. Clearances for the sides, top and ends must be 5. Install drain and vent valves in the evaporator and
adequate for Compressor, motor service and tube condenser.
removal. Verify the piping connections properly
oriented. 6. It is suggested that outlets be provided in the con-
denser water and chilled water piping for pressure
3. Driveline and shells must be placed on isolators gauges and thermometers.
of the correct rating and properly positioned. Rig-
ging should remain in place until the isolators are 7. All water piping must be cleaned and flushed prior
installed and bolted in place. to being connected to the unit or shells.
4. Insert spacing blocks under each corner of the 8. Strainers are to be installed in the chilled water
unit to support the shells while the piping is in- and condenser water circuits to protect the ves-
stalled and supported. sels and pumping equipment.
5. After all piping is installed, unit charged, and wa- 9. After the evaporator, condenser and refrigerant
ter in the shell tubes, rotate the leveling bolts one piping have been pressure tested, the refrigerant
at a time to level the unit. (See installation instruc- suction line, chilled water, oil return piping and
tions in job manual) evaporator vessel water boxes must be insulated.
Evaporator water box insulation should be remov-
6. All field installed intercooler piping, valves etc able for service.
should be cleaned prior to installation.
10. Supply 3 Phase Auxiliary power to the unit for the
7. All gaskets, flange bolts and studs must be of the Compressor oil pump drives.
proper size and torqued to the value required for
the bolt diameter. 11. Install and wire flow switches, high-pressure cut-
out and any interconnecting control wiring as re-
8. Do not remove any flange covers until the final quired.
piping is ready to be installed.
ELECTRICAL INSTALLATION
9. All components should remain sealed and
charged with Nitrogen until ready for assembly to 1. All electrical wiring must conform to all National
reduce the risk of contamination or oxidation and local electrical codes.
10. All piping must be fitted so that all bolt holes align 2. Qualified personnel regularly engaged in this type
without any external force applied. of work must perform all wiring.
11. Relief valve piping must be installed in accor- 3. All wiring must be of adequate size and insulation
dance with ASHRAE 15 and all local codes. quality and in accordance with the YORK draw-
ings.
INSTALLATION
4. Field wiring includes but may not limited to the
The following lists of tasks are the minimum require- motor starter fault / contacts, motor starter run
ments that must be completed prior to starting the unit. interlocks, remote hard wired start/stop, flow con-
See the job manual for more detailed installation in- trols and, building automation systems.
structions.
2 JOHNSON CONTROLS
FORM 160.82-CL1 (611)
START UP GUIDELINE FOR THE 6. Leak test the entire refrigerant system, reduce
REFRIGERANT SYSTEM the system pressure and repair any leaks.
Re-test with nitrogen and trace refrigerant
The steps listed below should be performed in the
to 80% of the relief valve setting.......................
order in which they appear. The liquid refrigerant is
not charged into the system until the control check 7. Disconnect the Compressor high discharge
out is completed. This should allow for minimal re- pressure switch and verify calibration to site
frigerant recovery processes if a component requires conditions. ........................................................
removal for repair.
This control cannot be calibrated
Do not energize panel until Step 19 in after the system is charged with
checklist. refrigerant.
JOHNSON CONTROLS 3
FORM 160.82-CL1 (611)
15. Confirm that the power supply voltage to Testing of the pumps has to be done before
control power transformer (T1) is correct, any Proximity Probe Check.
and is of the proper capacity and voltage.
Reference wiring diagram in job manual..........
16. Verify the fluids are in the Compressor oil
sump. (¼" wide red line is full, 1/8" red line
is empty)........................................................... 29. Press the HOME key and select LOW STAGE
17. Remove coupling hubs from high and COMPRESSOR Screen. Press PRV Cal to
low stage Compressor...................................... start the calibration. When complete press
End Calibration.................................................
18. Open all circuit breakers in the panel...............
30. Select the VGD key and calibrate the
19. Energize Main Power Disconnect..................... Low Stage VGD................................................
20. Close CB1 and check for 120VAC at terminal 6. 31. Press the HOME key and select the HIGH
STAGE COMPRESSOR Screen. Press PRV
DC Power Supply
Cal to start the calibration. When complete
Check the out puts from Power Supply.
press End Calibration.......................................
Terminal
32. Select the VGD key and calibrate the
1000 0 VDC............................................... High Stage VGD...............................................
1001 5 VDC............................................... 33. Perform Proximity Probe calibration for both high
1002 12 VDC.............................................. stage and low stage Compressors (Home \ X
Stage Compressor \ XS Prox Calibration). When
1004 24 VDC.............................................. the calibration is complete press the key to end
the calibration.
21. Close CB-2 and check for 120VAC at terminal 33
for Low Stage PRV and VGD Power Verify reference value agrees with reference val-
supply................................................................ ue on label inside panel noted on the inside of the
Panel Door.
22. Close CB-3 and check for 120VAC at terminal
34 for High Stage PRV and VGD Power If the Compressor is pressurized the shaft
supply................................................................ will have to be rotated by hand in the nor-
mal rotation direction to seat the thrust
23. Close CB-4 and check for 120VAC at
terminal 9 of Relay R8......................................
bearing position.
4 JOHNSON CONTROLS
FORM 160.82-CL1 (611)
36. Return to the CONDENSER Screen and select 41. Verify the LOW STAGE Compressor motor ro-
the ECONOMIZER Screen. Manually operate tation. Coupling center hubs must be removed
the economizer level valve LCV-116 to ensure before proceeding!
the valve opens and closes correctly. Check
This must be done by using a MOMENTARY
the Valve Positioner against the Panel Display
START switch. De-energize the control panel and
at 25, 50, 75 and 100% to ensure that the
install the momentary switch between terminal 3
valve and the panel correspond to Linear
and terminal 24.
Operation..........................................................
Re-energize the control panel and momentarily
37. Press the HOME key and select the SET-UP
press the start switch to verify proper motor rota-
Screen. Select the TEST OUTPUTS button and
tion.
manually test
After Low Stage Motor rotation is verified,
LS Liquid injection FCV 113A.......................
de-energize the control panel and remove
HS Liquid injection FCV 113B ...................... the momentary start switch...............................
Economizer bleed valve PCV 117................ 42. Check all relays and terminal strips for
excessive heating with IR thermometer.
LS oil return solenoid operation........................
Excessive heating can be defined as
38. Press the HOME key and select the CAPACITY a 20°F (-6.6°C) rise above ambient..................
CONTROLS \ PID Tuning, then OVERRIDES
43. Verify that the pressure sensors, level
Screen. Verify that the set points are
sensors, and temperature sensors are
adequate for the system design........................
reading correctly.................................................
39. Press the HOME key and select the
After all the controls have been tested and
CAPACITY CONTROLS Screen \
confirmed that they operate correctly the
ANTI - SURGE Screen. Verify the set
unit can be charged with liquid
points for the anti-surge operation.
refrigerant.........................................................
(PD1 - PD2 - MVP1 - MVP2)............................
Reference Surge Control Setpoints 44. Start the condenser water pumps and the
evaporator water pumps to establish flow
Calculation in this document.
in both vessels. ................................................
Check the BAS System for their flow readings
of the chiller / or use a Pressure Gauge to
obtain the Differential Pressure across the
Evaporator and Condenser Inlet Outlet
Both high stage and low stage coupling water boxes. Check these pressures
hubs must be removed before proceeding against the Design Specifications.....................
with compressor motor checks.
Verify Cooling Tower / Condenser entering
water temperature conditions...........................
The unit can now be started and tested for proper op-
40. Verify the HIGH STAGE Compressor motor ro- eration.
tation. Coupling center hubs must be removed
before proceeding!
This must be done by using a MOMENTARY
START switch. De-energize the control panel and
install the momentary switch between terminal 3
and terminal 77.
Re-energize the control panel and momentarily
press the start switch to verify proper motor rota-
tion.
After High Stage Motor rotation is verified,
de-energize the control panel and remove
the momentary start switch...............................
JOHNSON CONTROLS 5
FORM 160.82-CL1 (611)
6 JOHNSON CONTROLS
FORM 160.82-CL1 (611)
STEP THREE Lower the system head to the setpoint in the two stage
PD2. With the hot gas valve closed (hot gas valve
Calculate MVP1 and MVP2 can be placed in manual for this test) the compres-
The initial setpoint for Two Stage MVP1 should be 40 sor should not surge. If surge does occur increase the
The initial setpoint for Two Stage MVP2 should be 20 MVP2 by 5% or until surge stops.
The initial setpoint for Single Stage MVP1 should be 20 If the compressor does not surge then lower the MVP2
The initial setpoint for Single Stage MVP2 should be 10 by 5% increments until the unit surges. When the surge
point is found increase the MVP2 by 5% or until surge
Start the chiller in the two stage mode and
stops.
monitor the system head as displayed on
the system screen. If the compressor vanes are open above
70% and the unit surges the entering con-
denser water temperature may be above
design or the leaving chilled water is be-
Raise the system head to the setpoint in the two stage low design. In these conditions changing
PD1. With the hot gas valve closed (hot gas can be MVP1 or MVP2 will not stop the surging.
placed in manual for this test) the compressor should
not surge. If surge does occur increase the MVP1 by 5 Operate the chiller in the single stage mode and adjust
% or until surge stops. MVP1 and MVP2 in the same manner as in the two
stage mode.
If the compressor does not surge then lower the MVP1
by 5% increments until the unit surges. When the surge
point is found increase the MVP1 by 5% or until surge
stops.
JOHNSON CONTROLS 7
P.O. Box 1592, York, Pennsylvania USA 17405-1592 800-861-1001 Subject to change without notice. Printed in USA
Copyright © by Johnson Controls 2011 www.johnsoncontrols.com ALL RIGHTS RESERVED
Form 160.82-CL1 (611)
Issue Date: June 8, xx, 2011
NEW RELEASE