Managing TIme
Managing TIme
Objectives
After studying this unit, the student will be able to:
understand the importance of scheduling of various tasks during project
execution;
differentiate between traditional job scheduling and project activity
scheduling through network techniques like PERTICPM;
draw the project network diagram and to calculate project completion
fine; and
understand the importance of critical path and float in any project.
I
Structure
i
9.1 Introduction
I 9.2 GANTT Chart for Scheduling
r
I
9.3 Network Analysis for Project Management
I
I 9.4 Total Project Time and Critical Path
9.5 Project Scheduling
9.6 Summary
9.7 Self-Assessment Questions
9.8 Further Readings
fl 9.1 INTRODUCTION
The most important objective of all project managers is to complete the
project in time. A project is usually sub-divided into physically identifiable
and controllable units of activity or work content which is usually known as
4 Work Breakdown Structure (WBS). WBS helps the management to study the
logical inter-relationship among the various work elements systematically.
This WBS works as a framework for the management to communicate
throughout the period of project management.
Scheduling has been defined as a complex activity for deciding the starting
and completion date of any activity,or project. The various activities involve
in this second phase of project management, scheduling, are:
i) Identifying the precedence relationship among the activities or work
elements
ii) Determining the extent of interdependency of events involving work
elements
iii) Scheduling of activities by maintaining inter-relationship in order to
reach the targets of completion time and cost.
Weeks
ACTIVITY 1 2 3 4 5 6 7 8 9
.A I u
I I
C
I
.
I
D
Explanation of Fig 9.1 Project Scheduling
It has been reported in 1957 that E. J. Du Pond has saved one 1 million dollors
by employing the technique of network analysis for maintenance scheduling.
This technique is now known as Critical Path Method (CPM). Almost
concurrently U.S. Navy along with Booz, Allen and Hamilton, consulting
engineers, has developed another methodology for the management of US
Navy Polaris Project which is known as Programme Evaluation and Review
Technique (PERT). Although, these two techniques PERT and CPM have
invented in the context of specific project, but, by 1970s they have emerged as
very powerfill tools for the proper management of wide variety of project
ranging from sending space shuttle to the moon to starting a prima~yhealth
centre in a village by any NGO.
b) Each event, except starting and ending event, will have atleast one
incoming and one outgoing activity. The starting event has only outgoing
activity, while, the ending event has only incoming activity.
d)
Starting/
Tail Event
Completiod
Head Event
Size of the circle, length, orientation and stape of the arrow have no
significance in the project network.
1I
1
e) In any project network diagram time always L'lows from left to right. Head
,events are numbered higher than that of tail event.
f) Subsequent activity can begin only when its tail even is completed.
g) There must be cley indication of beginning and ending event for any
project. If any network diagram fails to indicate this without any
conhsion, that defect is known as Dangling and Looping. These errors
can be removed by introducing DUMMY or REDUNDANT ACTIVITY
which is indicated by broken line. The time taken for a dummy is
considered as Zero.
Usually, any network is described by stating the events i.e. starting and
finishing of activities. The PERT network is generally described by events in
which these activity times are considered as uncertain. But, in case of CPM
network, the time consumed by activities aredescribed deterrninisticakky.
However, this distinction of describing PERT and CPM network by the nature
of activity time has already been disappeared. They are now described
interchangeably by adopting either of the method. However, it is advisable to
maintain a consistent convention throughout the network logic.
1
Measure of ACTIVITY Time
Each activity in a network takes some time to perform. @e duration time for
an activity is the time which is actually expected to be required for carrying
out that activity. The time estimate for an activity can be either a uniquely
- determined value as in the case of CPM network or a probabilistic value
determined out of a chosen forum of distribution of any PERT network.
The duration time of an activity (t,,) can be conveniently handled
deterministically in CPM technique which deals with mostly repetitive type of
activity. The times require for activities demand creative ability, like design
and analysis, Research type and many non-repetitive type of jobs, cannot be
forecasted with certainty. PERT network is generally deals with such cases. In
order to reflect this uncertainty, a form of probability distribution (P= Beta) is
chosen to describe the activity time in PERT network. In any PERT network
the activity time is represented by three times in the sequence of a-m-b which
subsequently is converted into a single time estimate (te) with the help of
following formula
a+4m+b
te = Estimated Activity Time =
6
Where
a = Optimistic time, signified that nothing goes wrong
b = Pessimistic Time, signifies that everything goes wrong
m = Most likely Time, represents frequently occurring time.
Project Scheduling
9.4 TOTAL PROJECT TIME AND CRITICAL
PATH
Each activity in any network is connecting a Successor event with a
predecessor. The time at which an event can be completed is the maximum
time of the various paths flowing into that event. Similarly, the total project ,
time is the maximum of the elapsed times among all the paths in between the
starting and ending event of the project network.
i) Begin with the starting event, calling it zero time that means Ei = 0
ii) Proceed to each event in sequence and calculate the earliest possible time E,
Ej= Max (E,+t,,)
iii) After reaching at the last even, make E, = L, and start calculation in
backward direction with the help of the following equation
Li= Min (L, - tg)
iv) This process of calculation of Li value for each event will continue till the
starting event for which Li = 0 and Ei= Li= 0
Example 1
, Similarly
$?
?
ET7Max I E, + t,, , E6+ t6,1
=Max 111+8, 20+3 1
,
The Float is related with any activity. It is the-extra time available with that
activity. This extra time can be utilized for scheduling and resource
.reallocation. Total float is calculated with following equation. .
!
i
TF = Total Float = Lj- E, - tlj
The total float for critical activity iszero. Float exists for Non-Critical activity.
From Example- 1
Critical Activity: 2-5 Float = 1 1 - 4 - 7 = 0
The significance of the critical path needs to be understood properly by any Project Scheduling
project manager. Since, the critical path is that path having E and L values are
same, it indicates that no flexibility is available with the planner for changing
the schedule of these activities. It only indicates that all the critical activities
must have to be completed ac'cording to the planned schedule. Any deviation
from this plan would affect the finishing time of that critical activity which
will eventually affect the pro~ectcompletion time. It is observed that for some
activities, although, E and L values are same, but that activity cannot be
declared as critical activity. The reason for this is that the total float for that
activity is not zero, for example the activity 5-7 in Figure 9.2.
The cost is also considered as proportional to the time. Therefore, the project
cost will also increase with the increase of project time. In view of all these, it
is absolutely essential on the part of project manager to mobilize all the
resources in such a way so that all the critical activities could be completed
according to the planned schedule.
Tim,e (a - m - b)
7- 9- 11 5416 = 9
9- 11 -13 6616 = 11
6- 9- 12 5416 = - 9
. 9.5 PROJECT
SCHEDULING
activities and also the project completion time. At this stage, it is also possible
to identify the critical path. The primary objective of scheduling is to ensure
the completion of the project on the calculated completion d a t ~The. other
objective of scheduling is to maintain uniform or level requirement of all lcind
of resources during the project implementation period. For the llfillment of
these objectives, the activities can be scheduled on the basis of Early Start,
Early Finish, Late Start and Late Finish time.
------------
Since, theaEmd L values are same for all critical activities, these activities
have to be scheduled according to the times calculated earlier on the network
diagram. The choice for scheduling on the basis of four different times exists
only for n6n-critical activities whose E apd L values are different. The total
float for non-critical activities can be abaorbed fully or partially for scheduling
these activities. The depl~ymentof various resources will vary for the,
different schedule. An example of schedule based on early start date for the
PERT network diagram has s h o w In Figure 9.5. The broken line indicates the
existence of float for that specific non-critical activity.
I
The project manager can generate alternate schedule based on the four Project Scheduling
different times and also can calculate the resource requirement for each
schedule. The criteria for selection of a particular schedule will be the smooth
or even requirement of resources throughout the execution period of the
project. This makes the planning, procurement, coordination and execution
much more simplified on the part of the project manager.
9.6 SUMMARY
I
The project managers throughout the world are mostly concerned about the
proper scheduling of activities for meeting the project completion date. The
Gantt Chart invented in the early of 2 0 century
~ has been in use for
considerable period of time for the purpose of scheduling. To overcome the
several drawbacks of Gantt Chart, network methods like PERT and CPM
methods have been invented in late 1950s in USA. These methods have
established the interrelationship amongst the various activities of the project.
The network method of analysis of the project helps to identify the critical
path, critical activities and events.
SELF-ASSESSMENT QUESTIONS
1. What are the objectives of scheduling?
2. Explain Gantt Chart. Discuss its drawbacks
i
I 3. Driw the project network from the following data
Activity: 1-2 1-3 2-3 2-4 3-4 3-5 4-6 5-6
I
Time : 2 7 5 5 0 4 10 6
(Weeks)
4. Explain the significance of Float. Calculate the float for the problem given
w,
Project Menagemen*
9.8 ' FURTHER READINGS
1. Bhattacharyya, A. and Sorkhel, S., Management by NerworkAnalysis,
Institution of Engineers (India), Kolkata.
'. 2. Boloand, RGA., ILO, Project Management and the Environment, ILO,
Geneva 1986.
3. ChoudhuryS., Project Management, TMH, New Delhi
4. Joy, P.K., Total Project Management, Macmillan, India
5. King, W.R. and David, I., (Eds); Handbook of Project Management
6. Lock, D.L., Project ~ a n a ~ e m e nGower
t, Press, London
7. Nicholas, J.M., Managing Business and Engineering Projects, PHI,NPW
Delhi.
8. Project management (MS-52& E-2) IGNOU, New Delhi.