Set D: Offline
Set D: Offline
Part - A
(1 x 5 Marks = 05 Marks)
Instructions: Answer all questions
Q. Question Op
Mark
No tio BL CO PO
s
n
The power generated in a windmill is more in rainy season
since, damp air would mean more air mass
A. hitting the blades
1 B. depends on the height of the tower 1 2 1 1
C. depends on wind velocity
D. can be increased by planting tall trees close to the tower
Calculate the maximum energy produced by a power plant when
the power plant is operated for 24 hours and the installed
capacity is 30 kW.
2 A. 420 KWh 1 2 1 1
B. 520KWh
C. 620KWh D. 720KWh
The primary distribution voltage range is reduced a
A.33 kV to 11 kV
3 B.66 kV to 33 kV 1 1 1 1
C.132 kV to 33 kV D.132 kV to 66 kV
In secondary transmission, electric power transmitted is
transmitted at 33kV by __________ overhead systems to
Various substations.
4 A.3 phase 2 wire 1 3 1 1
B.3 phase 3 wire
C.3 phase D.3 phase 4 wire
The cost of power generation is increased by
A. Selecting proper equipment of longer life and proper capacity
5 B. Carrying out proper maintenance 1 1 1 1
C. Running large sized generators
D. Increasing the efficiency of the plant
Part – B
(2 x 4 Marks = 08 Marks)
Instructions: Answer any two questions