Lesson 4.1 Volume by End Area and Prismoidal Formula
Lesson 4.1 Volume by End Area and Prismoidal Formula
Module 3. EARTHWORKS
• Course Outcome
• Solve and analyze earthwork quantities
EARTHWORKS
Lesson 4.1. Areas of Cross-section and Volumes
▪ Earthwork is a process that involves the movement of a portion of the earth’s
Learning Outcome surface from one location to another and in a new position.
Solve the cross-sectional area and the volume of earthworks
▪ In many engineering projects, earthwork involve the excavation, removal and
dumping of earth.
▪ Typical earthworks include road construction, railway beds, dams, levees, and
canals. Other common earthworks are land grading to reconfigure the
topography of a site, or to stabilize slopes.
EARTHWORKS EARTHWORKS
Earthwork volumes must be estimated:
▪ Earthwork is a process that
involves the movement of a a. to enable route alignment to be located at such lines and levels that cut and fill are
portion of the earth’s surface balanced as far as practicable;
from one location to another
and in a new position. b. to enable contract estimates of time and cost to be made for proposed work;
c. to form the basis of payment for work carried out
▪ Typical earthworks include
road construction, railway
beds, dams, levees, and
canals. Other common
earthworks are land grading
to reconfigure the
topography of a site, or to
stabilize slopes.
1
11/04/2024
Excavation (CUT) = the removal of soil or rock from its natural location.
Side View
Embankment (FILL)= the placement and compaction of layers of earth or rock to form a roadbed of the
planned shape, density, and profile grade.
Sta 0+000
2
11/04/2024
Side slope is defined as the slope of the cut or fill expressed as the ratio of horizontal
On a terrain with rough Side-hill section occurs when distance to vertical distance.
topography, it may require passing on side-hill locations.
five-level section.
( A1 + A2 ) L L
VE = VP = ( A1 + 4 Am + A2 )
2 6
3
11/04/2024
Solution:
Sample Problem 1. b. Prismoidal Sample Problem 1. Sta 4+000 Sta 4+020
Formula
Given: L
VP = ( A1 + 4 Am + A2 ) Given:
Left Center Right 6 Left Center Right
Sta 4+000
7.38 0 12.28 Sta 4+000
7.38 0 12.28
1.92 3.15 5.19 1.92 3.15 5.19
8.82 0 10.08 A2 8.82 0 10.08
Sta 4+020 Sta 4+020 z
2.88 2.52 3.72 2.88 2.52 3.72 x
y
Am = + + + VP =855.46 m 3
ATotal 2 = 38.664 m 2 2 2 2 2 ATotal 2 = 38.664 m 2
L = 20 m Am =42.753 m 2 L = 20 m
4
11/04/2024
b. Compute the value of x at station 4+020 if it c. Compute the volume between stations 4+000
Sample Problem 2. Sample Problem 2.
has a cross sectional area of 14.64 sq. m. and 4+020 using end area method
Given: Sta 4+000 Given: 2
2.30 1.5 3
Left Cente Right Left Cente Right 1 4 1.0
6.45 r0 4.50 3
2.6 6.45 r0 4.50
Sta 2.0 2 Sta 2.30S 3 3 1.0S
2.30 1.50 1.00 x
4 2.30 1.50 1.00
4+000 1 4+000 6.45 4.50
6.00 0 6.90 6.00 0 6.90
Sta 2.00 X 2.60 3.0 3.0 3.0 3.90S Sta 2.00 X 2.60
4+020 6 6.90 4+020 A=A1+ A2 + A3 + A4
A=A1+A2 +A3 +A4 Area at Sta 4+020 = 14.64
(3.0)(2.3) (6.45)(1.5) (1.5)( 4.5) (3.0)(1.0)
Computed Values: sq m A= + + + =13.1625 m 2
Computed Values: 2 2 2 2
(3.0)(2.0) ( x )(6.0) ( x )(6.9) (3.0)(2.6)
b=6m 14.64= + + +
2 2 2 2 b=6m
Side slope = ( A1 + A2 ) L (14.64+13.1625)(20)
Side slope = VE = = = 278.025 m 3
1:1.5 x = 1.2 m 2 2
1:1.5