0% found this document useful (0 votes)
408 views5 pages

Lesson 4.1 Volume by End Area and Prismoidal Formula

Uploaded by

Cahulogan Kate
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
408 views5 pages

Lesson 4.1 Volume by End Area and Prismoidal Formula

Uploaded by

Cahulogan Kate
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

11/04/2024

Module 3. EARTHWORKS
• Course Outcome
• Solve and analyze earthwork quantities

Lesson 4.1. Areas of Cross-section and Volumes


EARTHWORKS
Learning Outcome
Lesson 4.1. Areas of Cross-sections and Volumes
Solve the cross-sectional area and the volume of earthworks

EARTHWORKS
Lesson 4.1. Areas of Cross-section and Volumes
▪ Earthwork is a process that involves the movement of a portion of the earth’s
Learning Outcome surface from one location to another and in a new position.
Solve the cross-sectional area and the volume of earthworks
▪ In many engineering projects, earthwork involve the excavation, removal and
dumping of earth.

▪ Typical earthworks include road construction, railway beds, dams, levees, and
canals. Other common earthworks are land grading to reconfigure the
topography of a site, or to stabilize slopes.

EARTHWORKS EARTHWORKS
Earthwork volumes must be estimated:
▪ Earthwork is a process that
involves the movement of a a. to enable route alignment to be located at such lines and levels that cut and fill are
portion of the earth’s surface balanced as far as practicable;
from one location to another
and in a new position. b. to enable contract estimates of time and cost to be made for proposed work;
c. to form the basis of payment for work carried out
▪ Typical earthworks include
road construction, railway
beds, dams, levees, and
canals. Other common
earthworks are land grading
to reconfigure the
topography of a site, or to
stabilize slopes.

1
11/04/2024

Cross-sectional Area Cross-sectional Area

➢ The cross-sectional area is the area of a


two-dimensional shape that is obtained
when a three dimensional object - such as
a cylinder - is sliced perpendicular to some
specified axis at a point.

Cross-sectional Area CUT and FILL

Sta 0+000 Existing ground


surface
CUT
Top View
Proposed
Elevation
FILL

Excavation (CUT) = the removal of soil or rock from its natural location.
Side View
Embankment (FILL)= the placement and compaction of layers of earth or rock to form a roadbed of the
planned shape, density, and profile grade.

CUT and FILL Types of cross-sections


Existing ground surface
Sta 0+020
Proposed Elevation

Sta 0+000

Level section is suitable for Three-level section is generally


flat terrain. used where ordinary ground
condition prevails.

2
11/04/2024

Types of cross-sections Side slopes

Side slope is defined as the slope of the cut or fill expressed as the ratio of horizontal
On a terrain with rough Side-hill section occurs when distance to vertical distance.
topography, it may require passing on side-hill locations.
five-level section.

Volume of Earthwork Volume of Earthwork

1. End Area Method 2. Prismoidal Formula


- A simple formula for estimating volumes of - A prismoidal method is used when a more exact method of
solids determining earthwork volumes is warranted

( A1 + A2 ) L L
VE = VP = ( A1 + 4 Am + A2 )
2 6

Sample Problem 1. Sample Problem 1. Solution:


( A1 + A2 ) L
a. End Area VE =
2
Given:
Given the cross section notes below of the ground which will be excavated for a Sta
roadway, compute the volume of excavation between Sta 4+000 and 4+020 Left Cente Right 4+000 3
7.38 r0 12.28 2 5.19
using the (a) End Area Method and (b) Prismoidal Formula. The roadway is 9 m. Sta 1.92 1
3.15 4
1.92 3.15 5.19
wide with side slopes of 1.5:1. 4+000 4.5 4.5
8.82 0 10.08
Left Cente Right Sta 7.38 12.28
7.38 2.88 2.52 3.72
Sta r0 12.28
4+020
1.92 3.15 5.19
4+000 Road width= 9 m ATotal1 = A1 + A2 + A3 + A4
8.82 0 10.08 ( 4.5)(1.92) (7.38)(3.15) (12.28)(3.15) ( 4.5)(5.19)
Sta Side slope = 1.5:1 ATotal 1 = + + +
2.88 2.52 3.72 2 2 2 2
4+020
ATotal 1 = 46.962 m 2

Lesson 4.1. Areas of Cross-section and Volumes

3
11/04/2024

Sample Problem 1. Solution: Sample Problem 1. Solution:


( A1 + A2 ) L ( A1 + A2 ) L
a. End Area VE = a. End Area VE =
Given: 2 Given: 2
Left Cente Right Sta Left Cente Right
7.38 r0 12.28 4+020 3
3.72 7.38 r0 12.28 A2 Sta 4+020
Sta 2.88 2
2.52 4 Sta
1.92 3.15 5.19 1 1.92 3.15 5.19
4+000 4+000 L
4.5
8.82 0 10.08 4.5
8.82 0 10.08
Sta Sta A1 Sta 4+000
2.88 2.52 3.72 8.82 10.08 2.88 2.52 3.72
4+020 4+020
Road width= 9 m ATotal 2 = A1 + A2 + A3 + A4 Road width= 9 m
Side slope = 1.5:1 Side slope = 1.5:1 ( 46.962 + 38.664)(20)
L = (Sta 4+020) – (Sta 4+000) VE =
Computed Values: A Total2 = 11.1132 12.7008 8.37 Computed Values: 2
= 4020 – 4000
ATotal 1 = 46.962 m 2 6.48+ + 2 + ATotal 1 = 46.962 m 2 = 20 m
ATotal 2 = 38.664 m VE = 856.26 m 3
ATotal 2 = 38.664 m 2

Solution:
Sample Problem 1. b. Prismoidal Sample Problem 1. Sta 4+000 Sta 4+020

Formula
Given: L
VP = ( A1 + 4 Am + A2 ) Given:
Left Center Right 6 Left Center Right

Sta 4+000
7.38 0 12.28 Sta 4+000
7.38 0 12.28
1.92 3.15 5.19 1.92 3.15 5.19
8.82 0 10.08 A2 8.82 0 10.08
Sta 4+020 Sta 4+020 z
2.88 2.52 3.72 2.88 2.52 3.72 x
y

Side slope = Am Side slope =


Road width= 9 m Road width= 9 m 4.5 4.5
1.5:1 1.5:1
a b
Computed Values: A1 Computed Values:
ATotal 1 = 46.962 m
2
ATotal 1 = 46.962 m
2

ATotal 2 = 38.664 m 2 ATotal 2 = 38.664 m 2 1.92+2.88 3.15+2.52 5.19+3.72 7.38+8.82 12.28+10.08


x= y= z= a= b=
2 2 2 2 2
L = 20 m L = 20 m x =2.4 y =2.835 z=4.455 a=8.10 b=11.18

Sample Problem 1. Solution: Sample Problem 1. Solution:


b. Prismoidal
Mid-section
Given: 3
4.455 Given: Formula
Left Center Right 2.4
2 2.835 4 Left Center Right ATotal 1 = 46.962 m 2 A m =42.753 m 2
1
7.38 0 12.28 7.38 0 12.28 L = 20 m
Sta 4+000 Sta 4+000 ATotal 2 = 38.664 m 2
1.92 3.15 5.19 4.5 4.5
1.92 3.15 5.19
8.82 0 10.08 8.10 11.18 8.82 0 10.08
Sta 4+020 Sta 4+020 L
2.88 2.52 3.72 2.88 2.52 3.72 VP = ( A1 + 4 Am + A2 )
6
Road width= 9 mSide slope = Road width= 9 mSide slope =
20
1.5:1 1.5:1 VP = [ 46.962+( 4)( 42.753)+38.664]
Am =A1+A2 +A3 +A4 6
Computed Values: Computed Values:
ATotal 1 = 46.962 m
2
( 4.5)(2.4) (8.10)(2.835) (2.835)(11.18) ( 4.5)( 4.455)
ATotal 1 = 46.962 m
2

Am = + + + VP =855.46 m 3
ATotal 2 = 38.664 m 2 2 2 2 2 ATotal 2 = 38.664 m 2

L = 20 m Am =42.753 m 2 L = 20 m

4
11/04/2024

a. Compute the side slope of both


Sample Problem 2. Sample Problem 2. sections
Given the cross section notes of an earthwork between station Given:
2.30 1.5
4+000 and 4+020. Assume both stations to have the same side slope Left Cente Right 1.0

and width of the base. 6.45 r0 4.50


Left Cente Right Sta Sta 4+000 2.30S b/2 b/2 1.0S
2.30 1.50 1.00
6.45 r0 4.50 4+000 6.45 4.50
Sta 6.00 0 6.90
2.30 1.50 1.00 Sta
4+000 2.00 X 2.60 b
+ 2.30S= 6.45
6.00 0 6.90 4+020 2
Sta 2.00 X 2.60 b
+ 1.0S= 4.50
4+020 Unknown: width of the
2
a. Compute the side slope of both sections base b = 6 (width of the base)
b. Compute the value of x at station 4+020 if it has a cross sectional
area of 14.64 sq. m. s = 1.5
c. Compute the volume between stations 4+000 and 4+020 using
end area method.

b. Compute the value of x at station 4+020 if it c. Compute the volume between stations 4+000
Sample Problem 2. Sample Problem 2.
has a cross sectional area of 14.64 sq. m. and 4+020 using end area method
Given: Sta 4+000 Given: 2
2.30 1.5 3
Left Cente Right Left Cente Right 1 4 1.0

6.45 r0 4.50 3
2.6 6.45 r0 4.50
Sta 2.0 2 Sta 2.30S 3 3 1.0S
2.30 1.50 1.00 x
4 2.30 1.50 1.00
4+000 1 4+000 6.45 4.50
6.00 0 6.90 6.00 0 6.90
Sta 2.00 X 2.60 3.0 3.0 3.0 3.90S Sta 2.00 X 2.60
4+020 6 6.90 4+020 A=A1+ A2 + A3 + A4
A=A1+A2 +A3 +A4 Area at Sta 4+020 = 14.64
(3.0)(2.3) (6.45)(1.5) (1.5)( 4.5) (3.0)(1.0)
Computed Values: sq m A= + + + =13.1625 m 2
Computed Values: 2 2 2 2
(3.0)(2.0) ( x )(6.0) ( x )(6.9) (3.0)(2.6)
b=6m 14.64= + + +
2 2 2 2 b=6m
Side slope = ( A1 + A2 ) L (14.64+13.1625)(20)
Side slope = VE = = = 278.025 m 3
1:1.5 x = 1.2 m 2 2
1:1.5

You might also like