Lecture 26
Lecture 26
QUARTER 1
Jan. Feb. March
150,000 120,000 110,000
QUARTER 2
April May June
100,000 130,000 150,000
QUARTER 3
July Aug. Sept.
180,000 150,000 140,000
Aggregate Planning: Strategies
4. Subcontracting
• Requires customers to wait for an order without loss of goodwill or the order
• Most effective when there are few if any substitutes for the product or service
• Often results in lost sales
6,200
= = 50 units per day
124
Numerical Example
Forecast demand
Production rate per working day
70 –
Level production using average
monthly forecast demand
60 –
50 –
40 –
30 –
0 –
Jan Feb Mar Apr May June = Month
ê ê ê ê ê ê
22 18 21 21 22 20 = Number of
working days
Numerical Example Plan 1 – constant workforce
COST CALCULATIONS
Regular-time labor $ 75,392 (= 7.6 workers x $80 per day x 124 days)
40 –
30 –
0 –
Jan Feb Mar Apr May June = Month
ê ê ê ê ê ê
22 18 21 21 22 20 = Number of
working days
Numerical Example : Plan 3- Chase
TABLE 3 Cost Computations for Plan 3
BASIC
EXTRA COST OF EXTRA COST OF
DAILY PRODUCTION
FORECAST INCREASING DECREASING
MONTH PROD COST (DEMAND X TOTAL COST
(UNITS) PRODUCTION (HIRING PRODUCTION
RATE 1.6 HRS/UNIT X
COST) (LAYOFF COST)
$10/HR)
$1,200
Feb 700 39 11,200 — 12,400
(= 2 x $600)
$600
Mar 800 38 12,800 — 13,400
(= 1 x $600)
$5,700
Apr 1,200 57 19,200 — 24,900
(= 19 x $300)
$3,300
May 1,500 68 24,000 — 24,300
(= 11 x $300)
$7,800
June 1,100 55 17,600 — 25,400
(= 13 x $600)
60 –
50 –
40 –
30 –
0 –
Jan Feb Mar Apr May June = Month
ê ê ê ê ê ê
22 18 21 21 22 20 = Number of
working days
Comparison
MRP I
Master Production Schedule (MPS)
Production
Figure 14.1
Marketing Finance
Capacity Customer demand Cash flow The Planning Process
Inventory
Master production
schedule
Change master
production
Material schedule?
requirements plan
Schedule and
execute plan
1 B(2) C(3)
1 week
2 weeks to
D produce
B
2 weeks
E
A
2 weeks 1 week
E
2 weeks 1 week
G C
3 weeks
F
1 week
D
| | | | | | | |
1 2 3 4 5 6 7 8
Time in weeks
MRP Structure
MRP by period
BOM Master report
production schedule
MRP by date
report
Lead times
(Item master file) Planned order
report
Inventory data
Purchase advice
Material
requirement
planning programs
(computer and
software) Exception reports
Purchasing data
Order early or late or
not needed
Order quantity too
small or too large
Determining Gross Requirements
• From the BOM, every Item A requires 2 Item Bs – 100 Item Bs are
required in week 7 to satisfy the order release for Item A
• The lead time for Item B is 2 weeks – release an order for 100 units of Item
B in week 5
• The timing and quantity for component requirements are determined by
the order release of the parent(s)
• The process continues through the entire BOM one level at a time – often
called "explosion”
• By processing the BOM by level, items with multiple parents are only
processed once, saving time and resources and reducing confusion
• Low-level coding ensures that each item appears at only one level in the
BOM
Gross Requirements Plan
Gross Material Requirements Plan for 50 Products (As)
TABLE 3
with Order Release Dates Also Shown
WEEK
LEAD
1 2 3 4 5 6 7 8 TIME
A. Required date 50
Order release date 50 1 week
B. Required date 100
Order release date 100 2 weeks
C. Required date 150
Order release date 150 1 week
E. Required date 200 300
Order release date 200 300 2 weeks
F. Required date 300
Order release date 300 3 weeks
D. Required date 600 200
Order release date 600 200 1 week
G. Required date 300
Order release date 300 2 weeks
Net Requirement Plan
Gross + Allocations
requirements
Total requirements
Available inventory
Net Requirement Plan
ITEM ON HAND ITEM ON HAND
A 10 E 10
B 15 F 5
C 20 G 0
D 10
2 × number of As = 80
3 × number of As = 120
Net Requirement Plan
2 × number of Bs = 130
2 × number of Cs = 200
2 × number of Cs = 200
2 × number of Bs = 130
2 × number of Fs = 390
1 × number of Fs = 195
Determining Net Requirements
A S
B C B C
Master schedule
Lead time = 4 for A Lead time = 6 for S for B
Master schedule for A Master schedule for S sold directly
Periods 5 6 7 8 9 10 11 8 9 10 11 12 13 1 2 3
40 50 15 40 20 30 10 10
Periods 1 2 3 4 5 6 7 8
Therefore, these are
40+10 15+30
Gross requirements: B 10 40 50 20 the gross
=50 =45 requirements for B
MRP Planning Sheet
Lot-Sizing Techniques
1. Lot-for-lot technique orders just what is required for production based on net
requirements
1. May not always be feasible
2. If setup costs are high, lot-for-lot can be expensive
WEEK 1 2 3 4 5 6 7 8 9 10
Gross
35 30 40 0 10 40 30 0 30 55
requirements
Scheduled
receipts
Projected on
35 35 0 0 0 0 0 0 0 0 0
hand
Net
0 30 40 0 10 40 30 0 30 55
requirements
Planned order
30 40 10 40 30 30 55
receipts
Planned order
30 40 10 40 30 30 55
releases
Gross
35 30 40 0 10 40 30 0 30 55
requirements
Scheduled
receipts
Projected on
35 35 0 40 0 0 70 30 0 0 55
hand
Net requirements 0 30 0 0 10 0 0 0 55 0
Planned order
70 80 0 85 0
receipts
Planned order
70 80 85
releases