100% found this document useful (1 vote)
198 views

Lighting Control System Testing & Commissioning Procedure

The document outlines testing and commissioning procedures for lighting control systems. It details pre-commissioning checks like ensuring installation is complete and no damage occurred. Commissioning steps include manually overriding circuits, downloading software, testing programmed parameters, and checking communications and interlocks with other systems.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
198 views

Lighting Control System Testing & Commissioning Procedure

The document outlines testing and commissioning procedures for lighting control systems. It details pre-commissioning checks like ensuring installation is complete and no damage occurred. Commissioning steps include manually overriding circuits, downloading software, testing programmed parameters, and checking communications and interlocks with other systems.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

12/15/2017 Lighting Control System Testing & Commissioning Procedure

Lighting Control System Testing & Commissioning Procedure


 Webmaster  May 30, 2015  Electrical Method Statements, Testing & Commissioning  131 Views

The purpose of this procedure is to define the step by step method to implement the correct practices for

the precommissioning & commissioning of “Lighting Control System”through the guidelines contained

herein so as to ensure that the job execution complies with the project requirements and serves the
intended function to satisfactory level.

TOOLS / EQUIPMENT

Portable Hand tools


Advertisement
Step Ladder

Lap top PC with RS-232 cable

Precommissioning Procedure for Lighting Control System


1. 7.1. Ensure that the Lighting Control System devices & panels

installation are complete and mechanical completion is approved.

2. Ensure that no damage has occurred between mechanical

completion & pre-commissioning.

3. Repair / replace damaged components, if any.

4. Ensure the Lighting Control, Core Control modules & the panels are properly tagged & identified.

5. Ensure that the wiring termination to the Lighting control Panels are complete.
Check Also
6. Ensure that the cables are pretested for continuity before termination.

7. Ensure that the earthing of Lighting Control panel has been completed.

8. Ensure that installation of light fittings fed from lighting control panels/ modules are complete including
termination.

9. Ensure that the cable installation & termination is complete in all the LCMs, CCMs, dimming control,line
Method Statement For the
coupler, switches, area couplers and central battery system.
Installation of UPS System
10. Ensure the cables are secured well on to the connections to avoid system misbehavior dueand
Following tools to any loose
equipment shall be required
connection. for the installation of
Uninterrupted Power Supply
11. Ensure that dimmable ballast are installed in the light fixtures where dimmingUPS
of lights
… are required.

12. Ensure the lighting system computer is properly installed and the installation is approved.

http://safeworkmethodofstatement.com/lighting-control-system-testing-commissioning-procedure/ 1/4
12/15/2017 Lighting Control System Testing & Commissioning Procedure

13. Ensure the system software & the configuration parameters are available.

14. Ensure the lighting control system is interfaced with BMS & interlocked with fire alarm system.

Commissioning Procedure for Lighting Control System

1. Ensure that all the pre-commissioning checks are carried out successfully & are approved.

2. Manually override each circuit using the override ON/OFF switch provided for each circuit in the relay

output module.

3. Test the respective lighting circuits to be ON as per the approved electrical load schedule.

4. Switch ON the power supply to the lighting control panel (LCP) with system devices for each EIB bus line.

5. Check for the communication of all devices i.e. bus couplers, relay output modules/lighting control

modules, twilight switch, etc., with the LCP having the system devices i.e. power supply module.

6. Download the application software in each of the devices (bus couplers and actuator modules) via a note
book PC connected to the RS-232 interface module.

7. Download the application software to the line couplers located in the LCP with system devices & check for
the communication between the line couplers.

8. Test the software loops as per the programmed parameters.

9. Switch ON & OFF the individual gang of the push button switches installed (wherever applicable) & check

that the respective programmed circuits are switched ON & OFF accordingly.
Check Also
10. Remove the communication bus cable from the power supply module feeding the bus devices & check for
the response of the individual actuators to work in the ‘fail safe’ mode (ON/OFF/As it is now programmed

for AS IT IS mode).

11. Switch ON the power supply for the standalone operation of the lighting control system.

12. Program the TP controller located in the control room to switch ON & OFF the individual groups as
programmed & check the respective programmed circuits are switched ON & Method Statement For the
OFF accordingly.

Installation
13. Edit the programmed TP-controller if required & then check for the response of UPS System
of the individual devices &
individual circuits. Following tools and
equipment shall be required
for the installation of
14. Program the timer groups of the TP controller as per project requirements forUninterrupted
the standalonePower
operation of
Supply
UPS …
the lighting control system.

http://safeworkmethodofstatement.com/lighting-control-system-testing-commissioning-procedure/ 2/4
12/15/2017 Lighting Control System Testing & Commissioning Procedure

15. Check for the communications of the line couplers from the lighting PC located in the Central Control
Room.

16. Check floor plans on the lighting graphics as per the as built drawings on the lighting PC located in the
Central Control Room.

17. Check the lighting circuits/luminaries status (ON/OFF) in each floor plan graphics.

18. Manually over ride (light ON/OFF) the lighting circuits through textual graphics on the PC & verify the
lighting circuits status i.e., the color of the lighting fixture is changing or not in the floor plan graphics.

19. Check the lighting circuits switch ON/OFF timings schedule on the lighting PC.

20. The interlock of the lighting system with the fire alarm system shall be checked. It shall be ensured all the
emergency lighting circuits are switched ON in case of fire signal.

21. The interface between the Lighting control system & the BMS system shall also be checked by triggering a

lighting circuit from the BMS work station.

Attachments:

Pre-commissioning check sheet for Lighting Control System

Commissioning check sheet for Lighting Control System

Risk Assesment

Advertisement

Check Also

Like Share 3 people like this. Sign Up to see what your friends like.

Join for latest Articles:

Enter your email address:

Method Statement For the


Installation of UPS System
Subscribe Following tools and
equipment shall be required
Delivered by FeedBurner for the installation of
Uninterrupted Power Supply
UPS …

Related Method Statements:

http://safeworkmethodofstatement.com/lighting-control-system-testing-commissioning-procedure/ 3/4
12/15/2017 Lighting Control System Testing & Commissioning Procedure

Method Statement For Testing & Commissioning Of Light…

METHOD STATEMENT FOR PRECOMMISSIONING & COMMISSIONING…

Method Of Statement For Installation of Lighting Control…

Method Statement For Testing & Commissioning Of…

Share this method statement:

Share 3 Share

Method Statement For Testing & Commissioning


Of Light Fittings & Fixtures
Below is a complete method statement for
testing and commissioning of Light Fittings as
required by the project requirements and light
fittings serve the intended function to
satisfactory level and achieve the required
In "Electrical Method Statements"

METHOD STATEMENT FOR PRECOMMISSIONING Method Statement For Fluke Testing &
& COMMISSIONING OF CENTRAL BATTERY Commissioning Of Telephone Data System
SYSTEM In "Electrical Method Statements"
In "Electrical Method Statements"

Check Also

Method Statement For the


Installation of UPS System
Following tools and
equipment shall be required
for the installation of
Uninterrupted Power Supply
UPS …

http://safeworkmethodofstatement.com/lighting-control-system-testing-commissioning-procedure/ 4/4

You might also like