Performance Re-Qualification Octagonal Blender
Performance Re-Qualification Octagonal Blender
OF
OCTAGONAL BLENDER
NAME OF THE EQUIPMENT : Octagonal Blender
EQUIPMENT NO. :
RQ PROTOCOL NO. :
RQ REPORT NO. :
MAKE :
CAPACITY :
LOCATION :
TABLE OF CONTENTS
S. No. TITLE PAGE No.
1.0 Pre Approval 3
Overview 4-5
2.1 Purpose 4
2.0 2.2 Background 4
2.3 Responsibility 4
2.4 Equipment Description 5
Performance Re-Qualification Procedure 6 -10
3.1 Training 6
3.0 3.2 Equipment Identification 6
3.3 Verification of Performance of the Octagonal Blender 7
3.4 Deviation and Corrective Action 10
4.0 Acceptance criteria 12
5.0 Summary and conclusion 12
6.0 Post approval signature 12
Appendix 13
7.0 7.1 Abbreviation 13
7.2 List of Document 13
JSA VALIDATION SERVICES
BADDI, H.P-BHARAT (INDIA)
1.0 PRE-APPROVAL
Prepared by
Reviewed by
Approved by
Authorized by
JSA VALIDATION SERVICES
BADDI, H.P-BHARAT (INDIA)
2.0 OVERVIEW
The Performance Re-Qualification of Octagonal Blender is carrying out in order to provide the high
degree of assurance that the equipment performed as intended and remain in the state of control.
2.1 PURPOSE
The purpose is to provide an outline for the Performance Re-Qualification of equipment for
performance attributes to verify that:
• The system meets the user requirement Specification.
• Document the verification that equipment performs consistently and in the state of control.
• Assure that Octagonal Blender is adequate to support the process for which the system is intended.
2.2 BACKGROUND
The Octagonal Blender supplied by Falcon Machineries; Equipment I.D. XXXX installed in Blending
area at XYZ (Company Name). This protocol defines the methods and documentation that shall be
used to evaluate the performance attributes of Octagonal Blender in accordance with the user
requirement specifications and intended use. The Reason for this requalification is Periodic/Schedule
Performance Requalification.
2.3 RESPONSIBILITIES:
2.3.1 Quality Assurance:
• To prepare/Review and Approval of the Performance Re-Qualification protocol and report.
• To Impart the Training to the team before the execution of protocol
• To execute the Performance Re-Qualification protocol along with other department
• To monitor protocol completeness and technical accuracy.
2.3.2 User Department
• To Review of the Performance Re-Qualification Protocol/Report.
• To monitor the validation activities and ensuring performance attributes as per the protocol.
• To monitor protocol completeness and technical accuracy.
• To review the data and approved the qualification procedure, if found satisfactory.
• To provide personnel to assist in the execution of the protocol/report.
JSA VALIDATION SERVICES
BADDI, H.P-BHARAT (INDIA)
• If the observed deviation does not have any major impact on the qualification the final conclusion
shall be provided.
• If the observed deviation has major impact on the qualification, deviation shall be reported to the
manufacturer for the corrective action and qualification activity shall be done.
3.1 Training
The validation team member shall be trained on the protocol execution of validation activity and report
compilation.
Capacity
Blender RPM
I.D. No.
Sr, No.
Model
Equipment Location
Facility
Area
PRODUCT NAME__________________________________________________
Comments:…………………………………………………...….……………………..………………
………………………………………………………………………………………………………
D1 Discharge Port
Composite Composite
JSA VALIDATION SERVICES
BADDI, H.P-BHARAT (INDIA)
Executed by
Reviewed by
Approved by
Authorized by
JSA VALIDATION SERVICES
BADDI, H.P-BHARAT (INDIA)
7.0 APPENDIX
7.1 ABBREVIATIONS
Kg : Kilogram
END OF DOCUMENT