2) Piping Installation Check List
2) Piping Installation Check List
2) Piping Installation Check List
Date: 29/04/2024
Contract Title: TWRP C3C - Domestic Liquids Modules - Civil and Building Services Works
Contractor: Sino Hydro Corporation Limited
RFIW Ref No.: 131233-WSW33-RN-K-5632
Line no.: ☐ ☐ ☐
Check Isometric / shop drawings against
P&ID’s are of latest revisions
☐ ☐ ☐
Check all items installed as per shop drawings
/ P&ID
☐ ☐ ☐
Check that the correct bolts / nuts / washers
and gaskets are installed at all mechanical ☐ ☐ ☐
joints
Check valves installed flow direction is correct ☐ ☐ ☐
Check all pipe supports/saddle support/valve
supports/U bolts /thrust blocks are completely
installed as per drawings and pipe support Std ☐ ☐ ☐
/ Spec. etc. schedule-additional supports may
be required – refer to standard drawings
Bolts for flanged or other mechanical joints
shall show two threads clear off the nut after ☐ ☐ ☐
tightening
Nuts tightened to the torque recommended by
joint manufacturer
☐ ☐ ☐
Acid cleaning on stainless steel weldment ☐ ☐ ☐
completed (Site Joints)
Pipe and pipe support contact between
dissimilar metals isolation done
☐ ☐ ☐
Pipes properly rest on the supports (No gap
between pipe and support) ☐ ☐ ☐
Flexible joints/Mechanical couplings Tie bolts
installed
☐ ☐ ☐
No welding joints and socket weld connections ☐ ☐ ☐
are on beam support
Tag plates on pipe spools are removed ☐ ☐ ☐
(Identification from shop)
All temporary supports removed ☐ ☐ ☐
Facility provided for draining the pipe system
and releasing air
☐ ☐ ☐
1
Flow meter, PIT, PRV. AVRV, Analyzers & etc. ☐ ☐ ☐
Installed as per drgs (or) tapping provided for
installation
Check all chain wheels for specified valves
have been installed
☐ ☐ ☐
Check the valves are fully operation,
accessible and the extended spindles are not ☐ ☐ ☐
damaged
Check the pipework Elevation / slope is
adequate and as indicated on the P&ID ☐ ☐ ☐
Check pressure gauge calibration is correct
and calibration certificate is current (Permeant ☐ ☐ ☐
if applicable)
Pipeline tie in requirement/location as per
drawings
☐ ☐ ☐
Check that all pipes/Valves are labelled and/or
painted colour code correctly/ Flow direction ☐ ☐ ☐
marked
Remarks: