Latihan Modul 5

The document contains inventory information for components used in a product including part numbers, quantities, safety stock levels, and forecasts. It also includes MRP schedules showing gross requirements, scheduled receipts, and net requirements for each component on a monthly basis.

Uploaded by

sasilawatisari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
52 views9 pages

Latihan Modul 5

The document contains inventory information for components used in a product including part numbers, quantities, safety stock levels, and forecasts. It also includes MRP schedules showing gross requirements, scheduled receipts, and net requirements for each component on a monthly basis.

Uploaded by

sasilawatisari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 9

BOM Safety

No. Component Name Code Part No Quantity Level On Hand


UOM Stock
1 Switch S 42 1 Piece 1 251 243
2 Body Assembly BA 43 2 Pieces 1 208 200
3 Green LED Indicator GL 44 1 Piece 1 205 190
4 PCB P 45 2 Pieces 2 216 243
5 Standard 3.5mm Jack SJ 46 1 Piece 2 185 210
6 Left Speaker LS 47 1 Piece 3 231 245
7 Right Speaker RS 48 1 Piece 3 161 181
8 Battery BA 49 2 Pieces 3 644 702
9 Amplifier A 50 50 Pieces 3 32,200 35,000

Item No : 1 Item No :
Lead Time : 1 Safety Stock:
On Hand : 341 DTF
Lot Size : 1 PTF
Period Past Due Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
Forecast 2,771 2,653 3,612 3,800 2,653 3,773
Customer Order 2,588 3,006 3,039 3,738 3,709 3,388
Projected Available Balance 341 789 789 789 789 789 789
Available to Promise 341 789 789 789 789 789 789
Master Schedule 3,036 3,006 3,039 3,738 3,709 3,388
Holding Schedule PORec (FP on
Lot Size Lead Time Setup Cost Order Policy PORel
Cost Period Unit Jan-22)
35 1 15 6 6 1,825 Silver-Meal Heuristic Dec-21 Nov-21
20 3 20 9 0 0 Lot for lot Dec-21 Nov-21
35 1 25 5 5 1,792 Silver-Meal Heuristic Nov-21 Oct-21
25 3 30 7 0 0 Lot for lot Nov-21 Oct-21
20 2 25 10 0 0 Lot for lot Oct-21 Sep-21
20 1 26 5 9 1,784 Silver-Meal Heuristic Oct-21 Sep-21
40 2 40 9 1 1,789 Wager Within Sep-21 Aug-21
50 1 15 5 6 1,939 Least Unit Cost Sep-21 Aug-21
100 1 10 2 5 150,452 Wager Within Sep-21 Jul-21

tem No : Speaker
Safety Stock: 789
DTF 6
PTF 6
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Des-21
3,981 2,583 3,861 3,276 3,371 3,587
3,696 3,901 3,269 2,960 3,761 3,953
504 789 197 473 789 789
789 1,074 1,074 1,666 1,982 1,982
3,696 4,186 3,269 3,552 4,077 3,953
Master Production Scheduling : Speaker

MPS Finished Product


Period Past Due Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21
Master Schedule 3,036 3,006 3,039 3,738 3,709 3,388 3,696 4,186
PORel 3,036 3,006 3,039 3,738 3,709 3,388 3,696 4,186 3,269

MRP Switch
Part No : 42 Description :
Quantity : 1 Safety Stock :
BOM UOM : piece Lot Size :
Level : 1 Lead Time :
On Hand : 251 Order Policy
Past Due 1 2 3 4
Period
Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
Gross Requirement
Scheduled Receipt
PAB1
Net Requirement
Planned Order Receipt
Planned Order Release
PAB2

MRP Body Assembly


Part No : 43 Description :
Quantity : 2 Safety Stock :
BOM UOM : pieces Lot Size :
Level : 1 Lead Time :
On Hand : 208 Order Policy :
Past Due 1 2 3 4
Period
Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
Gross Requirement
Scheduled Receipt
PAB1
Net Requirement
Planned Order Receipt
Planned Order Release
PAB2

MRP Green LED Indicator


Part No : 44 Description :
Quantity : 1 Safety Stock :
BOM UOM : piece Lot Size :
Level : 1 Lead Time :
On Hand : 205 Order Policy :
Past Due 1 2 3 4
Period
Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
Gross Requirement
Scheduled Receipt
PAB1
Net Requirement
Planned Order Receipt
Planned Order Release
PAB2

MRP PCB
Part No : 45 Description :
Quantity : 1 Safety Stock :
BOM UOM : piece Lot Size :
Level : 2 Lead Time :
On Hand : 216 Order Policy :
Past Due 1 2 3 4
Period
Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20
Gross Requirement
Scheduled Receipt
PAB1
Net Requirement
Planned Order Receipt
Planned Order Release
PAB2

MRP Standard 3.5mm Jack


Part No : 46 Description :
Quantity : 1 Safety Stock :
BOM UOM : piece Lot Size :
Level : 2 Lead Time :
On Hand : 185 Order Policy :
Past Due 1 2 3 4
Period
Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20
Gross Requirement
Scheduled Receipt
PAB1
Net Requirement
Planned Order Receipt
Planned Order Release
PAB2
Sep-21 Oct-21 Nov-21 Des-21
3,269 3,552 4,077 3,953
3,552 4,077 3,953 0

escription : Switch
afety Stock : 243
ot Size : 35
ead Time : 1
rder Policy : Silver-Meal Heuristic
5 6 7 8 9 10 11 12
Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21

bly
escription : Body Assembly
afety Stock : 200
ot Size : 20
ead Time : 3

Level 1
rder Policy : Lot for lot
5 6 7 8 9 10 11 12
Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Level 1

dicator
escription : Green LED Indicator
afety Stock : 190
ot Size : 35
ead Time : 1
rder Policy : Silver-Meal Heuristic
5 6 7 8 9 10 11 12
Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21

escription : PCB
afety Stock : 243
ot Size : 25
ead Time : 3
rder Policy : Lot for lot
5 6 7 8 9 10 11 12
Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21

Level 2
m Jack
escription : Standard 3.5mm Jack
afety Stock : 210
ot Size : 20
ead Time : 2
rder Policy : Lot for lot
5 6 7 8 9 10 11 12
Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21