CAV 2000 Series Automatic Viscometer Installation Qualification Procedure

Customer: ____________________________ Location: ___________________ Bath _____ of _____


CAV2000 s/n: ________ Service Unit s/n: _________ Date: _________ Technician: ___________
Visc Tube 1 s/n: _________ Range: ____________ Visc Tube 2 s/n:_____________ Range: __________

Date or N/A Component Change Reason


___________ (A) Stack __________________________________________________
___________ (B) Valve Tray __________________________________________________
___________ (C) Pneumatic Drawer __________________________________________________
___________ (D) Tube # ______ __________________________________________________

Procedure Initials Date 2nd  Date if


Change A-D
PREINSTALLATION:
1. Electrical Power (as specified by user)

2. Compressed Air/Nitrogen (Clean, Dry, Line Pressure set to 75-100 psi)

3. Sample/Waste Disposal (Customer supplied)

4. Cooling Water (For Instruments maintaining bath temperature below 40C)

5. Ventilation (Customer supplied as required)

6. Laboratory Environment (temperature, all safety features as required by customer)

7. Installation Area (Determined by number of units to be installed)

8. Instrument Clearance(Ceiling 68” or more above pedestal or bench top)

9. Tools for installation (Customer supplied 6’ step ladder, hammer, crowbar)

10. Solvent (Customer supplied to be compatible with material being tested)

11. Computer (If not purchased with unit contact Cannon for specifications)

INSTALLATION:
12. 80°C general offset entered

13. Over-temp potentiometer set to _____ °C. A

14. Current temperature offset entered for ________ °C or °F A

15. Check for leaks in all baths and airlines. BCD

16. Verify service unit voltage, frequency, and correct vacuum pump.

17. Solvent tanks work correctly and solvent lines plumbed correctly.

18. Check for solvent leaks. B

19. Make certain transformer strapped correctly and bolted down.


CAV 2000 Series Automatic Viscometer Installation Qualification Procedure
Procedure Initials Date 2nd  Date if
Change A-D
20. Check head unit for loose wires, cables, and proper crimps.

21. Check rear of unit for loose wires, cables, and proper crimps.

22. Parts secured properly - Power supplies, transformers, etc.

23. Swagelok and poly-flo fittings tightened properly. B

24. Instrument configured as ___DUAL or ___SINGLE solvent D

25. Instrument configured as ___LOW or ___HIGH temperature D

26. VISCPRO software Version __________

PASS [ ] FAIL [ ]
The following certified person completed the manufacturer’s procedure for the proper Installation
Qualification of this instrument:

Name: __________________________________
Title/Affiliation: ____________________________
Signature: ________________________________
Date: _______________