Chapter 7 - Reducing Project Duration
Chapter 7 - Reducing Project Duration
Chapter 7 - Reducing Project Duration
Chapter Outline
3 4
9.1 Rationale for Reducing Project Duration 9.2 Options for Accelerating Project Completion
• Crash is a term that has emerged in the project management lexicon for • Resources Are Not Constrained • Resources Are Constrained
shortening the duration of an activity or a project beyond when it normally can
- Add resources - Improve project team efficiency
be done.
- Outsource project work - Fast tracking
- Schedule overtime - Use critical-chain management
• Reasons for attempting to reduce the duration of a project are:
- Establish a core project team - Reduce project scope
- Time-to-market pressures
- Unforeseen delays - Do it twice—fast and correctly - Compromise quality
• FIGURE 9.1
7 8
• The project cost-duration graph is used to compare additional cost • Which activities to shorten?
alternatives for benefits. • Look for critical activities that can be shortened with the smallest increase in cost
per unit of time.
• Assumptions:
• Three major steps are required to construct a project cost-duration graph:
1. The cost-time relationship is linear.
1. Find total direct costs for selected project durations.
2. Normal time assumes low-cost, efficient methods to complete the activity.
2. Find total indirect costs for selected project durations.
3. Crash time represents a limit—the greatest time reduction possible under
3. Sum direct and indirect costs for these selected durations. realistic conditions.
4. Slope represents cost per unit of time.
5. All accelerations must occur within the normal and crash times.
9 10
11 12
15 16
• FIGURE 9.6
17