Training Module For NGCP External Customers - MTD
Training Module For NGCP External Customers - MTD
EXTERNAL CUSTOMERS
OUTLINE
Alberto C. Baritua
1 RESOURCE
SPEAKER
Power System Theory and
Application
Senior Manager
MTD-B SLOM
Grounding Resistor
R Connected to the starpoint of a
generator or transformer to limit the
line-to-ground fault current
AC Generator
A machine that produces AC power
(from mechanical to electrical energy)
when driven by a prime mover
Electrical Schematics
52 Circuit Breaker
A device designed to open a circuit
under normal/abnormal conditions
Disconnect Switch
A device that isolates equipment from
buses or live apparatus, sectionalizes
buses or circuits
Grounding Switch
Operates in tandem with the ordinary
line DS with the primary purpose of
grounding a T/L after opening the
ordinary DS. It is designed not to be
closed when the ordinary DS is at close
position
Electrical Schematics
DISTRIBUTION
LO
AD
BREAKERS BUS
FAULT ANALYSIS AND CLEARANCE
SYSTEM
Fault Clearance System
Basic Principles in Power System
• Line-to-line fault
FAULT ANALYSIS
Controls:
• Flow
• Pressure
Protective Measures:
• Pressure Relief valves
• Flow Control valves
Controls:
• Frequency
• Voltage
• Current
Controls:
• Frequency
• Voltage
• Current
Protective Measures:
• MW / MVAR / Frequency Regulator
• MLD / ALD / SIPS
• Surge & Lightning Arresters
h∝P Voltage ∝ Pressure
P ∝ ρ*g*h
Where:
P = Pressure
ρ = Density of water
g = acceleration due to gravity
h = height
Where:
V = Voltage (kV)
Isc = Short circuit current (kA)
MVAsc = MVA short circuit (MVA)
What if :
1. Tank bursts = Water totally spilled
2. Grid failed = Power loss
Short circuit of the Grid such as:
*Line – Ground Fault,
*Line – Line Fault,
results to the MVA capacity to discharge to the ground due to
lesser impedance. In which case, there will be no MVA capacity
left for the load.
Bicol
G
350 kVDC, 2 Lines, 1000 mm2
Oil-filled Submarine Cable
Samar
Panay
G
Cebu
Negros
Bohol
MINDANAO
LUZON-VISAYAS INTERCONNECTION
21 432
circuit kilometers of Circuit kilometers of
submarine cable overhead wires
MINDANAO-VISAYAS
INTERCONNECTION
184 422
Dumanjug, circuit kilometers of Circuit kilometers of
Cebu submarine cable overhead wires
Santander, Cebu
Lala, Lanao
del Norte
HVDC Major Components
DC TRANSMISSION LINES
* DC OVERHEAD LINES
* DC SUBMARINE CABLES
ELECTRODE STATION
CABLE TERMINAL STATION
HVDC Major Components
A. POWER TRANSFORMER
1. Insulation Resistance (5KV DC)
2. Insulation Power Factor (10KV AC)
3. Turns ratio
4. Winding resistance
5. Excitation
Circular No. 2008-0017: Guidelines on the Processing of OATS Applications
Effectivity Date: 01 July 2008
OLTC test
8.1 Tap check / Ripple test (Per phase)
9. Calibration of Temperature Monitoring Device
Circular No. 2008-0017: Guidelines on the Processing of OATS Applications
Effectivity Date: 01 July 2008
C. CURRENT TRANSFORMER
1. Insulation Resistance (DC)
2. Insulation Power Factor (AC)
3. Ratio and Phase Deviation (High Current at100% or
10% rated current)
4. Excitation/Saturation (Full tap)
Circular No. 2008-0017: Guidelines on the Processing of OATS Applications
Effectivity Date: 01 July 2008
D. POTENTIAL TRANSFORMER
1. Insulation Resistance (DC)
2. Insulation Power Factor (AC)
3. Ratio and Phase Deviation
E. LIGHTNING ARRESTER
1. Insulation Resistance (5KV DC)
2. Insulation Power Factor (10KV AC)
Circular No. 2008-0017: Guidelines on the Processing of OATS Applications
Effectivity Date: 01 July 2008
F. DISCONNECT SWITCH
1. Insulation Resistance (5KV DC)
2. Contact Resistance (High Current, at least 10%
current rating
I. GROUNDING SYSTEM
1. Earth / Soil Resistance
2. Ground Grid Integrity @ 300A AC
J. CAPACITOR BANK
1. Capacitance
2. Insulation Resistance
Circular No. 2008-0017: Guidelines on the Processing of OATS Applications
Effectivity Date: 01 July 2008
K. REACTOR
a. Insulation Resistance (5KV DC)
b. Insulation Power Factor (10KV AC)
c. Winding Resistance
d. Insulating Oil Tests
4.1 Dielectric Breakdown Voltage
4.2 Insulation Power Factor
e. Calibration of Temperature Monitoring Device
QUIZ!!! Enumerate the
minimum test
requirements for each
HVE in the Single Line
Diagram mandated
under OATS 2018-
00017
Part 2 –Introduction to the
importance of High Voltage
Equipment Tests
WHY PERFORM
ELECTRICAL TEST?
WHY PERFORM ELECTRICAL TEST?
Factory Test
1. Manufacturing stage
2. After manufacture – Finish product
3. Before delivery
63
TYPES OF TEST
Field Test
1. Acceptance Tests
2. Routine or Maintenance Tests
3. Special Tests
BASIC INSULATION
THEORY
What is an Insulation?
A material or a
combination of
Non-Conducting
Materials that
provides Electrical
Isolation of two
parts of different
voltages.
What is Dielectric?
Dielectric is a
material with
insulating
properties, it is
either gaseous,
solid or liquid
property.
What causes Insulation Failure?
Overheating
Moisture
What causes Insulation Failure?
Dirt/Contamination
Aging
What is the Purpose of Insulation Testing?
IT
C
DC VOLTAGE
SOURCE
RL IRC
IR
What are the three types of Test Currents during
Insulation Resistance Testing?
CAPACITANCE
CHARGING CURRENT
MICROAMPERES
TOTAL CURRENT
CURRENT IN
CONDUCTION ABSORPTION
OR LEAKAGE CURRENT
CURRENT
5 10 15 25
TIME IN SECONDS
What are the characteristics of a
Good DC Insulation?
Ѳ
E
100% PF
I
What is a Power Factor?
IC IT
δ
= COS Ѳ
Ѳ IR
=
E IT
I
What is a Power Factor?
S, Z P
Q,C δ
=
S
Ѳ R
=
E
Z
P, R
What are the two types of Test Currents during
Power Factor Testing?
IT
IC
IR
HIGH VOLTAGE
AC SOURCE
CP RP
IT
IC δ
ø
E
IR
What is a Dissipation Factor?
IT
IC δ = Tan δ
IR
Ѳ =
E IC
IR
What is a Dissipation Factor?
IT P
Q,C δ =
Q
R
Ѳ =
E C
P,R 84
COMPARISON OF PERCENT POWER
FACTOR AND DISSIPATION FACTOR
%PF %DF
Ѳ δ
(% COS) (% tan)
90 0 0 0
89.71 0.50 0.29 0.50
87.13 5.00 2.87 5.00
84.26 10.00 5.74 10.05
COMPARISON OF PERCENT POWER
FACTOR AND DISSIPATION FACTOR
%PF %DF
Ѳ δ
(% COS) (% tan)
81.37 15.00 8.63 15.18
53.13 60.00 36.87 75.00
45.00 70.71 45.00 100.00
0 100 90 Infinity
Why POWER FACTOR?
IC3 IT3 300 MVA
IT1 5 MVA
IC1 Ѳ
STOP GOOD
FAILED
DC Testing on Series Insulation
FAILED
FAILED
DC Testing on Series Insulation
FAILED
HIGH VOLTAGE
FAILED
DC SOURCE
FAILED
AC Testing on Series Insulation
C = 100pF 0.5 % PF
GOOD
GOOD
FAILED
PFA = 0.5+2.0+2.0
= 1.5%
3
CT = 50pF
DC Testing on Parallel Insulation
STOP STOP
HIGH VOLTAGE
DC SOURCE GOOD GOOD
FAILED
AC Testing on Parallel Insulation
PFA = 0.5+0.5+0.5
3 = 0.5% CT = 100+100+100 = 300pF
AC Testing on Parallel Insulation
PFA = 0.5+1.5+0.5
= 0.83% CT = 100+200+100 = 400pF
3
QUESTION!!!
On-Line
Test Methods
Off-Line Test Methods
Power Transformer
1. Winding Resistance Test
2. Turns Ratio Test
3. Insulation Resistance Test
▪ Spot Test
▪ Dielectric Absorption
Ratio
▪ Polarization Index
4. Insulation Power Factor
Test
▪ Bushing (C1 & C2)
▪ Overall (Winding)
5. Excitation Current Test
Off-Line Test Methods
Power Transformer
7. Oil Test
▪ Oil Dielectric
Breakdown Voltage
Test (ODBV)
▪ Moisture Content
Test
▪ Oil Power Factor
Test
▪ Dissolved Gas
Analysis (DGA) Test
Off-Line Test Methods
Power Transformer
8. Ripple Test
9. Short Circuit
Impedance Test
10.Bushing Current
Transformer
▪ Winding Resistance
Test
▪ Ratio & Polarity
Test
▪ Saturation Test
Key Risk Areas
Power Transformer
1. Bushing Current
Transformer
▪ Open Secondary Circuit
▪ Parallel Secondary Circuit
▪ Double Grounding
▪ Core Characteristics
▪ Cable Tagging
▪ Tightness of Sec.
Terminals
▪ Left Overhead Strands
4. Electromechanical
devices
5. Terminal box and
Local Control Cubicle
6. Cooling system
7. Bushing
Off-Line Test Methods
Current Transformer
1. Improper Connections
2. Tightness
3. Ground Grid Integrity
and Soil Resistivity
On-Line
High Voltage Equipment Test Methods
Infrared Thermal
Scanning
115
On-Line
High Voltage Equipment Test Methods
Partial Discharge
(PD) Monitoring
UV Corona Imaging
On-Line
High Voltage Equipment Test Methods
Oil Analysis
On-Line
High Voltage Equipment Test Methods
Leakage Current
Monitoring on LA’s
Ground Grid
Integrity Test
Part 4 – General Safety
Precautions
High Voltage Safety Tips
1. Ensure that only authorized employees work around high
voltage equipment.
2. Be careful around output circuits even when the input
power is off. Parallel power sources and energy storage
devices can still be dangerous.
3. Be careful when working with power supplies that serve
more than one area.
4. Before working in a high voltage area,
inspect the power supply and check
all protective devices.
“Talk less, do your job safely. Say
no to carelessness!”
Before Testing and Maintenance
1. All personnel must attend the toolbox meeting;
2. No Work Permit, No Work policy;
3. Check if power circuit breaker and disconnect switches
are in open position;
4. Check if grounding clusters are already connected to
line/equipment;
5. Install caution tapes and safety signs to partition working
areas;
6. Ground power equipment before making test connection
(This is to drain high voltage charge that may still be
present in the equipment).
“Talk less, do your job safely. Say no to carelessness!”
During Testing and Maintenance
1. Only authorized personnel/workers must be in the work
place;
2. Be sure that all grounding clusters are properly connected;
3. Horse playing is not allowed;
4. Use the proper tools when loosening or tightening bolts and
nuts
5. Verify if there are other groups working on the equipment.
CURRENT TRANSFORMER
PT / CVT
LIGHTNING ARRESTERS
OUTLINE
• Protection System
• Overcurrent Protection
• Differential Protection
• Minimum Requirements with the OATS
Rule
PROTECTION SYSTEM
Devastated Line and
Substation Equipment
Protection
Protection
Excerpts from Mason’s book “ The Art and Science of Protective Relays”
What
What is thePurpose
is the Purpose ofProtective
of the the Protective
Relaying?
Relaying?
Relay
Current/potential
Transformer
Circuit Breaker
Current Transformer
Trip Coil
Station
Battery
Relay Contacts
Components and
Components and Importance
Importance of System
of Protection
Protection Sytem
Purpose of Protection
•Detect abnormal conditions
•Overload
•Short-Circuit
•Isolate faulty part of the system
Types of Overcurrent Protection
Fuses
• Simple
• Can provide very fast fault clearance
• Less than 10ms for large fault current
• Limit fault energy
Arcing Time
Pre-arc Time
Prospective Fault Current
t
Total Operating
Time
Types of Overcurrent Protection
Fuses - Disadvantages
• Issues on coordination
• Limited sensitivity to earth faults
• Single phasing
• Fixed characteristic
• Need replacing following fault clearance
Difference of Relay over Fuse:
Relay
50 IF2 50 IF1
Types of Overcurrent Protection
• Problem
• Relies on there being a difference in fault level between
the two relay locations
• Cannot discriminate if IF1 = IF2
50 IF2 50 IF1
Types of Overcurrent Protection
51 51
51 51
• Problem
• Longest operating time is at the source where fault level is
highest
Types of Overcurrent Protection
IS APPLIED CURRENT
(RELAY CURRENT SETTING)
Discrimination by both “time” and “current”. The relay operation time is inversely
proportional to the fault current.
Types of Overcurrent Protection
• Electronic, multi-characteristic
• Fine settings, wide range
• Integral instantaneous elements
Types of Overcurrent Protection
I>2
TIME
I>3
I>4
CURRENT
• Relay Characteristics
• Relay Current Setting
• Grading Margin
• Time Multiplier Setting
O/C Relay Characteristics
IEC Characteristics
0.14
• SI t = TMS
M0.02 −1
13.5
• VI t = TMS
M −1 LTI
80
• EI t =TMS SI
M2 −1
120 VI
• LTI t =TMS
M−1 EI
R1 R2 IF
R1 R2 IF
Traditionally T
I
• Safety margin = 0.1
• Total = 0.4 s
O/C Relay Current Grading Margin
Between Relay
R
I
• Current setting of relay should be 3-4 x rating of fuse to ensure
coordination
• Use EI curve to grade with fuse
• Assume fuse minimum operating time = 0.01s
• Grading Margin = 0.4Tf + 0.15s over whole characteristic
O/C Relay Time Multiplier Setting
Calculation
• Calculate relay operating time required, Treq
• Consider grading margin
• Fault level
• Calculate op time of inverse characteristic with TMS
=1, T1
• TMS = Treq/T1
Instantaneous Protection
OUTLINE
i. Introduction
ii. Basic Concept and principle of
application
iii.Types of differential relays
iv.Principles Of Application
v. Advantage and Dis-advantages
Differential Relay
PROTECTION
• Record as-found metering parameters from the relay monitor or from multi-
meter output before testing;
• Ensure that the test plug is properly connected to the relay tester.
• When testing distance relays, insert the test plug for current input first
before the test plug for voltage input.
Safety Precautions for Specific
Equipment/Devices
PROTECTION
• Make sure to double check relay tester connection before injecting current or
voltage inputs.
• Make sure to set current and voltage parameters to zero at the relay tester
monitor or laptop to prevent injecting default values by accident which may
exceed the relay’s tolerance.
PROTECTION
• Make sure to restore first the analog inputs before restoring all trip
outputs.
• Make sure to check whether trip outputs from the relay was reset after
testing before restoring the trip connection.
• Make sure to reset and clear all recorded events on the relay before
restoration.
• Record metering values from the relay’s HMI or monitor to ensure that
everything is normal.
Safety Precautions for Specific
Equipment/Devices
CT INPUTS
• Ensure that the relay in test is isolated from the CT circuit without
disturbing other relay in series.
PT INPUTS
TRIP OUTPUT
• Objectives
• SCADA System
• What is SCADA?
• Where is SCADA used?
• Metering System
• Types of Metering
• Purpose and Application
OBJECTIVES
OBJECTIVES
❑BAY LEVEL
consists of the individual IEDs. They process the data supplied by the
process level and make local control decisions. They also transmit data BAY LEVEL
for further processing and monitoring to the higher-level control and
data acquisition system, the SCADA system.
❑PROCESS LEVEL
contains devices such as circuit breakers or data acquisition devices for PROCESS LEVEL
current, voltage and other parameters. This is where the electrical
energy is switched.
DESIGN
STATION BUS
PROTOCOL
CONVERTER
BAY LEVEL
BCU METERING RELAYING
PROCESS BUS
STATION LEVEL
BAY LEVEL
PROCESS LEVEL
PROCESS LEVEL IMPLEMENTATION
POWER TRANSFORMER
PROCESS LEVEL IMPLEMENTATION
POWER TRANSFORMER
Pressure relief valve:
Essentially a spring loaded device designed to quickly
reduce the pressure inside the tank to a normal value.
Generally, a trip switch assembly is provided for signaling
and monitoring purposes.
Oil thermometer:
This element is used to for measuring the temperature of
the dielectric oil and shows it outside via temperature
indicators
PROCESS LEVEL IMPLEMENTATION
POWER TRANSFORMER
Buchholz relay:
Any internal trouble, such as insulation breakdown or high
activity partial discharges, can cause decomposition of
materials contained in power transformers, such as
pressboard, wood and oil. This produces gas bubbles that rise
to the top of transformer tank.
The Buchholz relay is designed to detect such gas bubbles and
activate switches for alarm or trip signals.
POWER TRANSFORMER
Winding temperature sensor:
This is a combined arrangement for obtaining winding temperature by an indirect method. It is based on the fact
that the temperature difference between the winding and the oil in the transformer tank depends upon the
current present in the winding. The device receives an input from an oil thermometer and adds the temperature
effect produced by the winding current, which is obtained from a current transformer installed in the bushing of
the power transformer.
PROCESS LEVEL IMPLEMENTATION
PROCESS LEVEL IMPLEMENTATION
POWER TRANSFORMER
Control Raise/Low
(OLTC, Cooling System) On/Off Fan Group 1 & 2 Temperature Winding Temperature HV
Manual Winding Temperature MV
Auto Winding Temperature LV
Fan Group 1 Oil Temperature OLTC
Fan Group 1 Oil Temperature Main Tank
Remote Reset for Local Annunciator Panel
Metering Primary Uab Secondary Uab Tertiary Uab
Remote Reset for Remote Annunciator Panel
Primary Ubc Secondary Ubc Tertiary Ubc
Primary Uca Secondary Uca Tertiary Uca
Status/Alarm Buchholz Alarm Status/Alarm Cooler Group/Stage 1 Running/Alarm
Primary Uan Secondary Uan Tertiary Uan
Buchholz Trip Cooler Group/Stage 1 Motor Supply Fail
Primary Ubn Secondary Ubn Tertiary Ubn
Leakage Protection of Air-Bag Alarm Fan/Cooler Group/Stage 2 Running/Alarm
Primary Ucn Secondary Ucn Tertiary Ucn
Winding Temp. HV/LV/TV Alarm Fan/Cooler Group/Stage 2 Motor Supply Fail
Primary I Secondary I Tertiary I
Winding Temp. HV/LV/TV Trip Oil Pump Motor Supply Fail
Primary Ib Secondary Ib Tertiary Ib
Oil Temp. Alarm LCP AC/DC Power Supply Fail
Primary Ic Secondary Ic Tertiary Ic
Oil Temp. Trip RCP AC/DC Power Supply Fail
Primary In Secondary In Tertiary In
Sudden Pressure Relay Trip Transformer Paralleling On
Primary P Secondary P Tertiary P
OLTC Pressure Relief Trip Transformer Paralleling Master/Follower
Primary Q Secondary Q Tertiary Q
Main Tank Pressure Relief Trip Parallel Failure
Primary S Secondary S Tertiary S
Oil Level Low Main Tank OLTC Local/Remote/Auto
Primary cos Secondary cos Tertiary cos
Oil Level High Main Tank OLTC Tap Change in Progress
Primary Freq Secondary Freq Tertiary Freq
Oil Level High OLTC Tap Change incomplete
Oil Level Low OLTC Tap Change in position
OLTC Control Off OLTC Motor Trip
Voltage Regulator Failure Dehydrator/Breather Alarm
Shutter Valve Alarm Surge Counter Ph. A/B/C
Rupture Disk Alarm Tap Position (BCD)
Oil Filter Unit Alarm Reset Alarm
PROCESS LEVEL IMPLEMENTATION
Local/Remote Switch
LOCAL/REMOTE
SWITCH
DC MCB
AUXILIARY CONTACT
CLOSE COIL
SF6 LOCK-OUT
CONTACT
CLOSE MCB
POWER CIRCUIT BREAKER IMPLEMENTATION
REMOTE CLOSE
SWITCH
CLOSE COIL
SF6 LOCK-OUT
CONTACT DI – SF6 Lock-out Alarm AI – SF6 Level
Analog Output Signal (Sf6 gas level, oil level, nitrogen level,
etc.
Cybersecurity compliance
Cybersecurity compliance
MASTER
MASTER
TELECOM
TELECOM STATION
STATION
SUBSTATION ENERGY METERING
SYSTEM
Purpose and applications
Purpose and applications
1. Analog meters: also called electromechanical meters. They have an analog display. They do not offer any
connectivity.
2. Digital meters: also called electric meters. They have a digital display (LCD or LED display), they offer connectivity
and some instant functionalities.
USAGE OF ENERGY METERS
USAGE OF ENERGY METERS
BUS
CT
LOAD
PCB
METER
PT
COMPONENTS OF A METERING SYSTEM
COMPONENTS OF A METERING SYSTEM
1. INSTRUMENT TRANSFORMER
(CURRENT AND POTENTIAL TRANSFORMER)
2. CABLES
3. TERMINAL BLOCK
4. MARSHALING KIOSK/PANEL
5. TEST SWITCH
6. METER
BLOCK DIAGRAM
Block Diagram
SWITCHYARD CONTROL PANEL/ ROOM
BCT M
Test Block Terminal E
at Block Test
Marshaling at Control Switch T
Kiosk Panel E
PT R
Detailed Wiring Diagram
Detailed Wiring Diagram
Thank you.