Proforma For Analysis of Unit Rate of Excavation of Tunnels by Cyclic Drilling and Blasting (
Proforma For Analysis of Unit Rate of Excavation of Tunnels by Cyclic Drilling and Blasting (
Proforma For Analysis of Unit Rate of Excavation of Tunnels by Cyclic Drilling and Blasting (
IS 10061 :1991
( Reaffirmed 2001 )
( FFfT y+vl )
Indian Standard
PROFORMA FOR ANALYSIS OF UNIT RATE
OF EXCAVATION OF TUNNELS BY
CYCLIC DRILLING AND BLASTING
(First Revision >
@ BIS 1991
FOREWORD
This Indian Standard ( First Revision > was adopted by the Bureau of Indian Standards, after the draft
finalized by the Cost Analysis and Cost Estimates Sectional Committee had been approved by the
River Valley Division Council.
Tunnels are provided for various purposes such as for river diversion during construction of dams,
pressure conduits to serve as penstocks for power house, pressure or free flow conduits in water carrier
system, spillways and for rail and road transporation. Tunnelling may be either in rock or in soft
ground or shield driven. The tunnelling costs depend not on14 on labour, machinery and materials of
construction but also on the purpose of construction, types of rocks and soils bored through including
physical defects of the geological formations, the number of entrances provided for excavating the
tunnel, etc. The cost of excavation of tunnels may vary therefore from place to place. To have a
proper comparison of the unit rates of excavation of various tunnels, it is necessary to have uniformity
in the analysis of the costs of different parameters which make up the unit rate, which has been brought
out in this standard in the form of proforma.
This standard was first published in 1981. The revision of this standard has been taken up in the light
of the experience gained during the last nine years in the use of this standard. This standard has
been revised and additional items, required to be covered have been added.
IS 10061 : 1991
Indian Standard
PROFORMA FOR ANALYSISOF UNIT RATE
OF EXCAVATION OF TUNNELS BY
CYCLIC DRILLING AND BLASTING
(First Revision j
1 SCOPE 5. Construction Agency
This standard lays down proforma for analysis of a) Departmental or contractor
unit rate of tunnel excavation. It does not include b) Name of department/contractor
provisions for tunnel lining.
6. Shape of~the tunnel ( circular, horse shoe,
2 CLASSIFICATION elliptical, vertical walled with arch roof )
7. Excavated size of the tunnel ( excavated
For ease of comparison of unit rates of excavation dimensions to the pay-line )
of various tunnels, the following classification for
tunnels should be adopted: 8. Type of final lining
1
Is 10061:1991
c) Reaches with inadequate rock cover and p) Location and lead of dump yard from
adverse ground water conditions portal
d) Reaches showing rock distress
19. Air supply — Installed capacity of com-
e) Reaches of bad rock strata causing break pressors pipe size
through conditions
Water supply — Capacity of tank, pipe
f) Any other adverse geological conditions. size, length, etc.
18. Equipment at each tunnel heading 20. Electrification
a) Drill Jumbo Main supply voltage
Type Transformer details
Overall dimensions
Spacing
Number of decks
Motive power Lighting voltage
Trolley line rectification (in case of electric-
b) Drilling machines ( hydro-booms; traction )
ladder drilling system with fast rock
drills; other drills ) Firing voltage
Number and Type 21. Excavation data ( in reaches of competent
c) Drill steel and drill bits ( a brief des- rock strata )
cription )
a) Type of strata
d) Mucking machine Average number of drill holes and size
Make and model of holes per round
Capacity
Motive power Type of cut-holes pattern
Number of mucking machine Number and size of cut-holes
e) Haulage equipment. ~ Number, make, Average depth of drill-holes
Locos-Diesel/Electr]c ~model and Average actual advance
Rubber tyred carriers j capacity Type of explosive and detonators used
~ Quantity of explosive used per round ‘
f) Muck trucks
Mine cars/diesel/ I Number, make, Explosive factor ( kg~m’ )
electric ) model and b) Time Cycle
Rubber tyred carriers J capacity
Moving drill jumbo up to . .. ( h Min)
g) Ventilation the face and drilling the
i) Diameter of ventilation duct round
Make, model, type and capacity of Average drilling rate . . . ( cms per Afin )
main blowers Loading the round; . .. (hkfin)
Spacing of main blowers removing drill jumbo from
ii) Same as above in case of exhaust the face firing the circuits
blowers — at the face inside the Smoke clearance time .. . ( &fin)
tunnel and spacing Advancing mucking machine ( h &fin )
h) Pumping arrangements inside the tunnel to the muck pile, scaling
Number of pumps — main/feeder down loose rocks and
Type of pumps mucking out
Capacity of pumps Time for installation of steel
Spacing of pumps supports sets
Length, size and nature of pipelines-
rnain/feeder Time for secondary blast- .. . ( h Min )
ing and muck removal
j) Tunnel supporting arrangement Number of sets installed
k) Communication arrangement inside Spacing of sets
and outside Time for installation . .. (h Min)
m) Instruments for monitoring Time for lagging and .. . ( Min )
n) Instruments for determining stresses blocking
inrock OR
w. -, —.—..——
IS 10061:1991
( Clause 3.1 )
i) Drilling
a) Machinery and equipment excluding air
operating cost
b) Compressed air
CJ Other material
d) Labour
ii) Blasting
a) Machinery and equipment
b) Material
c) Labour
iii) Scaling, Mucking and Disposal
a) Scaling
b) Machinery and equipment
c) Labour
iv) Shotcreting/GunitingjRock bolting and Consolid-
ation grouting
a) Shotcreting
b) Guniting
c) Rock bolting
d) Consolidation grouting
e) Labour
v) Supports and Lagging
a) Machinery and equipment
b) Material
c) Ldbour
vi) Facilities
a) Ventilation
b) Surveying
c) Lighting
d) Dewatering
e) Communication
f) Instrumentation
g) Tracks
h) Miscellaneous items
vii) Ancillaries and Incidentals
a) Construction of the following:
1) Labour and staff quarters
2) Service roads
3) Electric power supply
4) Water supply system
5) Sanitation system
6) Drainage system
7) Other amenties including first-aid, medical
facilities and safety arrangements and
rescue operatians
b) avl:Fetenance/operation of’ items mentioned
This would include establishment, office stationery, general tools and plant, staff cars, their running and
maintenance, insurance, workman’s compensation,statutory benefits, telephone and telecommunication facilities
interest liabilities on borrowings from the owner and bank guarantee charges etc.
NOTE - All items mentioned above shall include depreciation, erection, operation, repairs and mainten-
ance and dismantling of machinery where used. All items of labour mentioned above shall include indirect
statuatory and other benefits payable to the labour.
4
Standard Mark
The use of the Standard Mark is governed by the provisions cf the Bureau of Indian
Standards Act, 1986 and the Rules and Regulations made thereunder. The Standard Mark
on products covered by an Indian Standard conveys the assurance that they have been
produced to comply with the requirements of that standard under a well defined system
of inspection, testing and quality control which is devised and supervised by BIS and
operated by the producer. Standard marked products are also continuously checked by
BIS for conformity to that standard as a further safeguard. Details of conditions under
which a licence for the use of the Standard Mark may be granted to manufacturers or
producers may be obtained from the Bureau of Indian Standards.
Bureau of Indian Standards
BIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to
promote harmonious development of the activities of standardization, marking and quality
certification of goods and attending to connected matters in the ~country.
Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced
in any form without the prior permission in writing of BIS. This does not preclude the free use,
in the course of implementing the standard, of necessary details, such as symbols and sizes, type
or grade designations. Enquiries relating to copyright be addressed to the Director
( Publications ), BIS.
Indian Standards are reviewed periodically and revised, when necessary and amendments, if
any, are issued from time to time. Users of Indian Standards should ascertain that they are in
possession of the latest amendments or edition. Comments on this Indian Standard may be
sent to BIS giving the following reference:
Headquarters :
Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002
Telephones : 331 01 31, 331 13 75 Telegrams : Manaksanstha
( Common to all Offices )