1MRK505180-UEN B en Installation and Commissioning Manual Busbar Differential Protection IED REB 670 1.1
1MRK505180-UEN B en Installation and Commissioning Manual Busbar Differential Protection IED REB 670 1.1
1MRK505180-UEN B en Installation and Commissioning Manual Busbar Differential Protection IED REB 670 1.1
Manufacturer:
ABB AB
Substation Automation Products
SE-721 59 Västerås
Sweden
Telephone: +46 (0) 21 34 20 00
Facsimile: +46 (0) 21 14 69 18
www.abb.com/substationautomation
Table of contents
Table of contents
Section 1 Introduction.......................................................................7
Introduction to the installation and commissioning manual................7
About the complete set of manuals for an IED..............................7
About the installation and commissioning manual.........................8
Intended audience.........................................................................9
Related documents........................................................................9
Revision notes...............................................................................9
Section 3 Overview........................................................................15
Commissioning and installation overview.........................................15
Overview................................................................................31
Mounting procedure for side-by-side rack mounting..............32
IED 670 mounted with a RHGS6 case...................................32
Side-by-side flush mounting........................................................33
Overview................................................................................33
Mounting procedure for side-by-side flush mounting.............34
Making the electrical connection......................................................35
IED connectors............................................................................35
Overview................................................................................35
Front side connectors.............................................................36
Rear side connectors.............................................................37
Connection diagrams.............................................................39
Connecting to protective earth.....................................................45
Connecting the power supply module.........................................45
Configuration for analog CT inputs..............................................46
Connecting to CT and VT circuits................................................46
Connecting the binary input and output signals...........................46
Making the screen connection.....................................................48
Optical connections..........................................................................49
Connecting station communication interfaces (OEM and
SLM)............................................................................................49
Connecting remote communication interfaces (LDCM)...............50
Galvanic X.21 line data communication (X.21-LDCM).....................51
Connecting Galvanic X.21 line data communication module
(X.21 LDCM)................................................................................51
Installing the serial communication cable for RS485........................53
RS485 serial communication module..........................................53
Installing the serial communication cable for RS485 SPA/
IEC...............................................................................................56
Data on RS485 serial communication module cable...................58
Installing the GPS antenna...............................................................58
Installing the GPS antenna..........................................................58
Antenna installation................................................................58
Electrical installation...............................................................59
Overview......................................................................................90
Preparing the connection to the test equipment..........................91
Putting the IED into test mode.....................................................91
Connecting test equipment to the IED.........................................92
Verifying the connections and the analog inputs.........................92
Releasing the function(s) to be tested.........................................93
Disturbance report.......................................................................94
Introduction.............................................................................94
Disturbance report settings....................................................94
Disturbance recorder (DR).....................................................94
Event recorder (ER)...............................................................95
Identifying the function to test in the technical reference
manual ........................................................................................95
Exit test mode..............................................................................95
Basic IED functions..........................................................................96
Parameter setting groups (ACGR)..............................................96
Verifying the settings..............................................................96
Completing the test................................................................96
Differential protection........................................................................96
Busbar differential protection (PDIF, 87B)...................................96
General...................................................................................96
Operation of the differential protection from CTx input...........97
Stability of the general differential protection.........................99
Operation of fast open CT detection algorithm.....................100
Operation of slow open CT detection algorithm...................101
Completing the test..............................................................102
Check of trip circuits and circuit breakers ............................102
Current protection...........................................................................102
Four step phase overcurrent protection (PTOC, 51/67)............102
Verifying the settings............................................................103
Completing the test..............................................................104
Four step single phase overcurrent protection (POCM,
51/67)........................................................................................104
Verifying the settings............................................................104
Completing the test..............................................................105
Breaker failure protection (RBRF, 50BF)...................................105
Checking the phase current operate value, IP>...................106
Checking the residual (EF) current operate value “IN>” set
below “IP>”...........................................................................106
Checking the re-trip and back-up times................................106
Verifying the re-trip mode.....................................................107
Verifying the back-up trip mode............................................108
Verifying instantaneous back-up trip at “CB faulty”
condition ..............................................................................109
Recording.............................................................................132
Secondary injection..............................................................132
Alarm test.............................................................................132
Self supervision check..........................................................132
Trip circuit check..................................................................133
Measurement of service currents.........................................133
Restoring..............................................................................133
Section 16 Glossary.......................................................................141
Glossary.........................................................................................141
Section 1 Introduction
en06000097.vsd
The Operator’s Manual (OM) contains instructions on how to operate the protection
IED during normal service once it has been commissioned. The operator’s manual
can be used to find out how to handle disturbances or how to view calculated and
measured network data in order to determine the cause of a fault.
The IED 670 Engineering guide (EG) contains instructions on how to engineer the
IED 670 products. The manual guides to use the different tool components for IED
670 engineering. It also guides how to handle the tool component available to read
disturbance files from the IEDs on the basis of the IEC 61850 definitions. The third
part is an introduction about the diagnostic tool components available for IED 670
products and the PCM 600 tool.
The IEC 61850 Station Engineering guide contains descriptions of IEC 61850
station engineering and process signal routing. The manual presents the PCM 600
and CCT tool used for station engineering. It describes the IEC 61850 attribute editor
and how to set up projects and communication.
• The chapter “Safety information” presents warning and note signs, that the user
should pay attention to.
• The chapter “Overview” is a summary of the major tasks faced when installing
and commissioning an IED.
• The chapter “Unpacking and checking the IED” explains how to take delivery
of the IED.
• The chapter “Installing the IED” explains how to install the IED.
• The chapter “Checking the external optical and electrical connections” explains
how to check that the IED is properly connected to the protection system.
• The chapter “Energizing the IED” explains how to start the IED.
• The chapter “Establishing connection and verifying the SPA/IEC-
communication” contains explains how to enter SPA/IEC settings and verifying
the SPA/IEC communication.
• The chapter “Establishing connection and verifying the LON communication”
contains a reference to another document.
• The chapter “Configuring the IED and changing settings” explains how to
download settings and configure the terminal.
• The chapter “Verifying settings by secondary injection” contains instructions on
how to verify that each included function operates correctly according to the set
values.
• The chapter “Primary injection testing” describes a test with primary current
through the protected zone.
• The chapter “Commissioning and maintenance of the fault clearing system”
discusses maintenance tests and other periodic maintenance measures.
• The chapter “Fault tracing and repair” explains how to troubleshoot.
• The chapter “Glossary” is a list of terms, acronyms and abbreviations used in
ABB technical documentation.
Requirements
The installation and commissioning personnel must have a basic knowledge in
handling electronic equipment. The commissioning and maintenance personnel must
be well experienced in using protection equipment, test equipment, protection
functions and the configured functional logics in the protection.
Always avoid touching the circuitry when covers are removed. The
product contains electronic circuits which can be damaged if exposed
to static electricity (ESD). Lethal high voltage circuits are also
exposed when covers are removed.
Always use suitable isolated test pins when measuring signals in open
circuitry. Potentially lethal voltages and currents are present.
the IED without proper earthing may damage both IED and measuring
circuitry and may cause injuries in case of an accident.
Take adequate measures to protect the eyes. Never look into the laser
beam.
Changing the active setting group will inevitably change the IEDs
operation. Be careful and check regulations before making the
change.
Section 3 Overview
The settings for each function must be calculated before the commissioning task can
start. A configuration, done in the configuration and programming tool, must also be
available if the IED does not have a factory configuration downloaded.
Procedure
5.1 Overview
The mechanical and electrical environmental conditions at the installation site must
be within the limits described in the IED technical data. Dusty, damp places, places
susceptible to rapid temperature variations, powerful vibrations and shocks, surge
voltages of high amplitude and fast rise time, strong induced magnetic fields or similar
extreme conditions should be avoided.
Sufficient space must be available in front of and at the rear of the IED to allow access
for maintenance and future modifications. Flush mounted IEDs should be mounted
so that IED modules can be added and replaced without excessive dismantling.
5.2 Dimensions
E
K
D
A F
B C
G J
xx04000448.vsd
H
D F
J
B G
C H xx05000502.vsd
xx05000501.vsd
xx05000503.vsd
Case size A B C D E F G H J K
(inches)
6U, 1/2 x 19” 10.47 8.81 9.53 10.07 8.10 7.50 8.02 - 9.00 -
6U, 3/4 x 19” 10.47 13.23 9.53 10.07 12.52 7.50 12.4 - 9.00 -
6U, 1/1 x 19” 10.47 17.65 9.53 10.07 16.86 7.50 16.86 18.31 9.00 19.00
The H and K dimensions are defined by the 19” rack mounting kit.
A C
E
D
xx04000465.vsd
xx06000182.vsd
G
D
B
E
F
C
xx05000505.vsd
B
E
C
D
en04000471.vsd
The different mounting kits contain all parts needed including screws and assembly
instructions. The following mounting kits are available:
The same mounting kit is used for side-by-side rack mounting and side-by-side flush
mounting.
Generally, all the screws included in delivered mounting kits are of Torx type and a
screwdriver of the same type is needed (Tx10, Tx15, Tx20 and Tx25).
A B C D
Description
A Flush mounting
B 19” Panel rack mounting
C Wall mounting
D Side-by-side rack or flush mounting
5.3.2.1 Overview
All IED sizes, 1/2 x 19”, 3/4 x 19” and 1/1 x 19” and RHGS6 6U 1/4 x 19”, cases,
can be flush mounted. Only a single case can be mounted in each cut-out on the cubicle
panel, for class IP54 protection.
The flush mounting kit are utilized for IEDs of sizes: 1/2 x 19”, 3/4 x 19” and 1/1 x
19” and are also suitable for mounting of RHGS6, 6U 1/4 x 19” cases.
1
7
2
6
5
3
xx06000246.vsd
Procedure
5.3.3.1 Overview
All IED sizes can be mounted in a standard 19” cubicle rack by using the for each
size suited mounting kit which consists of two mounting angles and fastening screws
for the angles. The mounting angles are reversible which enables mounting of IED
size 1/2 x 19” or 3/4 x 19” either to the left or right side of the cubicle.
Please note that the separately ordered rack mounting kit for side-by-
side mounted IEDs, or IEDs together with RHGS cases, is to be
selected so that the total size equals 19”.
1a
1b
xx04000452.vs d
Procedure
1. Carefully fasten the mounting angles (1a, 1b) to the sides of the IED.
Use the screws (2) supplied in the mounting kit.
2. Place the IED assembly in the 19” panel.
3. Fasten the mounting angles with appropriate screws.
5.3.4.1 Overview
All case sizes, 1/2 x 19”, 3/4 x 19” and 1/1 x 19”, can be wall mounted. It is also
possible to mount the IED on a panel or in a cubicle.
When mounting the side plates, be sure to use screws that follows the
recommended dimensions. Using screws with other dimensions than
the original may damage the PCBs inside the IED.
If fiber cables are bent too much, the signal can be weakened. Wall
mounting is therefore not recommended for communication modules
with fiber connection; Serial SPA/IEC 60870-5-103 and LON
communication module (SLM), Optical Ethernet module (OEM) and
Line data communication module (LDCM).
3
4
2
6
xx04000453.vs d
Procedure
The IED can be equipped with a rear protection cover which is recommended to use
with this type of mounting. See figure 14.
To reach the rear side of the IED, a free space of 80 mmis required on the unhinged
side.
3
1
80 mm 2
en06000135.vsd
Figure 14: How to reach the connectors on the rear side of the IED.
Procedure
1. Remove the inner screws (1), upper and lower on one side.
2. Remove all three fixing screws (2), on the opposite side, from wall support.
3. The IED can now be swung out for access to the connectors, after removing any
rear protection.
5.3.5.1 Overview
IED case sizes, 1/2 x 19” or 3/4 x 19” and RHGS cases, can be mounted side-by-side
up to a maximum size of 19”. For side-by-side rack mounting, the side-by-side
mounting kit together with the 19” rack panel mounting kit must be used. The
mounting kit has to be ordered separately.
When mounting the plates and the angles on the IED, be sure to use
screws that follows the recommended dimensions. Using screws with
other dimensions than the original may damage the PCBs inside the
IED.
2
1
xx04000456.vsd
Procedure
An 1/2 x 19” or 3/4 x 19” size IED can be mounted with a RHGS (6 or 12 depending
on IED size) case. The RHGS case can be used for mounting a test switch of type
RTXP 24. It also has enough space for a terminal base of RX 2 type for mounting of,
for example, a DC-switch or two trip relays.
1 2
1 2 1 2
1 1 1 1
2 2 2 2
3 3 3 3
4 4 4 4
5 5 5 5
6 6 6 6
7 7 7 7
8 8 8 8
xx06000180.vsd
Figure 16: IED 670 (1/2 x 19”) mounted with a RHGS6 case containing a test
switch module equipped with only a test switch and a RX2 terminal
base.
5.3.6.1 Overview
It is not recommended to flush mount side by side mounted cases if IP54 is required.
If your application demands side-by-side flush mounting, the side-by-side mounting
details kit and the 19” panel rack mounting kit must be used. The mounting kit has
to be ordered separately. The maximum size of the panel cut out is 19”.
When mounting the plates and the angles on the IED, be sure to use
screws that follows the recommended dimensions. Using screws with
other dimensions than the original may damage the PCBs inside the
IED.
1 2
xx06000181.vsd
Figure 17: Side-by-side flush mounting details (RHGS6 side-by-side with 1/2 x
19” IED).
Procedure
5.4.1.1 Overview
The quantity and designation of connectors depend upon the type and size of the IED.
The rear cover plates are prepared with space for the maximum of HW options for
each case size and the cut-outs that are not in use are covered with a plate from factory.
Module Description
Line data communication modules (LDCM) (short Modules used for digital communication to remote
range, medium range, long range, X21) terminal.
Serial SPA/LON/IEC 60870-5-103 Used for SPA/LON/IEC 60870–5–103
communication modules (SLM) communication
Optical ethernet module (OEM) PMC board for IEC 61850 based communication.
GPS time synchronization module (GSM) Used to provide the IED with GPS time
synchronization.
Static output module (SOM) Module with 6 fast static outputs and 6 change over
output relays.
IRIG-B Time synchronization module Module with 2 inputs. One is used for handling both
pulse-width modulated signals and amplitude
modulated signals and one is used for optical input
type ST for PPS time synchronization.
PosNo Description
1 IED serial communication port with RJ45 connector
2 Ethernet cable with RJ45 connectors
The cable between PC and the IED serial communication port shall
be a crossed-over Ethernet cable with RJ45 connectors. If the
Figure 25: Binary output module (BOM). Output contacts named XA corresponds to rear position X31, X41,
etc. and output contacts named XB to rear position X32, X42, etc.
Figure 27: Binary in/out module (IOM). Input contacts named XA corresponds to rear position X31, X41, etc.
and output contacts named XB to rear position X32, X42, etc.
The cubicle must be properly connected to the station earthing system. Use a
conductor with a core cross section area of at least 4 mm2 (AWG 12).
3
1
en05000509.vsd
Figure 28: Rear view of IED with one TRM showing earthing points.
PosNo Description
1 Main protective earth to chassis
2 Earthing screw to Power supply module (PSM)
3 Earthing screw to Transformer input module (TRM). (There is one earth connection per TRM)
Use the main protective earth screw (1) for connection to the stations
earthing system. Earthing screws for PSM module (2) and TRM
module (3) must be fully tightened to secure protective earth
connection of these modules.
the auxiliary supply must be routed separated from the current transformer cables
between the terminal blocks of the cubicle and the IEDs connections. The connections
are made on connector X11. For location of connector X11, refer to section "Rear
side connectors".
Use a solid conductor with a cross section area between 2.5-6 mm2 (AWG14-10) or
a stranded conductor with a cross section area between 2.5-4 mm2 (AWG14-12).
If the IED is equipped with a test-switch of type RTXP 24 COMBIFLEX wires with
20 A sockets must be used to connect the CT and VT circuits.
Connectors X401 and X402 (for location see section "Rear side connectors") for
current and voltage transformer circuits are so called “feed-through terminal blocks”
and are designed for conductors with cross sectional area up to 4 mm2 (AWG 12).
The screws used to fasten the conductors should be tightened with a torque of 1Nm.
If the IED is equipped with a test-switch of type RTXP 24 COMBIFLEX wires with
20 A sockets, 1.5mm² (AWG16) conductor area must be used to connect the auxiliary
power.
Procedure
All wiring to the female connector should be done before it is plugged into the
male part and screwed to the case. The conductors can be of rigid type (solid,
stranded) or of flexible type.
The female connectors accept conductors with a cross section area of 0.2-2.5
mm2 (AWG 24-14). If two conductors are used in the same terminal, the
maximum permissible cross section area is 0.2-1 mm2 (AWG 24-18 each).
If two conductors, each with area 1.5 mm2 (AWG 16) need to be connected to
the same terminal, a ferrule must be used, see figure 31. This ferrule, is applied
with the by Phoenix recommended crimping tool, see figure "". No soldering
is needed. Wires with a smaller gauge can be inserted directly into the female
connector receptacle and the fastening screw shall be tightened with a torque of
0.4 Nm (This torque applies to all binary connectors).
2. Plug the connector to the corresponding back-side mounted male connector
3. Lock the connector by fastening the lock screws
xx02000742.vsd
2 1
xx06000168.vsd
PosNo Description
1 Is ferrule,
2 A bridge connector, is used to jump terminal points in a connector.
Lc Cc Lc
Rx Tx
External
IED
Equipment
Tx Rx
2
Sc Sc 2
1 en06000190.vsd
PosNo Description
1 Outer shield
2 Protective earth screw
3 Inner shield
• Optical ports X311: A, B (Tx, Rx) and X311: C, D (Tx, Rx) on the OEM module
are used for IEC 61850 communication. Connectors are of ST type. When the
optical ethernet module is used, the protection plate for the galvanic connection
must not be removed.
• Optical port X301: A, B (Tx, Rx) on the SLM module is used for SPA or IEC
60870-5-103 communication. Connectors are of ST type (glass) or HFBR Snap
in (plastic).
• Optical port X301: C, D (Tx, Rx) on the SLM module is used for LON
communication. Connectors are of ST type (glass) or HFBR Snap in (plastic).
Connectors are generally color coded; connect blue or dark grey cable connectors to
blue or dark grey (receive) back-side connectors. Connect black or grey cable
connectors to black or grey (transmit) back-side connectors.
The fiber optical cables are very sensitive to handling. Do not bend
too sharply. The minimum curvature radius is 15 cm for the plastic
fiber cables and 25 cm for the glass fiber cables. If cable straps are
used to fix the cables, apply with loose fit.
Always hold the connector, never the cable, when connecting or
disconnecting optical fibers. Do not twist, pull or bend the fiber.
Invisible damage may increase fiber attenuation thus making
communication impossible.
Please, strictly follow the instructions from the manufacturer for each
type of optical cables/connectors.
When LDCM is used for binary signal exchange between IEDs in the same station
or even within the same panel (i.e. between three one-phase REB 670) the fiber optic
cables can be quite short (i.e. 1-2 meters). In such installation it is of outmost
importance to set LDCM setting parameter OptoPower = LowPower.
The galvanic X.21 line data communication module uses a ABB specific PC*MIP
Type II format.
C
en07000196.vsd
1 3
2 en07000195.vsd
Soft ground
To avoid ground loops when the grounds are connected, a soft ground connection for
the IO-ground can be used. This is handled in the ground selection connector.
X.21 connector
Screw
terminal 1
X3 2
1
2 RS485
3 PWB
Screw 4
terminal
5
X1
6
Backplate
en07000140.vsd
Figure 35: The connection plate to the backplate with connectors and screws.
This figure also shows the pin numbering from the component side
The distance between earth points should be < 1200 m (3000 ft), see figure 36 and
37. Only the outer shielding is connected to the protective earth at the terminal. The
inner and outer shieldings are connected to the protective earth at the external
equipment. Use insulating tape for the inner shield to prevent contact with the
protective earth. Make sure that the terminals are properly earthed with as short
connections as possible from the earth screw, for example to an earthed frame.
The terminal and the external equipment should preferably be connected to the same
battery.
Cc 1)
Cc
1 2 3 4 5 6 1 2 3 4 5 6 2)
X1 X1
External
IED IED Equipment (PC)
PE PE PE
PE 1) 3)
en07000141.vsd
Where:
1 The inner shields shall be connected together (with an isolated terminal block) and only have
one earthing point in the whole system, preferably at the external equipment (PC).
The outer shield shall be connected to Protective Earth (PE) in every cable end i.e. to PE at
all relay terminals and to PE at External equipment (PC). The first terminal will have only one
cable end but all others of course two.
2 Connect according to installation instructions for the actual equipment, observe the 120 ohms
termination.
3 The protective earth should be close to the external equipment (< 2m)
Cc Communication cable
PE Protective earth screw
Cc 1)
Cc
1)
1 2 3 4 5 6 1 2 3 4 5 6 2)
X1 X1
External
IED IED Equipment (PC)
PE PE PE
PE 1) 3)
en07000142.vsd
Where:
1 The inner shields shall be connected together (with an isolated terminal block) and only have
one earthing point in the whole system, preferably at the external equipment (PC).
The outer shield shall be connected to Protective Earth (PE) in every cable end i.e. to PE at
all relay terminals and to PE at External equipment (PC). The first terminal will have only one
cable end but all others of course two.
2 Connect according to installation instructions for the actual equipment, observe the 120 ohms
termination.
3 The protective earth should be close to the external equipment (< 2m)
Cc Communication cable
PE Protective earthscrew
en03000110.vsd
Where:
1 is cable
2 is screw
Pair separator
Pair Shield
Drain wire
Conductor
Overall shield
Separator
Jacket
en07000139.vsd
The EIA standard RS-485 specifies the RS485 network. An informative excerpt is
given in section "Installing the serial communication cable for RS485 SPA/IEC".
1 Normative references
EIA Standard RS-485 - Electrical Characteristics of Generators and Receivers for Balanced Digital
Multipoint Systems
2 Transmission method
RS-485 differential bipolar signaling
2.1 Differential signal levels
Two differential signal levels are defined:
A+ =line A positive with respect to line B
A- =line A negative with respect to line B
2.2 Galvanic isolation
The RS485 circuit shall be isolated from earth by:
Riso ≥ 10 MW
Ciso ≤ 10 pF
Three isolation options exist:
a) The entire node electronics can be galvanically isolated
Table continued on next page
b) The bus interface circuit can be isolated form the rest of node electronics by optoisolators,
transformer coupling or otherwise.
c) The RS485 chip can include built-in isolation
2.3 Bus excitation and signal conveyance
2.3.1 Requirements
a) The RS485 specification requires the Signal A and Signal B wires.
b) Each node also requires (5 V) Excitation of the RS485 termination network.
c) Vim - the common mode voltage between any pair of RS485 chips may not exceed 10 V.
d) A physical ground connection between all RS485 circuits will reduce noise.
2.3.2 Bus segment termination network
The termination network below required at each end of each Bus Ph-segment.
ExV+
Ru = 390 ohm
1/4 W, 2%
Signal B
Rt = 220 ohm
1/4 W, 2%
Signal A
Rd = 390 ohm
1/4 W, 2%
DGND
en03000112.vsd
1 6
4 7
5
xx05000510.vsd
PosNO Description
1 GPS antenna
2 TNC connector
3 Console, 78x150 mm
Mount the antenna and console clear of flat surfaces such as buildings walls, roofs
and windows to avoid signal reflections. If necessary, protect the antenna from
animals and birds which can affect signal strength. Also protect the antenna against
lightning.
Always position the antenna and its console so that a continuous clear line-of-sight
visibility to all directions is obtained, preferably more than 75%. A minimum of 50%
clear line-of-sight visibility is required for un-interrupted operation.
99001046.vsd
Use a 50 ohm coaxial cable with a male TNC connector on the antenna end and a
male SMA connector on the receiver end to connect the antenna to IED 670. Choose
cable type and length so that the total attenuation is max. 26 dB at 1.6 GHz. A suitable
antenna cable can be supplied with the antenna.
The antenna has a female TNC connector to the antenna cable. For location of GPS
module, refer to section "Rear side connectors". Connection diagram for GPS module
is shown in figure 24.
Make sure that the antenna cable is not charged when connected to
the antenna or to the receiver. Discharge the antenna cable by short-
circuiting the end of the antenna cable with some metal device and
then connect it to the antenna. When the antenna is connected to the
cable, connect the cable to the receiver. IED 670 must be switched
off when the antenna cable is connected.
6.1 Overview
The user must check the installation which includes verifying that the IED is
connected to the other parts of the protection system. This is done with the IED and
all connected circuits de-energized.
Check that the wiring is in strict accordance with the supplied connection diagram.
• Polarity check.
• VT circuit voltage measurement (primary injection test).
• Earthing check.
• Phase relationship
• Insulation resistance check
The polarity check verifies the integrity of circuits and the phase relationships. The
check should be performed as close as possible to the IED.
The primary injection test verifies the VT ratio and the wiring all the way through
from the primary system to the IED. Injection must be performed for each phase-to-
neutral circuit and each phase-to-phase pair. In each case voltages in all phases and
neutral are measured.
The CTs must be connected in accordance with the circuit diagram provided with the
IED, both with regards to phases and polarity. The following tests shall be performed
on every primary CT connected to the IED 670:
• primary injection test to verify the current ratio of the CT, the correct wiring up
to the protection IED and correct phase sequence connection (i.e. L1. L2, L3)
• polarity check to prove that the predicted direction of secondary current flow is
correct for a given direction of primary current flow. This is an essential test for
the proper operation of the differential function.
• CT secondary loop resistance measurement in order to confirm that the current
transformer secondary loop dc resistance is within specification and that there
are no high resistance joints in the CT winding or wiring.
• CT excitation test in order to confirm that the current transformer is of the correct
accuracy rating and that there are no shorted turns in the current transformer
windings. Manufacturer's design curves should be available for the current
transformer in order to compare the actual results.
• check the earthing of the individual CT secondary circuits to verify that each
three-phase set of main CTs is properly connected to the station earth and only
at one electrical point.
• Insulation resistance check.
• Phase identification of CT shall be made.
Both primary and secondary sides must be disconnected from the line
and IED when plotting the excitation characteristics.
Check that the auxiliary supply voltage remains within the permissible input voltage
range under all operating conditions. Check that the polarity is correct.
7.1 Overview
Before the procedures in this chapter can be carried out the connection to external
circuitry must have been checked which ensures that the installation was made
correctly.
The user could also check the software version, the IEDs serial number and the
installed modules and their ordering number to ensure that the IED is according to
delivery and ordering specifications. The user must energize the power supply of the
IED to start it up. This could be done in number of ways, from energizing a whole
cubicle to energizing a single IED. The user should reconfigure the IED to activate
the hardware modules in order to enable the self supervision function to detect
possible hardware errors. Then the IED time must be set. The self supervision function
(Diagnostics in HMI) should also be checked to verify that the IED unit operates
properly.
When the IED is energized, the green LED instantly starts flashing. After
approximately 55 seconds the window lights up and the window displays ‘IED
Startup’. The main menu is displayed and the upper row should indicate ‘Ready’ after
about 90 seconds. A steady green light indicates a successful startup.
1 2 3
t (s)
0 55 90
xx04000310.vsd
3 The main menu is displayed. A steady green light indicates a successful startup.
If the upper row in the window indicates ‘Fail’ instead of ‘Ready’ and the green LED
flashes, an internal failure in the IED has been detected. See section 3.3 "Checking
the self supervision function" in this chapter to investigate the fault.
An example of the local HMI with a small LCD is shown in figure 44.
The different parts of the medium size LHMI is shown in figure 44The LHMI, exists
in an IEC version and in an ANSI version. The difference is on the keypad operation
buttons and the yellow LED designation.
4 Label
5 Local/Remote LEDs
6 RJ45 port
7 Communication indication LED
8 Keypad
Each logical I/O module has an error flag that indicates signal or module failure. The
error flag is also set when the physical I/O module of the correct type is not detected
in the connected slot.
This procedure describes how to navigate the menus in order to find the cause of an
internal failure when indicated by the flashing green LED on the HMI module.
Procedure
The communication between the IED and the PCM 600 is independent of the used
communication protocol within the substation or to the NCC. It can be seen as a
second channel for communication.
The communication media is always Ethernet and the used protocol is TCP/IP.
Each IED 670 product has an Ethernet front connector for PCM 600 access.
Depending very much on the station concept and the used station protocol additional
Ethernet interfaces may be available on the rear side of the IED 670. All Ethernet
interfaces can be used to connect PCM 600.
When an Ethernet based station protocol is used the PCM 600 communication can
use the same Ethernet port and IP address. The IED 670 is able to separate the
information belonging to the PCM 600 dialog.
For the connection of the PCM 600 to the IED two basic variants have to be
considered.
• direct point to point link between PCM 600 and the IED 670
• indirect link via a station LAN or from remote via a network
The physical connection and the IP-addresses must be configured in both cases before
a dialog can start. The steps to do this are:
The rules etc. for the configured IP addresses are part of the project.
IED670
RJ45
PCM600
Tx Tx
Rx Rx
en05000810.vsd
Figure 45: Point to point link between IED 670 and PCM 600 using a null-modem
cable
Remark
Administrator rights are requested to change the configuration as described above.
en05000812.vsd
en05000813.vsd
en05000814.vsd
Figure 48: Step 3: select the TCP/IP protocol and open Properties
en05000815.vsd
Figure 49: Step 4: specify a TCP/IP address and Subnet mask for the PC
1. via the first window of the wizard by including a new IED 670 in a project
2. by entering the IP-address of the IED 670 in the Object Properties window
• select the IED to enter the IP-address
• open the Object Properties window
• place the cursor in the IP Address row and enter the IP-address.
en05000643.vsd
en05000811.vsd
The used alternative depends very much on the time at which the IP-address is
available. Alternative 2 allows a change of the IP-address at any time.
If the IED is connected to a monitoring or control system via the rear SPA/IEC port,
the SPA/IEC port has to be set either for SPA or IEC use.
When using the SPA protocol, the rear SPA/IEC port must be set for SPA use.
Procedure
Set the same slave number and baud rate as set in the SMS system for the IED.
The SPA/IEC port is located at IED X310 on the rear side of the IED.
Procedure
To verify that the rear communication with the SMS/SCS system is working, there
are some different methods. Choose one of the following.
1. Use a SPA-emulator and send “RF” to the IED. The answer from the IED should
be “”.
2. Generate one binary event by activating a function which is configured to an
event block where the used input is set to generate events on SPA. The
configuration must be made with the PCM 600 software. Verify that the event
is presented in the SMS/SCS system.
During the following tests of the different functions in the IED, verify that the events
and indications in the SMS/SCS system are as expected.
Procedure
1. Check that the master system time-out for response from the IED, for example
after a setting change, is > 40 seconds.
2. Use a protocol analyzer and record the communication between the IED and the
IEC master. Check in the protocol analyzer’s log that the IED answers the master
messages.
3. Generate one binary event by activating a function which is configured to an
event block where the used input is set to generate events on IEC. The
configuration must be made with the PCM 600 software. Verify that the event
is presented in the IEC master system.
During the following tests of the different functions in the IED, verify that the events
and indications in the IEC master system are as expected.
The SPA communication is mainly used for SMS. It can include different numerical
relays/terminals with remote communication possibilities. The fibre optic loop can
contain < 20-30 terminals depending on requirements on response time. Connection
to a personal computer (PC) can be made directly (if the PC is located in the
substation) or by telephone modem through a telephone network with ITU (CCITT)
characteristics.
Where:
1 A separate minute pulse synchronization from station clock to obtain ± 1 ms accuracy for time
tagging within the substation might be required.
The test can only be carried out when the whole communication system is installed.
Thus, the test is a system test and is not dealt with here.
The communication protocol LON (Local Optical Network) is available for IED 670
products as an option.
Gateway
Star coupler
RER 111
en05000663.vsd
An optical network can be used within the Substation Automation system. This
enables communication with the IED 670s through the LON bus from the operator’s
workplace, from the control center and also from other IEDs via bay-to-bay horizontal
communication.
The fiber optic LON bus is implemented using either glass core or plastic core fiber
optic cables.
The HV Control 670 software module is included in the LIB 520 high-voltage process
package, which is a part of the Application Software Library within MicroSCADA
applications.
The HV Control 670 software module is used for control functions in IED 670s. This
module contains the process picture, dialogues and a tool to generate the process
database for the control application in MicroSCADA.
Use the LNT, LON Network Tool to set the LON communication. This is a software
tool applied as one node on the LON bus. In order to communicate via LON, the IEDs
need to know which node addresses the other connected IEDs have, and which
network variable selectors should be used. This is organized by the LNT.
The node address is transferred to the LNT via the local HMI by setting the parameter
ServicePinMsg=YES. The node address is sent to the LNT via the LON bus, or the
LNT can scan the network for new nodes.
The communication speed of the LON bus is set to the default of 1.25 Mbit/s.This
can be changed by the LNT.
The setting parameters for the LON communication are set via the local HMI. Refer
to the Technical reference manual for setting parameters specifications.
These parameters can only be set with the LNT, LON Network Tool.
These parameters can only be set with the LNT, LON Network Tool.
The chapter does not contain instructions on how to create a configuration or calculate
settings. Please consult the application manual for further information about how to
calculate settings.
It takes a minimum of three minutes for the IED to save the new
settings, during this time the DC supply must not be turned off.
11.1 Overview
The customer specific values for each setting parameter and a configuration file have
to be available before the IED can be set and configured, if the IED is not delivered
with a configuration.
Use the PCM 600 configuration tool to verify that the IED has the expected
configuration. A new configuration is done with the CAP tool. The binary outputs
can be selected from a signal list where the signals are grouped under their function
names. It is also possible to specify a user-defined name for each input and output
signal.
Each function included in the IED has several setting parameters which have to be
set in order to make the IED behave as intended. A factory default value is provided
for each parameter. A setting file can be prepared using the parameter setting tool
(PST), which is available in the PCM 600 package.
Each of the included functions in the IED has to be set and this can be performed
through the local HMI. The user must browse to the desired function and enter the
appropriate value. The parameters for each function can be found in the local HMI.
The Operators Manual (OM) is structured in a similar way to the LHMI and provides
a detailed guide to the use of the local HMI including paths in the menu structure and
brief explanations of most settings and measurements. See the Technical reference
manual for a complete list of setting parameters for each function. Some of the
included functions may not be used. In this case the user can set the parameter
“Operation” to “Off” to disable the function.
The primary CT data are entered from the HMI menu branch:
This parameter defines the primary rated current of the CT. For two set of CTs with
ratio 1000/1 and 1000/5 this parameter is set to the same value of 1000 for both CT
inputs. Negative values (i.e. -1000) can be used in order to reverse the direction of
the CT current by software for the differential function. This might be necessary if
two sets of CTs have different star point locations in relation to the protected busbar.
It is recommended that this parameter is set to zero, for all unused CT inputs.
For main CTs with 2A rated secondary current, it is recommended to connect the
secondary wiring to the 1A input and to set the rated primary current to one half times
its true value. For example, a CT with a primary secondary current ratio of 1000/2A
can be treated as a 500/1A CT.
Take the rated permissive overload values for the current inputs into
consideration.
When the configuration is downloaded and completed, the IED is automatically set
into normal mode. For further instructions please refer to the users manuals for PCM
600.
12.1 Overview
• Calculated settings
• Application configuration diagram
• Signal matrix (SMT) configuration
• Terminal diagram
• Technical reference manual
• Three-phase test equipment
• PCM 600
The setting and configuration of the IED must be completed before the testing can
start.
The test equipment should be able to provide a three-phase supply of voltages and
currents. The magnitude of voltage and current as well as the phase angle between
voltage and current must be variable. The voltages and currents from the test
equipment must be obtained from the same source and they must have minimal
harmonic content. If the test equipment cannot indicate the phase angle, a separate
phase-angle measuring instrument is necessary.
Prepare the IED for test before testing a particular function. Consider the logic
diagram of the tested protection function when performing the test. All included
functions in the IED are tested according to the corresponding test instructions in this
chapter. The functions can be tested in any order according to user preferences and
the test instructions are therefore presented in alphabetical order. Only the functions
that are used (Operation is set to On) should be tested.
Please observe the measuring accuracy of the IED, the test equipment
and the angular accuracy for both of them.
Please consider the configured logic from the function block to the
output contacts when measuring the operate time.
12.2.1 Overview
This section describes how to prepare the IED to verify settings.
be checked to ensure that indications are correct. Functions to test, signals and
parameter names can be found in the technical reference manual.
COMBIFLEX system is used, when the test-plug handle is inserted into the test
switch. Preparations for testing are automatically carried out in the proper sequence
(i.e. blocking of tripping circuits, short circuiting of CT’s, opening of voltage circuits,
making IED terminals available for secondary injection). Terminals 1 and 12 of the
test switch are not disconnected as they supply DC power to the protection IED.
The test-plug handle leads may be connected to any type of test equipment or
instrument. When a number of protection IEDs of the same type are tested, the test-
plug handle only needs to be moved from the test switch of one protection IED to the
test switch of the other, without altering previous connections.
Using COMBIFLEX test system to prevent unwanted tripping when the handle is
withdrawn, latches on the handle secure it in the half withdrawn position. In this
position, all voltages and currents are restored and any reenergizing transients are
given a chance to decay before the trip circuits are restored. When the latches are
released, the handle can be completely withdrawn from the test switch, restoring the
trip circuits to the protection IED.
Procedure
The Test Mode menu is found under the Test folder in the LHMI:
Test/IED test mode/TestMode
2. Use the up and down arrows to choose ‘On’ and press ‘E’.
3. Press the left arrow to exit the menu.
The dialog box ‘Save changes’ appears.
4. Choose ‘Yes’, press E and exit the menu.
The yellow start LED above the LCD will start flashing when the IED is in test
mode.
IL1 IL1
IL2 IL2
IL3 IL3
NI IN (I4,I5)
IED TEST SET
IEC61850
en05000467.vsd
Figure 54: Connection example of the test set to the IED 670
Procedure
Procedure
12.2.7.1 Introduction
• Disturbance recorder
• Event list
• Event recorder
• Fault locator (not included in all products)
• Trip value recorder
• Indications
If the disturbance report is running, then its sub-function are also running and so it is
not possible to only switch these functions off. The disturbance report function is
switched off from PCM 600 or from the local HMI.
When the IED is in test mode, the disturbance report can be made active or inactive.
If the disturbance recorder is turned on during test mode, recordings will be made.
When test mode is switched off all recordings made during the test session are cleared.
Settings for the control of the disturbance recorder during test mode are located in
the local HMI under:
Evaluation of the results from the disturbance recording function requires access to
a PC either permanently connected to the IED or temporarily connected to the
Ethernet port (RJ 45) on the front. The PCM 600 software package must be installed
in the PC.
Disturbance upload can be performed by the use of PCM 600 or by any third party
tool with IEC 61850 protocol. Reports can automatically be generated from the PCM
600 tool. Disturbance files can be analyzed by any tool reading Comtrade formatted
disturbance files.
It could be useful to have a printer for hard copies. The behavior of the disturbance
recording function can be checked when IED protective functions are tested. When
the IED is set to operate in test mode, there is a separate setting for operation of the
disturbance report, which also affects the disturbance recorder.
A manual trig can be started at any time. This results in a recording of the actual
values from all recorded channels.
Prepare the IED for verification of settings as outlined in section "Overview" and
section "Preparing for test" in this chapter.
The result from the event recorder can be viewed on the local HMI or, after upload,
in PCM 600.
Prepare the IED for verification of settings as outlined in section "Overview" and
section "Preparing for test" in this chapter.
When testing binary inputs, the event list (EL) might be used instead. No uploading
or analyzing of registrations is then needed since the event list keeps running,
independent of start of disturbance registration.
Procedure
Procedure
1. Check the configuration of binary inputs that control the selection of the active
setting group.
2. Browse the ‘ActiveGroup’ menu to achieve information about the active setting
group.
The ActiveGroup menu is located in the local HMI under:
Test/Function status/Setting groups
3. Connect the appropriate dc voltage to the corresponding binary input of the IED
and observe the information presented on the HMI display.
The displayed information must always correspond to the activated input.
4. Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting
groups are described in the corresponding PCM documents and instructions for
the operators within the SCS are included in the SCS documentation.
Continue to test another function or end the test by changing the test mode setting to
off. Restore connections and settings to their original values, if they were changed
for testing purposes.
12.4.1.1 General
Prepare the IED for verification of settings as outlined in section "Overview" and
section "Preparing for test" in this chapter.
The typical connection between the 3-Ph current test set and REB 670 terminals is
shown in figure 55.
3-Phcurrent
T estSet
L1 L2 L3 N
en01000112.vsd
Figure 55: Typical test connection for CT3 current input when COMBITEST
RTXP 24 test switch is delivered together with one-phase REB 670
terminal
Testing will be explained from one general current input CTx (i.e. x=1, 2,..., Nmax;
where Nmax is equal to the maximum number of used CT inputs). Follow the
following test instructions for all used current inputs in REB 670 terminal.
Procedure
1. Connect the test set for injection of 3-phase current (or if not available 1-phase
current) to the current terminals of CTx input of REB 670 terminal.
2. Check and write down the value for the configuration parameter “CT Prim Input
x” which should correspond to the rated primary CT current of the main CT
connected to CTx current input.
3. Check the value for the configuration parameter ZoneSel/CTx. If this value is
“Fixed to ZA”, “Fixed to ZB” or “Fixed to ZA & - ZB” proceed with next point.
(If this value is “CtrlIncludes” energize the binary input “CTRLZA” in order to
include the current from this current input into ZA measurement.)
4. If this value is “CtrlExcludes” de-energize the binary input “CTRLZA” in order
to include the current from this current input into ZA measurement.
5. Make sure that, when used, Check zone is properly set and enabled.
6. Increase the current in phase L1 until the correct differential function (i.e. either
ZA or ZB) operates and note the incoming and differential currents at the
moment of operation.
7. Check that trip and alarm contacts operate according to the scheme wiring.
8. Check that trip information is stored in the Event List (if connected).
9. Switch-off the current
10. Check that trip reset information is stored in the Event List (if connected).
11. Check in the same way the function by injecting current in phases L2 and L3.
12. Inject a symmetrical 3-phase current and note the operate value (possible with
3-phase test set only).
13. Connect the timer and set the current to five times the set value for
DiffOperLevel parameter.
14. Switch on the current and note the operate time.
15. If the value for the configuration parameter ZoneSel/CTx is “CtrlIncludes” de-
energize the binary input “CTRLZA” and now energize the binary input
“CTRLZB” in order to include the current from this current input into ZB
measurement.
16. If the value for the configuration parameter ZoneSel/CTx is “CtrlExcludes”
energize the binary input “CTRLZA” and now de-energize binary input
“CTRLZB” in order to include the current from this current input into ZB
measurement.
17. Repeat the steps from 4 to 12 for zone ZB
18. If the value for the configuration parameter ZoneSel/CTx is “CtrlIncludes”
energize now both binary inputs “CTRLZA” and “CTRLZB” in order to include
the current from this current input into both measuring zone simultaneously.
19. If the value for the configuration parameter ZoneSel/CTx is “CtrlExcludes” de-
energize now both the binary inputs “CTRLZA” and “CTRLZB” in order to
include the current from this current input into both measuring zone
simultaneously.
20. Make sure that the dedicated binary output “ACTIVE” from Zone
Interconnection block has logical value one.
21. Repeat the steps from 4 to 12. Note that now both zones shall operate during
these tests.
22. Check in the same way that the differential function properly operates for all
used and connected CT inputs.
For stability test one current input shall always be used as a reference input. The
reference current input then shall be tested for stability against all other current inputs
in REB 670 terminal. It is recommended to use current input CT1 as the reference
current input. The typical connection between the 3-Ph current test set and REB 670
terminals for this type of tests is shown in figure 56.
3-Ph current
Test Set
L1 L2 L3 N
I1 I2
2A
X401 2B
AI01 1 3A
3B
2 2A
X401 2B
AI01 1 3A
3B
2 2A
X401 2B
AI01 1 3A
3B
2
en01000113.vsd
Figure 56: Typical test connection for CT3 and CT1 current input phase L1 when
COMBITEST RTXP 24 test switch is delivered together with one-
phase REB 670 terminal
The connections are shown for phase L1 only. Similar connection shall be used for
testing phase L2 & L3 also.
Testing will be explained for one general current input CTx (i.e. x=2, 3,...,Nmax;
where Nmax is equal to the maximum number of used CT inputs).
Procedure
1. Connect the currents I1 and I2 from the 3-ph test set test set to the current
terminals of CT1 & CTx inputs of REB 670 terminal as shown in figure 56.
2. Make sure that current measurement from CT1 and CTx inputs are included into
the same differential zone (see previous test instruction for more details)
3. Set the current I2 (i.e. current connected to reference current input CT1) to the
nominal value of 1A (or to 5A if CT1 is connected to a main CT with 5A
secondary rating) at zero degree.
4. Set the current I1 (i.e. connected to current input CTx) to the value calculated
by the following formula:
(Equation 1)
where:
IXr is rated secondary current of the current input CTx (i.e. normally 1A or 5A)
CT Prim Input1 is the rated primary CT current of the main CT connected to CT1 current input
CT Prim Inputx is the rated primary CT current of the main CT connected to CTx current input
5. Set the phase angle of current I1 to 180 degrees if both current inputs (i.e. CT1
and CTx) has the same sign for entered configuration parameters CT Prim
Input1 & CT Prim Input3 (i.e. both positive or both negative). Otherwise set the
phase angle of current I1 to zero degree.
6. Inject these two currents into REB 670. Differential function shall be stable.
Write down the service values for incoming and differential currents for phase
L1. Differential current should be very small.
7. Switch off the currents.
8. Repeat the same test procedure for phases L2 and L3.
For open CT test two current input shall always be used. The typical connection
between the 3-Ph current test set and REB 670 terminals for this type of tests is shown
in figure 56.
The connections are shown for phase L1 only. Similar connection shall be used for
testing phase L2 & L3 also.
Procedure
1. Connect the currents I1 and I2 from the 3-ph test set test set to the current
terminals of CT1 & CT3 inputs of REB 670 terminal as shown in figure 56.
2. Make sure that current measurement from CT1 and CT3 inputs are included into
the same differential zone (see previous test instructions for more details).
3. Set the current I2 (i.e. current connected to input CT1) to the nominal value of
1A (or to 5A if CT1 is connected to a main CT with 5A secondary rating) at
zero degree.
4. Set the current I1 (i.e. connected to current input CT3) to the value calculated
by the following formula:
(Equation 2)
where:
I3r is rated secondary current of the current input CT3 (i.e. normally 1A or 5A)
CT Prim Input1 is the rated primary CT current of the main CT connected to CT1 current input
CT Prim Input3 is the rated primary CT current of the main CT connected to CT3 current input
5. Check that the value of the product I1*CT Prim Input3 is bigger that the value
of the product 1.1*Open CT Level (this is just a check to see that enough current
will be disconnected later during testing in order for open CT algorithm to
operate).
6. Set the phase angle of current I1 to 180 degrees if both current inputs (i.e. CT1
and CT3) has the same sign for entered configuration parameters CT Prim
Input1 & CT Prim Input3 (i.e. both positive or both negative). Otherwise set the
phase angle of current I1 to 0 degree.
7. Inject these two currents into REB 670 for approximately 5s. Differential
function shall be stable. Write down the service values for incoming and
differential currents for phase L1. Differential current should be very small.
8. Then switch off the current I2 only (i.e. set its magnitude back to 0A).
9. Open CT condition shall be detected by the IED. The differential function will
be blocked.
10. Check that open CT alarm contacts operate according to the scheme wiring.
11. Check that open CT information is stored in the Event List (if connected).
12. Switch-off the currents.
13. Reset the open CT blocking by using the Reset menu on built-in HMI.
14. Check that open CT reset information is stored in the Event List (if connected).
15. Repeat the same test procedure for phases L2 and L3.
For open CT test two current input shall be always used. The typical connection
between the 3-Ph current test set and REB 670 terminals for this type of tests is shown
in figure 56.
The connections are shown for phase L1 only. Similar connection shall be used for
testing phase L2 & L3 also.
Procedure
1. Connect the currents I1 and I2 from the 3-ph test set to the current terminals of
CT1 & CT3 inputs of REB 670 terminal as shown in figure 56.
2. Make sure that current measurement from CT1 and CT3 inputs are included into
the same differential zone (see previous test instructions for more details).
3. Set the current I2 (i.e. current connected to current input CT1) to the nominal
value of 1A (or to 5A if CT1 is connected to a main CT with 5A secondary
rating) at zero degree.
4. Set the current I1 (i.e. connected to current input CT3) to the value calculated
by the following formula:
(Equation 3)
where:
I3r is rated secondary current of the current input CT3 (i.e. normally 1A or 5A)
CT Prim Input1 is the rated primary CT current of the main CT connected to CT1 current input
CT Prim Input3 is the rated primary CT current of the main CT connected to CT3 current input
5. Check that the value of the product 0.15*I1*CT Prim Input1 is bigger that the
pre-set value of OCTOperLev. If it is not increase current into CT1 input until
this condition is satisfied and change current into input CT3 accordingly.
6. Set the phase angle of current I1 to 180 degrees if both current inputs (i.e. CT1
and CT3) has the same sign for entered configuration parameters CT Prim
Input1 & CT Prim Input3 (i.e. both positive or both negative). Otherwise set the
phase angle of current I1 to 0 degree.
7. Inject these two currents into REB 670. Differential function shall be stable.
Write down the service values for incoming and differential currents for phase
L1. Differential current should be approximately 15% of the incoming current.
8. After pre-set time determined by parameter tSlow OCT, open CT condition shall
be detected by the IED. The differential function will be blocked.
9. Check that open CT alarm contacts operate according to the scheme wiring.
10. Check that open CT information is stored in the Event List (if connected).
11. Switch-off the currents.
12. Reset the open CT blocking by using the Reset menu on built-in HMI.
13. Check that open CT reset information is stored in the Event List.
14. Repeat the same test procedure for phases L2 and L3.
Continue to test another function or end the test by changing the test mode setting to
off. Restore connections and settings to their original values, if they were changed
for testing purposes.
The trip circuits are tested as part of the secondary/primary injection test.
Check that the circuit breakers associated with the REB 670 protection scheme
operate when the tripping relays are activated. The trip relays are conveniently
activated by secondary injection to activate a suitable protection function.
Procedure
1. Connect the test set for appropriate current injection to the appropriate IED
terminals.
If there is any configuration logic which is used to enable/block any of 4
available overcurrent steps, make sure that step under test is enabled (i.e. end
fault protection).
If 1 of 3 currents for operation is chosen: Connect the injection current to
terminals L1 and neutral.
If 2 of 3 currents for operation is chosen: Connect the injection current into
terminal L1 and out from terminal L2.
If 3 of 3 currents for operation is chosen: Connect the symmetrical 3 phase
injection current into terminals L1, L2 and L3.
2. Connect the test set for the appropriate three-phase voltage injection to the IED
terminals L1, L2 and L3. The protection shall be fed with a symmetrical three
phase voltage.
3. Set the injected polarizing voltage slightly larger than the set minimum
polarizing voltage (default is 5% of Ur) and set the injection current to lag the
appropriate voltage by an angle of about 80° if forward directional function is
selected.
If 1 of 3 currents for operation is chosen: The voltage angle of phase L1 is the
reference.
If 2 of 3 currents for operation is chosen: The voltage angle of phase L1 – the
voltage angle of L2 is the reference.
If 3 of 3 currents for operation is chosen: The voltage angle of phase L1 is the
reference.
If reverse directional function is selected, set the injection current to lag the
polarizing voltage by an angle equal to 80° + 180°.
4. Increase the injected current and note the operated value of the studied step of
the function.
5. Decrease the current slowly and note the reset value.
6. If the test has been performed by injection of current in phase L1, repeat the test
when injecting current into terminals L2 and L3 with polarizing voltage
connected to terminals L2 respectively L3 (1 of 3 currents for operation).
7. If the test has been performed by injection of current in phases L1 – L2, repeat
the test when injecting current into terminals L2 – L3 and L3 – L1 with
appropriate phase angle of injected currents.
8. Block higher set stages when testing lower set stages according to below.
9. Connect a trip output contact to a timer.
10. Set the injected current to 200% of the operate level of the tested stage, switch
on the current and check the time delay.
For inverse time curves, check the operate time at a current equal to 110% of
the operate current for tmin.
11. Check that all trip and start contacts operate according to the configuration
(signal matrixes)
12. Reverse the direction of the injected current and check that the protection does
not operate.
13. If 2 of 3 or 3 of 3 currents for operation is chosen: Check that the function will
not operate with current in one phase only.
14. Repeat the above-described tests for the higher set stages.
15. Finally check that start and trip information is stored in the event menu.
Continue to test another function or end the test by changing the test mode setting to
off. Restore connections and settings to their original values, if they were changed
for testing purposes.
Procedure
1. Connect the test set for appropriate current injection to the appropriate IED
terminals.
If there is any configuration logic which is used to enable/block any of 4
available overcurrent steps, make sure that step under test is enabled (i.e. end
fault protection).
2. Increase the injected current and note the operated value of the studied step of
the function.
3. Decrease the current slowly and note the reset value.
4. Block higher set stages when testing lower set stages according to below.
5. Connect a trip output contact to a timer.
6. Set the injected current to 200% of the operate level of the tested stage, switch
on the current and check the time delay.
For inverse time curves, check the operate time at a current equal to 110% of
the operate current for tmin.
7. Check that all trip and start contacts operate according to the configuration
(signal matrixes)
8. Repeat the above-described tests for the higher set stages.
9. Finally check that start and trip information is stored in the event menu.
Continue to test another function or end the test by changing the test mode setting to
off. Restore connections and settings to their original values, if they were changed
for testing purposes.
The function(s) has to be set and configured before the testing can start. The BFP
function is highly flexible in that it permits a choice of functional and tripping modes.
The various modes are checked at the factory as part of the design verification. In
certain cases only modes with a high probability of coming into operation need to be
checked, in order to verify the configuration and settings.
• Calculated settings
• Valid configuration diagram for the IED
• Valid terminal diagram for the IED
• Technical reference manual
• Three-phase test equipment
The test equipment should be able to provide a three-phase supply of currents (and
for some start functions also voltage). The magnitude and angle of currents (and
voltages) should be possible to vary.
Make sure the IED is prepared for test before starting the test session. Consider the
logic diagram of the function when performing the test. The response from a test can
be viewed in different ways:
To verify the settings in the most common back-up trip mode “1 out of 3” it is
sufficient to test phase-to-earth faults.
At mode “2 out of 4” the Phase current setting, IP> can be checked by single phase
injection where the return current is connected to the summated current input. The
value of residual (EF) current “IN” set lower than IP> is easiest checked in back-up
trip mode “1 out of 4”.
The check of the IP> current level is best made in FunctionMode=Current and
BuTripMode= “1 out of 3” or “2 out of 4”.
Procedure
1. Apply the fault condition, including start of BFP, with a current below set
IP>.
2. Repeat the fault condition and increase the current in steps until a trip occurs.
3. Compare the result with the set IP>.
4. Disconnect AC and start input signals.
Note: If “No I> check” or “Retrip off” is set, only back-up trip can be used to
check set IP>.
12.5.3.2 Checking the residual (EF) current operate value “IN>” set below
“IP>”
The check of low set IN> current level is best made in FunciontMode= Current and
BuTripMode= “1 out of 4”.
Procedure
1. Apply the fault condition, including start of BFP, with a current just below set
IN>.
2. Repeat the fault condition and increase the current in steps until trip appears.
3. Compare the result with the set IN>.
4. Disconnect AC and start input signals.
The check of the set times can be made in connection with the check of operate values
above. Choose the applicable function and trip mode, such as FunctMode= Current
and RetripMode = I> check.
Procedure
1. Apply the fault condition, including start of BFP, well above the set current
value. Measure time from “Start of BFP”.
2. Check the re-trip t1 and back-up trip times t2 and t3
In applicable cases the back-up trip for multi-phase start “t2MPh” and back-up
trip 2, “t2 + t3” can also be checked. For check of “t2MPh” a two-phase or three-
phase start shall be applied.
3. Disconnect AC and start input signals.
Choose the mode below, which corresponds to the actual case. In the cases below it
is assumed that FunctionMode = Current is selected.
Procedure
1. Apply the fault condition, including start of BFP, with phase current well above
set value “IP”
2. Arrange switching the current off, with a margin before back-up trip time, t2.
It may be made at issue of re-trip command.
3. Check that re-trip is achieved, if selected, but no back-up trip.
4. Disconnect AC and start input signals.
The normal mode BuTripMode = “1 out of 3” should have been verified in the tests
above. In applicable cases the modes “1 out of 4” and “2 out of 4” can be checked.
Choose the mode below, which corresponds to the actual case.
Procedure
Procedure
below IP>, but of such value that the residual (EF) current (3I0) will be above
set value IN>.
5. Verify that back-up trip is not achieved.
6. Disconnect AC and start input signals.
Applies in a case where signal “CB faulty and unable to trip” is connected to input
CBFLT.
Procedure
1. Repeat the check of back-up trip time. Disconnect current and start input signals.
2. Activate the input CBFLT. The output CBALARM (CB faulty alarm) should
appear after set time tCBAlarm. Keep the input activated.
3. Apply the fault condition, including start of BFP, with current above set current
value.
4. Verify that back-up trip is obtained without intentional delay, e.g. within 20 ms
from application of start.
5. Disconnect injected AC and input signals.
It is assumed that re-trip without current check is selected, RetripMode = No I> check.
Procedure
Checking the case with fault current above set value IP>Pickup_PH
The operation shall be as in FunctionMode = Current.
Procedure
Procedure
Continue to test another function or end the test by changing the test mode setting to
off. Restore connections and settings to their original values, if they were changed
for testing purposes.
The function(s) has to be set and configured before the testing can start. The BFP
function is highly flexible in that it permits a choice of functional and tripping modes.
The various modes are checked at the factory as part of the design verification. In
certain cases only modes with a high probability of coming into operation need to be
checked, in order to verify the configuration and settings.
• Calculated settings
• Valid configuration diagram for the IED
• Valid terminal diagram for the IED
• Technical reference manual
• Single phase test equipment
The test equipment should be able to provide a single phase supply of currents. The
magnitude of currents should be possible to vary.
Make sure the IED is prepared for test before starting the test session. Consider the
logic diagram of the function when performing the test. The response from a test can
be viewed in different ways:
Procedure
1. Apply the fault condition, including start of BFP, with a current below set
IP>.
2. Repeat the fault condition and increase the current in steps until a trip occurs.
3. Compare the result with the set IP>.
4. Disconnect AC and start input signals.
Note: If “No I> check” or “Retrip off” is set, only back-up trip can be used to
check set IP>.
The check of the set times can be made in connection with the check of operate values
above. Choose the applicable function and trip mode, such as FunctMode= Current
and RetripMode = I> check.
Procedure
1. Apply the fault condition, including start of BFP, well above the set current
value. Measure time from “Start of BFP”.
2. Check the re-trip t1 and back-up trip times t2 and t3
3. Disconnect AC and start input signals.
Choose the mode below, which corresponds to the actual case. In the cases below it
is assumed that FunctionMode = Current is selected.
Procedure
1. Apply the fault condition, including start of BFP, with phase current well above
set value “IP”
2. Arrange switching the current off, with a margin before back-up trip time, t2.
It may be made at issue of re-trip command.
3. Check that re-trip is achieved, if selected, but no back-up trip.
4. Disconnect AC and start input signals.
Applies in a case where signal “CB faulty and unable to trip” is connected to input
CBFLT.
Procedure
1. Repeat the check of back-up trip time. Disconnect current and start input signals.
2. Activate the input CBFLT. The output CBALARM (CB faulty alarm) should
appear after set time tCBAlarm. Keep the input activated.
3. Apply the fault condition, including start of BFP, with current above set current
value.
4. Verify that back-up trip is obtained without intentional delay, e.g. within 20 ms
from application of start.
5. Disconnect injected AC and input signals.
It is assumed that re-trip without current check is selected, RetripMode = No I> check.
Procedure
7. Arrange disconnection of CB closed signal(s) well before set back-up trip time
t2.
8. Verify that back-up trip is not achieved.
9. Disconnect injected AC and start input signals.
Checking the case with fault current above set value IP>Pickup_PH
The operation shall be as in FunctionMode = Current.
Procedure
Procedure
Continue to test another function or end the test by changing the test mode setting to
off. Restore connections and settings to their original values, if they were changed
for testing purposes.
12.6 Control
Prepare the IED for verification of settings as outlined in the section "Overview" and
section "Preparing for test" in this chapter.
The verification test is performed together with protection and trip functions.
Figure 60 illustrates a suggested testing arrangement, where the circuit-breaker (CB)
is simulated by an external bi-stable relay (BR), for example a relay type RXMVB2
or RXMD or Breaker Simulator of ABB. The following manual switches are used:
Use a secondary injection relay test set to operate the protection function. The test
set shall be switched off when a trip signal is given or when the BR comes to open
position to simulate real conditions.
The CB simulation can be made more elaborate, including simulation of the operating
gear condition, CBREADY of either the type ready for a Close-Open (CO) cycle, or
the type ready for an Open-Close -Open (OCO) cycle.
The CB condition CBREADY of a type, CO, shall be high (true) until a closing
operation is performed. It then goes low (false) for a recharging time of about 5 - 10
s. After that it is high again.
A CB condition CBREADY of a type, OCO shall be high (true) before and during
tripping (Start reclosing). During tripping it goes low for a recharging time, e.g. 10
s. It may thus be low at the instant of reclosing. After each Open or Close operation
it may need a recharging period before it goes high again.
IED
AR01 - CLOSE CB
BR
SC
Trip
ST
AR01 - CB POS
SRY
AR01 - CB READY
To test
set
+ -
en04000202.vsd
Procedure
that is not possible, other means of time measurement and recording should be
arranged.
Procedure
Select the test cases to be run according to what is applicable to the particular
application. It may for instance be a) three-phase single-shot reclosing, b) two-shot
reclosing or c) single-phase and three-phase single shot reclosing. Below a case with
single-phase and three-phase single-shot reclosing is illustrated.
Procedure
Before a new reclosing sequence can be run, the CBREADY and CBPOS (CB
closed) must be set manually.
7. Repeat the sequence by simulating a three-phase transient and permanent faults,
and other applicable cases, such as signal to STARTHS and High-speed
reclosing.
If just single-phase reclosing is selected, FirstShot=1ph, a check can be run to
make sure that a three-phase trip does not result in any reclosing. Other similar
cases can be checked as required.
1. Check that the reclosing function is operative, e.g. by making a reclosing shot.
Keep the CBREADY signal high.
2. Set the breaker simulating relay BR in Open position.
3. Close the BR relay and apply immediately a fault and thereby a START signal.
4. Check that no reclosing takes place.
Procedure
Reconnect any links or connection terminals, which may have been opened for
the tests.
4. Reset indications, alarms and disturbance recordings.
Clearing of the disturbance report must be done via the PCM 600 using the
Disturbance handling tool.
Continue to test another function or end the test by changing the test mode setting to
off. Restore connections and settings to their original values, if they were changed
for testing purposes.
12.7 Monitoring
During testing, the IED can be set when in test mode from the PST. The functionality
of the event reporting during test mode is set from the PST as follows:
In Test Mode, individual event blocks can be blocked from the PCM 600.
Individually event blocks can also be blocked from the local HMI under the menu:
Test of the multiple command function block and multiple trasmit is recommended
to be performed in a system, that is, either in a complete delivery system as an
acceptance test (FAT/SAT) or as parts of that system, because the command function
blocks are connected in a delivery-specific way between bays and the station level
and transmit.
Command and trasmit function blocks included in the operation of different built-in
functions must be tested at the same time as their corresponding functions.
To perform a test of the binary signal transfer to remote end the hardware (LDCM)
and binary input and output signals to transfer must be configured as required by the
application.
There are two types of internal self-supervision of the binary signal transfer to remote
end:
Status for inputs and outputs as well as self-supervision status are available from the
local HMI under the menus:
Test correct functionality by simulating different kind of faults. Also check that sent
and received data is correctly transmitted and read.
A test connection is shown in figure 61. A binary input signal (BI) at End1 is
configured to be transferred through the communication link to End2. At End2 the
received signal is configured to control a binary output (BO). Check at End2 that the
BI signal is received and the BO operates.
Repeat the test for all the signals configured to be transmitted over the communication
link.
A test with primary current through the protected zone is usually a final check that
the current circuits are correctly connected to the IED protection scheme. It is
important to have an appropriate source, which is able to inject sufficient current in
the primary circuit in order to distinguish between noise and real injected current.
Therefore it is recommended that the injection current should be at least 10% of rated
CT primary current.
REx 670
Primary Injection
Test Set CT Input
1200/1
Optional equipment
(i.e,Test Switch,CB
Fail relay,other relays)
en05000470.vsd
Testing will be explained from one general current input CTx (i.e. x=1, 2,..., Nmax;
where Nmax is equal to the maximum number of used CT inputs).
Follow the following test instructions for all used current inputs in a IED 670.
Procedure
1. Connect the test set for injection primary current to the main CT connected to
the current IEDs of CTx input of the IED as shown in figure 62.
2. Make sure that current measurement from the CTx input are included in one of
the differential zones.
3. Inject the primary current in phase L1 and note the incoming and differential
currents on the IED HMI display. The values of the incoming and the differential
currents shall correspond to the injected primary current.
4. Check that the current is present only in the phase being tested.
5. If injected current is high enough check that trip contacts operate according to
the scheme wiring.
6. Check that trip information is stored in the Disturbance recorder and Event list
(if connected).
7. Switch-off the current.
8. Check in the same way the function by injecting current in phases L2 and L3
It is recommended that each primary CB is tripped directly from the protection scheme
at least once during these tests. This will confirm the trip circuit connection between
the protection scheme and the CB.
REB 670
Primary Injection
Test Set
en05000307_1.vsd
Figure 63: Typical test connection for primary injection which should confirm the
stability of the main CT connected to current inputs of the IED.
For this type of primary injection tests a suitable current source should be applied
across the primary windings of two CTs connected in series as shown in figure 63.
The testing is normally done on one phase at the time. The currents in the secondary
winding of these CTs are then opposite in phase. The differential current displayed
by the IED should be negligible while the incoming current displayed should be equal
to the value of the injected primary current. The IED must not issue the trip command
during these tests. If it trips or the differential current has a high value it usually means
that there is a wiring problem in the CT circuits connected to the current input CTx
(i.e. a differential current equal to twice the injection current probably indicates wrong
polarity of the main CT connected to the CTx current input). This problem must be
solved before the protection scheme is put in service.
Procedure
1. Connect the test set for primary current injection to the main CTs as shown in
figure 63.
2. Make sure that current measurement from two used CT inputs are included in
the same differential zone.
3. Inject the primary current in phase L1 and note the incoming and differential
currents on the IED HMI display.
The value of the incoming current for phase L1 shall correspond to the injected
primary current. The value of the differential current for phase L1 shall be
negligible.
4. Check that the current is present only in the phase being tested.
5. Switch the current off.
6. Check the function in phases L2 and L3 by injecting current in the same way.
The busbar disconnector replica is used in order to provide the information to the
REB 670 differential IEDs which of the measured CT currents shall be included
within different differential zones. In order to form the busbar disconnector replica
it is necessary to use the auxiliary contacts from each busbar disconnector. For more
information please refer to the Application Manual for REB 670 IED.
After all these tests are conducted the REB 670 protection scheme can be put in
service.
The protection relay system is in an "on-guard" situation where they can be inactive
for several years and then suddenly be required to operate within fractions of a second.
This means that maintenance testing with certain time intervals should be performed
to detect failures of the protection IED or the surrounding circuits. This is a
complement to the advanced self supervision in the modern protection IED.
Relays are not expected to deteriorate with usage but extreme conditions such as
mechanical shocks, AC or DC transients, high ambient temperatures, and high air
humidity always have a certain likelihood of causing damages.
Delivered equipment undergoes extensive testing and quality control in the ABB
manufacturing program. All types of IEDs and their integral components have been
subject to extensive laboratory testing during the development and design work. Prior
to series production of a specific IED, it is Type tested according to national and
international standards. Each individual relay in normal production is individually
tested and calibrated before delivery.
During the design of the station certain steps shall be taken to limit the risk of failures
e.g. all relay coils are connected to negative potential to earth to prevent contact
corrosion due to electrolyte.
During commissioning all protection functions shall be verified with the setting
values used at each plant. The commissioning tests must include verification of all
circuits by green-lining the circuit diagrams and the configuration diagrams for the
used functions.
Further, the settings for protection functions are tested and recorded carefully as
outlined for the future periodic maintenance tests described below.
The final testing will include primary verification of all directional functions where
load currents is checked on the IED through the LHMI or the PCM 600 tool. The
amplitudes and angles of all currents and voltages should be checked and the
symmetry verified.
Directional functions have information about the measured direction and for example
measured impedance. These values must be checked and verified as correct with the
export or import of power available.
Finally final trip tests must be performed. This involves activation of protection
functions or tripping outputs with the circuit breaker closed and the tripping of the
breaker verified. When several breakers are involved each must be checked
individually and it must be verified that the other involved breakers are not tripped
at the same time.
The periodicity of all tests depends on several factors, for example the importance of
the installation, environment conditions, simple or complex equipment, static or
electromechanical relays etc.
The normal maintenance praxis of the user should be followed. However ABB
proposal is to test:
First maintenance test should always be carried out after the first half
year of service.
When protection IEDs are combined with built-in control the test
interval can be increased drastically, up to for instance 15 years,
because the IED continuously reads service values, operates the
breakers etc.
Testing of protection relays shall preferably be made with the primary circuit de-
energized. The relay cannot protect the circuit during testing. Trained personnel may
test one relay at a time on live circuits where redundant protection is installed and de-
energization of the primary circuit is not allowed.
ABB protection relays are preferably tested by aid of components from the
COMBITEST testing system described in information B03-9510 E. Main
components are RTXP 8/18/24 test switch located to the left in each protection relay
and RTXH 8/18/24 test handle which is inserted in test switch at secondary testing.
All necessary operations such as opening of trip circuits, short-circuiting of current
circuits and opening of voltage circuits are automatically performed in the right order
to allow for simple and safe secondary testing even with the object in service.
14.3.2.1 Preparation
Before starting maintenance testing the test engineers should scrutinize applicable
circuit diagrams and have the following documentation available: Test instructions
for protection IEDs to be tested. Test records from previous commissioning and
maintenance tests. List of valid settings. Blank test records to fill in measured values.
14.3.2.2 Recording
It is of utmost importance to carefully record the test results. Special test sheets
covering the frequency of test, date of test and achieved test values should be used.
Relay setting list and protocols from previous tests should be available and all results
should be compared for differences. At component failures, spare equipment is used
and set to the requested value. A note of the exchange is made and the new measured
values are recorded. Test records for several years of testing should be stored in a
common file for a station, or a part of a station, to give a simple overview of the period
of testing and achieved test values. These test records are valuable when analysis of
service disturbances shall be done.
The periodic maintenance test is done by secondary injection from a portable test set.
Each protection shall be tested according to the secondary injection test information
for the specific protection IED. Only the setting values adopted shall be checked for
each protection function. If the discrepancy between obtained value and requested
set value is too big the setting should be adjusted, the new value recorded and a note
should be made in the test record.
When inserting the test handle the alarm and event signalling is normally blocked.
This is done in IED 670 by setting the Event reporting to off during the test. This can
be done when the test handle is inserted or the IED is set to test mode from the LHMI.
At the end of the secondary injection test it should be checked that the event and alarm
signalling is correct by activating the events and performing some selected tests.
Once secondary testing has been completed it should be checked that no self
supervision signals are activated continuously or sporadically. Especially check the
time synchronizsation system, GPS or other, and communication signals, both station
communication(61850/SPA/LON..) and remote communication, for example line the
differential communication system.
When the protection IED undergoes an operational check, a tripping pulse is normally
obtained on one or more of the output contacts and preferably on the test switch. The
healthy circuit is of utmost importance for the protection operation. If the circuit is
not provided with a continuous trip circuit supervision it is possible to check that
circuit is really closed when the test-plug handle has been removed by using a high-
ohmic voltmeter and measuring between the plus and the trip output on the panel.
The measurement is then done through the tripping magnet of the circuit breaker
(note! Breaker must be closed) and therefore the complete tripping circuit is checked.
Please observe that the test system does not have its built-in security during this test.
If the instrument should be set on Amp instead of Volts, the circuit breaker naturally
is tripped, therefore, greatest care is necessary.
Trip circuit from trip relays to circuit breaker is often supervised by trip circuit
supervision relay. It can then be checked that a circuit is healthy by opening tripping
output terminals in the cubicle. When terminal is opened an alarm shall be achieved
on the signal system after a delay of some seconds. However, remember to close the
circuit directly after the test and tighten the terminal carefully!
After a maintenance test it is recommended to measure the service currents and service
voltages recorded by the protection IED. The service values are checked on the IED
670 local HMI or with the PCM 600 tool. Ensure that the correct values and angles
between voltages and currents are recorded. Also check the direction of directional
functions such as Distance and directional overcurrent functions.
14.3.2.8 Restoring
Thus a list should be prepared of all items disturbed during test so that all can be put
back into service quickly and without overlooking something. It should be put back
into service item by item and signed by the responsible engineer.
Diagnostics/IED status/General
Under the Diagnostics menus, indications of a possible internal failure (serious fault)
or internal warning (minor problem) are listed.
Also the internal signals, such as INT--FAIL and INT--WARNING can be connected
to binary output contacts for signalling to a control room.
In the IED Status - Information, the present information from the self-supervision
function can be viewed. Indications of failure or warnings for each hardware module
are provided, as well as information about the external time synchronization and the
internal clock. All according to table 17. Loss of time synchronization can be
considered as a warning only. The IED 670 has full functionality without time
synchronization.
When an internal fault has occurred, you can retrieve extensive information about the
fault from the list of internal events available in the SMS part:
The list of internal events provides valuable information, which can be used during
commissioning and during fault tracing.
The internal events are time tagged with a resolution of 1 ms and stored in a list. The
list can store up to 40 events. The list is based on the FIFO principle, when it is full,
the oldest event is overwritten. The list cannot be cleared; its content cannot be erased.
The internal events in this list not only refer to faults in the IED, but also to other
activities, such as change of settings, clearing of disturbance reports, and loss of
external time synchronization.
The information can only be retrieved with the aid of the PST software package. The
PC can be connected either to the port at the front or at the rear of the IED.
Table 18: Events available for the internal event list in the IED
Event message: Description Generating signal:
INT--FAIL Off Internal fail status INT--FAIL (reset event)
INT--FAIL INT--FAIL (set event)
INT--WARNING Off Internal warning status lNT--WARNING (reset event)
INT--WARNING lNT--WARNING (set event)
INT--NUMFAIL Off Numerical module fatal error INT--NUMFAIL (reset event)
status
INT--NUMFAIL INT--NUMFAIL (set event)
INT--NUMWARN Off Numerical module non-fatal error INT--NUMWARN (reset event)
status
INT--NUMWARN INT--NUMWARN (set event)
IOn--Error Off In/Out module No. n status IOn--Error (reset event)
IOn--Error IOn--Error (set event)
ADMn-Error Off Analog/Digital module No. n ADMn-Error (reset event)
status
ADMn-Error ADMn-Error (set event)
MIM1-Error Off mA-input module status MIM1-Error (reset event)
MIM1-Error MIM1-Error (set event)
INT--RTC Off Real Time Clock (RTC) status INT--RTC (reset event)
INT--RTC INT--RTC (set event)
INT--TSYNC Off External time synchronization INT--TSYNC (reset event)
status
Table continued on next page
The events in the internal event list are time tagged with a resolution of 1 ms.
This means that when using the PC for fault tracing, it provides information on the:
An alternative is to open the IED and send only the faulty circuit board to ABB for
repair. When a printed circuit board is sent to ABB, it must always be placed in a
metallic, ESD-proof, protection bag. The user can also purchase separate replacement
modules.
Most electronic components are sensitive to electrostatic discharge and latent damage
may occur. Please observe usual procedures for handling electronics and also use an
ESD wrist strap. A semi-conducting layer must be placed on the workbench and
connected to earth.
If the IED 670 has been calibrated with the system inputs, the calibration procedure
must be performed again to maintain the total system accuracy.
If a IED 670 needs to be repaired, the whole IED must be removed and sent to an
ABB Logistic Center. Before returning the material, an inquiry must be sent to the
ABB Logistic Center.
e-mail: [email protected]
15.4 Maintenance
Instructions from the power network company and other maintenance directives valid
for maintenance of the power system must be followed.
Section 16 Glossary
16.1 Glossary
AC Alternating current
A/D converter Analog to digital converter
ADBS Amplitude dead -band supervision
ADM Analog digital conversion module, with time synchronization
ANSI American National Standards Institute
AR Autoreclosing
ArgNegRes Setting parameter/ZD/
ArgDir Setting parameter/ZD/
ASCT Auxiliary summation current transformer
ASD Adaptive signal detection
AWG American Wire Gauge standard
BBP Busbar protection
BFP Breaker failure protection
BIM Binary input module
BOM Binary output module
BR External bi-stable relay
BS British standard
BSR Binary signal transfer function, receiver blocks
BST Binary signal transfer function, transmit blocks
C37.94 IEEE/ANSI protocol used when sending binary signals
between IEDs
CAN Controller Area Network. ISO standard (ISO 11898) for serial
communication
CAP 531 Configuration and programming tool
CB Circuit breaker
CBM Combined backplane module
CCITT Consultative Committee for International Telegraph and
Telephony. A United Nations sponsored standards body
within the International Telecommunications Union.
CCM CAN carrier module
CCVT Capacitive Coupled Voltage Transformer
Class C Protection Current Transformer class as per IEEE/ ANSI
CMPPS Combined mega pulses per second
CO cycle Close-open cycle
Co-directional Way of transmitting G.703 over a balanced line. Involves two
twisted pairs making it possible to transmit information in both
directions
COMTRADE Standard format according to IEC 60255-24
Contra-directional Way of transmitting G.703 over a balanced line. Involves four
twisted pairs of with two are used for transmitting data in both
directions, and two pairs for transmitting clock signals
CPU Central processor unit
CR Carrier receive
CRC Cyclic redundancy check
CS Carrier send
CT Current transformer
CVT Capacitive voltage transformer
DAR Delayed auto-reclosing
DARPA Defense Advanced Research Projects Agency (The US
developer of the TCP/IP protocol etc.)
DBDL Dead bus dead line
DBLL Dead bus live line
DC Direct current
DFT Discrete Fourier transform
DIP-switch Small switch mounted on a printed circuit board
DLLB Dead line live bus
DNP Distributed Network Protocol as per IEEE/ANSI Std.
1379-2000
DR Disturbance recorder
DRAM Dynamic random access memory
DRH Disturbance report handler