SE APG SnapINverter SA Dynamic Export Commisioning Setup
SE APG SnapINverter SA Dynamic Export Commisioning Setup
FRONIUS SNAPINVERTER
SA DYNAMIC EXPORT COMMISSIONING SETUP
Procedure as of 1st July 2023
Application Guide
© Fronius Australia Pty Ltd.
Version 2.0/2023
Fronius reserves all rights, in particular rights of reproduction, distribution and translation.
No part of this work may be reproduced in any way without the written consent of Fronius. It must not be saved, edited, reproduced or distributed using any
electrical or electronic system.
You are hereby reminded that the information published in this document, despite exercising the greatest of care in its preparation, is subject to change and that
neither the author nor Fronius can accept any legal liability.
Gender-specific wording refers equally to female and male form.
08/2023 1/9
1. CHANGE LOG
02/07/2023 1.0 First release (Single Inverter sites only) Fronius Australia
24/08/2023 2.0 Revised Solarweb setup and device registration Fronius Australia
2. SCOPE
This document outlines the necessary commissioning procedure required to set up the SnapINverter series
inverters to operate under a SAPN Dynamic Export agreement as a part of the SA Smart Homes Scheme. The
commissioning steps outlined in this document are “additional” steps required on top of the standard inverter
commissioning process. Please consult our other documentation for information on how to perform the standard
commissioning steps.
IMPORTANT: This version 1.0 release of this document is ONLY valid for “single inverter” and “Inverter inbuilt”
communication sites. Multi-Inverter sites are not yet possible with the “inverter inbuilt / native” solution.
For multi-inverter sites an external 3rd party devices MUST be used instead. Multi-Inverter functionality will be
released in the coming months once available.
For more information on the Dynamic Export Regulations installers are encouraged to visit the following
website:
https://www.energymining.sa.gov.au/industry/modern-energy/solar-batteries-and-smarter-homes/regulatory-
changes-for-smarter-homes/dynamic-export-limits-requirement
08/2023 2/9
NOTE: Due to the infancy of this emerging technology, there are steps in this guide that could change over
time. The user is therefore advised to always use the latest version posted on the Fronius Australia website.
.
NOTE: After completion the Datamanager MUST be running the firmware version 3.27.1-3 or greater.
If the firmware is lower than 3.27.1-3, please update the Datamanager via the WebUI firmware update trigger
OR via Solarweb.
/ Go to “Settings”
NOTE: A “service” password should have already been set when commissioning the Fronius Smart Meter.
08/2023 3/9
/ Then go to “DNO Editor”
08/2023 4/9
NOTE: The Pre-Commissioning Export Limit is an additional fallback limit which the inverter maintains before
the Dynamic Export is in place. As soon as the inverter has communication to the SAPN Utility Server the
“local” export limit will be overridden.
/ Scroll down to “Cloud Control” and tick “Allow cloud control for grid/utility compliance purposes”
/ Then click on the “tick” symbol to save
IMPORTANT: If the Cloud Control “Allow cloud control for grid/utility compliance purposes” is NOT
activated, the inverter will not be able to receive the export limit commands from SAPN.
08/2023 5/9
6. SOLAR.WEB CLOUD SETUP
6.1 Create system in Solar.web
Create a new system in Solar.web as per the standard process, see how to here:
https://www.youtube.com/watch?v=umE6-fTwRKA
For tracking of system performance, the correct site address and installation date of the system is entered
08/2023 6/9
6.3 Select & fill in Grid connection details
IMPORTANT: Ticking the “Only tick to register PV system for Dynamic/Flexible Export sites controlled
by Fronius.” box registers the inverter system with the SAPN Utility server and creates the LFDI in the
backgraound automatically. ONLY tick this box if the system is to be controlled by the Fronius cloud. i.e. Fronius
internal native solution.
DO NOT tick if controlled by Catch Relay, Zeco Marschall. The registration for these devices MUST be done by
them directly.
Also DO NOT tick this box for the SAPN Remote Disconnect functionality.
08/2023 7/9
7.2 Run “Export Capability Test”
To run the “Export Capability Test” click on the “TEST EXPORT CAPABILITY” button.
Progress will be shown of each test being performed.
IMPORTANT: the system MUST be exporting at least 500W for the test to PASS. If the export is below 500W,
you will have to perform a test at another time OR turn loads off to enable the export to exceed 500W.
NOTE: this process can take up to 15mins depending on when the last data upload was executed.
When all GREEN ticks are present the test is finished and PASSED
08/2023 8/9
END OF DOCUMENT
To access Technical articles, Quick guides, Whitepapers and other technical documents, please visit the
Tech Support Area for Installers on our website
08/2023 9/9