PROJECT

MANAGEMENT
CLASS - 1
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through I. The project is completed when all the tasks
are completed.

Q1. What is the minimum duration in which the task can be completed?

Q2. At most how many tasks can be completed in the first 9 hours from the start?

Q3. What is the shortest possible time from the start by when task F can be
completed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through G. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through J. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through F. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through K. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through K. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the details of the different steps involved in the opening of a store
after the finalization of the premises. More than one work can be completely
simultaneously as long as all work to be completed before it is over.

Q1) What is the earliest time, from the start, by which the false ceiling work can start?
a) 7th day b) 8th day c) 9th day d) 10th day
Q2 If the work is to be finished at the earliest, then the maximum number of days we
can wait to start the fire safety work is?
TITA( If you can start the work on the 9th day, then you will mention 8 as your
answer)
Q3) What is the least time from the start in which all the work can be completed?
a) 12 days b) 13 days c) 14 days d) None of these
Q4) If the work is to be done in the least possible time, what can be the maximum
time gap between the start of the networking work and the start of the flooring work?
a) 4 days b) 5 days c) 6 days d) 7 days
Healthy Bites is a fast food joint serving three items: burgers, fries and ice cream. It has two employees Anish and Bani who prepare the items ordered by the clients.
Preparation time is 10 minutes for a burger and 2 minutes for an order of ice cream. An employee can prepare only one of these items at a time. The fries are
prepared in an automatic fryer which can prepare up to 3 portions of fires at a time, and takes 5 minutes irrespective of the number of portions. The fryer does not
need an employee to constantly attend to it, and we can ignore the time taken by an employee to start and stop the fryer; thus, an employee can be engaged in
preparing other items while the frying is on. However fries cannot be prepared in anticipation of future orders.
Healthy Bites wishes to serve the orders as early as possible. The individual items in any order are served as and when ready; however, the order is considered to be
completely served only when all the items of that order are served.
The table below gives the orders of three clients and the times at which they placed their orders;

Q1) Assume that only one client’s order can be processed at any given point of time. So, Anish or Bani cannot start preparing a new order while a previous order is
being prepared. At what time is the order placed by Client 1 completely served?
A) 10:17 B) 10:10 C) 10:15 D) 10:20

Q2) Assume that only one client’s order can be processed at any given point of time. So, Anish or Bani cannot start preparing a new order while a previous order is
being prepared. At what time is the order placed by Client 3 completely served?
A) 10:35 B) 10:22 C) 10:25 D) 10:17

Q3)Suppose the employees are allowed to process multiple orders at a time, but the preference would be to finish orders of clients who placed their orders earlier.
At what time is the order placed by Client 2 completely served?

A) 10:10 B) 10:12 C) 10:15 D) 10:17

Q4) Suppose the employees are allowed to process multiple orders at a time, but the preference would be to finish orders of clients who placed their orders earlier.
Also assume that the fourth client came in only at 10:35. Between 10:00 and 10:30, for how many minutes is exactly one of the employees idle?
A) 7 B) 10 C) 15 D) 23