Repainting and Replacement of Existing Gutter
Repainting and Replacement of Existing Gutter
A. MANPOWER COST
No. of Project
Item Position Rate Cost, Php Remarks
Personnel Duration, days
Foreman 1 30 900.00 27,000.0
Safety Officer 1 90 700.00 63,000.0
Paintor 6 90 750.00 405,000.0
helpers 3 90 600.00 162,000.0
scaffolder 3 60 500.00 90,000.0
welder 1 7 750.00 5,250.0
Tinsmithry 3 45 700.00 94,500.0
Service Driver 1 90 550.00 49,500.0
-
TOTAL FOR MANPOWER COST 896,250.0
B. MATERIAL COST
1 PAINTING WORKS -
1.1 Paint, Davies, Liquid tile cast 22.0 gals 650.00 14,300.0
1.1.1 Paint, Davies, Megacryl Primer, DV -1350, white 40.0 gals 695.00 27,800.0
1.1.2 Paint, Davies,Bio-fresh, BF-50506, inner calm 30.0 gals 875.00 26,250.0
1.1.3 Marine epoxy 15.0 gals 2,400.00 36,000.0
1.1.4 Patching Compound 60.0 kls 80.00 4,800.0
1.1.5 Rust Converter, DV-XR-61 Gray 10.0 gals 987.00 9,870.0
1.1.6 Laquer thinner 6.0 gals 575.00 3,450.0
1.1.7 Assorted Sandpaper 1.0 lot 15,000.00 15,000.0
1.1.8 Paint tray 9.0 pcs 200.00 1,800.0
1.1.9 Paint roller 12.0 pcs 120.00 1,440.0
1.1.10Sakoline 3.0 roll 6,500.00 19,500.0
1.1.11Paint, Epoxy enamel 10.0 gals 1,950.00 19,500.0
1.1.12Paint, Megacryl, black 6.0 gals 750.00 4,500.0
1.1.13Paint Brush, asstd 6.0 pcs 75.00 450.0
1.1.14Square tube, 2x2" 10.0 pcs 850.00 8,500.0
1.1.15Welding rod 3.0 kg 120.00 360.0
-
2 REPLACEMENT OF EXISTING GUTTER -
2.1 Removal of Existing Gutter 4.0 units 11,000.0 44,000.0
2.2 Prepaint GI Sheet Gutter 24"x8' 96.0 pcs 650.0 62,400.0
-
-
-
-
-
-
-
-
TOTAL FOR MATERIAL COST 299,920.0
C. GENERAL REQUIREMENTS
SUBTOTAL 15,000.0
SUBTOTAL 170,000.0
E. INDIRECT COSTS
Page 1 of 2
SUBTOTAL 372,915.9
F. OTHER COSTS
SUBTOTAL -
SUMMARY OF COST
DESCRIPTION COST (Php) REMARKS
A MANPOWER 896,250.0
B MATERIALS 299,920.0
F OTHER COSTS -
Name & Signature : Jomar E. Bienes Name & Signature : Marissa L. Encina
Position : Project Engineer Position : Gen. Manager
Page 2 of 2