Gas
Gas
Gas
Tanaka Professor
Emeritus, The University of Tokyo, Tokyo, Japan Y. Okada General
Manager, Japan Oil Engineering Co., Ltd., Tokyo, Japan Y. Ichikawa
General Manager, Japan Drilling Co., Ltd., Tokyo, Japan Keywords:
Offshore, rotary drilling, offshore drilling rig, jack-up, semisubmersible,
drillship, offshore oil and gas production, platform, FPSO, subsea
.production systems
Contents
Introduction .1
Summary
Introduction .1
The chapter describes mainly the present situation of offshore drilling
and production of oil and natural gas. The first section is devoted for an
outline of the rotary drilling method, as oil and gas wells onshore and
offshore are drilled by the method. A hole made by a drilling bit is called
a well. The objective of making the well is to produce underground fluids
such as fresh water, brine, crude oil, natural gas and geothermal fluids,
and to study properties of deeply situated formations. The Middle East
area and China are said to have had wells producing water or natural gas
even in the era before Christ. By the year 1200, wells 450 m deep were
drilled in China by a spring-pole drilling method. The principle of the
method is to generate percussion by dropping heavy tools on the
bottom of the hole. The spring-pole drilling method was the predecessor
of a cable drilling method that had been used till after 1970s. Hand-
powered rotary devices were introduced to make geothermal wells in
Italy and water wells in France in early 1800s. Machine-powered rotary
devices and circulation systems were introduced by the late 1850’s. In
1901, the Lucas gusher at Spindletop oil field, the United States of
America, was successfully drilled and completed by the rotary drilling
method with circulation of fluid that consisted of water and clay. The
first cementing job to shut off water was carried out in 1903. The use of
bentonite as an ingredient of drilling fluid began in 1935 and has
contributed to improve mud properties. Three-cutter rock bits equipped
with jet nozzles were introduced to clean the bottom-hole of cuttings
around 1950. The technology of directional drilling has made great
progress to the level of extended reach drilling (ERD) and horizontal
wells through the development of down-hole mud motors and
measurement-while-drilling tools (MWD). Over-water drilling from a pier
extended from seashore was carried out in the late 1890’s. Drilling and
production of oil in the location where the land was out of sight was
accomplished offshore Louisiana, the United States of America, in 6 m of
water in 1947. The well was drilled from a tender-assisted platform
system. Four basic types of mobile offshore drilling rigs were developed
not long after drilling the first offshore well: the submersible rig in 1949,
the ship-shaped rig in 1953, the jack-up rig in 1954, and the
semisubmersible rig in 1962. Drill ships and semisubmersible rigs are
called floaters. These structures float during operations. Floaters are
equipped with unique facilities that are not used in onshore operations:
the marine riser, the motion compensation, and the stationkeeping
system. The dynamic positioning system (DPS) was introduced for deep-
sea operations in 1961. The scientific research well “SG-3” in Russia
reached the depth of 12 263 m in 1988, and has had the depth record
ever since. The deepest exploration drilling for hydrocarbons was carried
out to the depth of 9583 m in the United States of America in 1974. As
for offshore wells, a hydrocarbon exploration well was drilled offshore
Brazil in 2965 m of water in 2001. A production well was completed with
a subsea completion system offshore Brazil in 1852 m of water in 1998.
The offshore technology is steadily in progress toward deeper and
deeper seas to search and produce subsea resources for the future
.welfare of the world
1 صوره
A number of strings of casing are set in the well. The purposes of casing
are to protect fresh-water sands, to prevent drilling problems such as
heaving formations and high-pressure zones, and finally to provide a
means of production of oil and gas if the well is productive. The annular
space between the casing and the borehole should be filled with cement
W to support the casing and prevent the flow of underground fluids up
.to the surface and/or into the fresh-water zones
Intermediate strings of casing are set to case the long open section of
the hole or the zones causing trouble. The last string of casing is the
production casing that is set immediately above, or through, the
production formations The main functions of the rotary drilling rig are as
:follows
.Steel tooth bits. Insert bits (or tungsten carbide insert bits)
Cooling and lubricating the bit and the drill stem. The drilling fluids are
composed of base fluids, clay minerals, chemicals, and inert solids. Their
base fluids classify them as follows: water-base muds, oil-base muds, air
or gas drilling. Bentonite, a kind of clay, is preferred to make up water-
base muds. A small quantity of chemicals adds in the mud to control the
viscosity and filtration properties. Inert solids such as barite are mixed in
the mud to adjust the density. In the conventional system of the rotary
drilling, the rotary table rotates the drill stem, but the down-hole mud
motor and the top drive device are applied to rotate the bit in the
directional and horizontal well drilling, or to improve operations in the
vertical well drilling. The technical advancement of the measurement-
while-drilling tools (MWD) and the logging-while-drilling tools (LWD) has
contributed to the almost real-time acquisition of the down-hole
information. Owing to these tools it has become easy to drill directional
and horizontal wells. Directional wells with long horizontal departure are
called extended-reach-drilling (ERD) wells. The definition of an extended
reach well is a well with a measured depth to true vertical depth ratio
greater than 2.0. An ERD well in the united Kingdom drilled in 1999 to
access offshore reserves from onshore had a record of a departure of 10
728 m with a measured depth of 11 287 m and approximately 1600 m
true vertical depth. A definition of a horizontal well is a well with a hole
section exceeding an inclination of 85 degrees. The adoption of the
directional wells, extended-reach wells, horizontal wells, and the
multilateral wells has a share in the economical development of oil and
gas fields. Figure3 is an example of horizontal wells in the North Sea.
.Figure 4 shows various types of multilateral wells
الصورة الثالثة
الصورة الخامسة
الصورة السادسة
Jack-up rigs
Self-contained platforms
Water depth less than 50 m and calm sea: tender or jack-up assisted -
platforms
Water depth less than 400 m and mild sea: self-contained platforms -
الصورة السابعة
:There are two basic leg configurations of jack-up rigs
Mat-supported type for soft seabed: Legs is connected with a mat. The
mat rests on the seabed to stably support the rig. The type is used on
.flat sea-bottom in water depth of up to 50 m. The penetration is slight
Prior to raising the hull to the safe working height above the ocean
waves, it is required to preload the legs that penetrate the ocean
sediments. It is necessary for the sediments that the legs are pushing
against to support the weight of the jack-up hull and also the additional
drilling equipment placed on the rig during drilling operations and
certain drilling loads. If the sediments are not dense enough to support
these loads, one or more of the jack-up legs may suddenly/rapidly push
(punch) through the sea floor sediments. A leg punch through can
severely damage the legs and hull, thus jeopardizing the safety of the
.rig
Once the preloading operation is complete, the hull can be raised to the
desired height above the ocean waves. The height of the hull above the
sea surface is called the air gap. The air gap depends on the expected
height of the waves and also the height of the production platform if
drilling a well on a production platform. Depending on the design of the
rig, there is a slot either in the hull to allow the wellhead to be
positioned under the rig floor, or the rig floor and support structure
(substructure) can be extended/slid-out (cantilevered) from the side of
the hull to the desired drilling position. Once the rig is placed in
operating position, drilling process is carried out in a way similar to land
.operations after the outer casing and surface BOP is installed
الصورة الثامنة
Submersible drilling rigs consist of upper and lower hulls connected by a
network of posts or beams. The drilling equipment and living quarters
are installed on the upper hull deck. The lower hull has the buoyancy
capacity to float and support the upper hull and equipment. When water
is pumped into the lower hull, the rig submerges and rests on the
seabed to provide a working place for the drilling. Movement and
drilling operations proceed as that of the jack-up rig. Most submerged
rigs are used only shallow waters of 8 to 10 meters. Ship-shaped
submersible rigs are also used, which are called swamp barges. Swamp
barges have operated in swamp and marsh areas in Nigeria, Indonesia,
and the southern part of United States of America. An arctic mobile
drilling unit having conical, sloping-side structure belongs to the
.submersible type
الصورة التاسعة
If weather conditions (wind, swell, and current) become too harsh, the
drilling operations must be shut down due to excessive motion of the
tender. The tender platforms are used in Gulf of Guinea and the Persian
Gulf waters where good weather conditions prevail, resulting in low
.downtime less than 2% of total operation time
الصورة العاشرة
Wind and current forces push a floater away from the location directly
above the subsea wellhead. Waves raise and fall the floater. The
technology has developed to overcome these effects caused by weather
.conditions
The marine riser system consists of riser pipe, riser tensioners, and
ancillaries. The riser pipe is connected to the top of subsea BOP, and is
pulled up by the riser tensioner system onboard to keep vertical
configuration. The riser pipe serves as a conduit for returning mud to the
surface from the hole, and as a guide for running drill stem and casing
from the floater to the hole under the seafloor
Drillships .3.3.2
The first drillship was introduced in offshore services in 1953, and the
dynamic positioning system was equipped in drillships in 1961. Drillships
.are shown in Figure 12
New generation drillships built in 1990s have the capacity to drill wells in
the waters up to 3000 meters. These ships have production test facilities
and oil storage tanks in addition to the usual drilling equipment. To
improve the efficiency of deepwater operations with the aim of
economic advantages, the PROPRIETARY dual-activity drilling system OF
TRANSOCEAN INC. is shown in the larger drillship in Figure 12. The dual-
activity rigs have two sets of drilling equipment such as mud pumps,
drawworks, top drives, and mud treatment system. When a hole is
drilled by the first drilling system, the second drilling system is used for
making up casing and tubing strings in advance, and so on. Although the
dual-activity system in the deepwater drillship is in the early stage of
deployment, it is readily recognized that the system can save significant
.time and cost of drilling operations
The lower hulls provide improved stability for the vessel. Also, the open
area between the
If hunt for petroleum, i.e. oil and natural gas, was extended from
onshore to offshore, so was the use of equipment employed for its
production. Petroleum production and field processing equipment
typically includes wells to safely bring oil and gas from underground
formation to surface, separation equipment to separate gas, oil and
associated water, some means of transporting the products to market
such as pressure booster (pump/compressor) and pipelines. In the
majority of offshore fields these pieces of equipment used are
essentially the same as those used in onshore fields. In order to bring
the equipment to offshore environment, some sort of supporting
structure is needed to keep them above water, namely, offshore
platforms. The above Californian piers were in this sense the first
offshore platforms for petroleum production. Bottom-supported
platforms have been in use ever since, though material to build them
changed from wood to steel and concrete. These platforms, whilst good
in that they can provide working environment probably closest to that
onshore, have problems of sharply increasing cost with increasing water
depth and long lead time for construction. To counter these problems,
the petroleum industry came up with floating platforms in the 1970s.
These include semisubmersibles, a natural functional extension of their
sisters in the MODU fleet, ship-shaped floating production storage and
offloading systems (FPSOs) and tension leg platforms (TLPs). More
variations were added in later years. If these platforms are one way of
coping with the offshore environment, enabling equipment intended for
onshore application to be used there more or less as it is, the other way
is to make the equipment capable of functioning in underwater
environment and put it on the seabed, that is, a subsea production
system. The first production equipment that was put completely
underwater was a well, a gas well completed on the bottom of Lake Erie
in United States of America in 1943. Although this well used completion
equipment for onshore use without modification, one designed
specifically for subsea application was subsequently developed. To date
there have been more than 1000 wells worldwide drilled and completed
subsea. The advancement of subsea technology meanwhile has led to
development of other kinds of equipment tailored for subsea
application, namely, manifolds to collect/divert produced and service
fluids to desired flow paths, multi-phase pumps that can boost the
pressure of the mixture of gas and liquid and gas/liquid separators, all
with associated controls equipment. Today these platforms and subsea
systems are applied in various combinations, each aimed at best suiting
the particular environment in which they operate. These are offering the
petroleum industry many options to choose from for production
systems. However, research and development still continue to tap oil
.and gas in still deeper water and still harsher environment
The most widely used platforms are so-called template platforms. This
type of platform, Figure14, usually consists of jacket, piles and deck. The
jacket is fixed to sea bottom by means of piles and they together support
the deck load. The deck is the topside structure of the platform and
houses most of the equipment. The jacket is fabricated from steel
tubulars at a yard, transported on and launched at the site from a barge,
upended, lowered to the sea bottom and piled. The deck is usually
divided into several modules, which are individually fabricated at a yard
or shipyard, transported on a barge to the site where the jacket is
.already installed, lifted and fixed onto the jacket
الصوره الرابعه عشر وربنا مفتحت شيت البايو وافتكرت القرف ده
Yard space and launch barge size available at the time of the project
limit the jacket size. Cognac platform jacket installed in 312 m of water
in the Gulf of Mexico in 1977 to 1978 was fabricated in three pieces and
they were sequentially lowered to and connected together on the
seabed, because there was no barge large enough to transport it in one
piece at that time. Size of the individual deck module is greatly
influenced by the lifting capacity of the crane vessel available.
Attractiveness of less number of heavier lifts in terms of cost and other
aspects has encouraged construction of heavy lifting vessels and those
with twin cranes with several thousand ton lifting capacity are available.
Function of this type of platform can vary from simple well protection to
combined drilling and production with all the necessary equipment to
drill wells and process and transport the produced fluid. Storage
function is not normally provided. This type has found application in
water as deep as 411 m in the Gulf of Mexico. As the water depth
increases, maintaining stiffness to rigidly resist the overturning moment
as the template platforms do becomes prohibitively expensive. The
alternative is structures that have much longer sway period than that of
high-energy storm waves, avoiding resonance of structures with these
waves. This type of platforms is called compliant towers and has been
applied in water depths in excess of 500 m. Another type of bottom-
supported structure is the gravity platforms, Figure15. They derive
required stability from their own weight. The substructure is usually built
from concrete in deep, protected water near shore such as fjord and
firth. Deck is usually built in one piece, brought on a barge or barges
over to and then mated with almost completely submerged
substructure. The completely assembled platform is then towed to the
installation site and ballasted down to seafloor. Because of this unique
way of construction, geographical locations to which this type is
applicable are limited. Only a few applications can be found in the world
except in the North Sea, where Norwegian fjords and Scottish firths
provide ideal construction sites. This type is inevitably massive and
suitable for self-contained drilling and production role. Storage
capability can be easily incorporated, making this type suitable for
situations where pipeline transportation is not readily available
floating production storage and offloading system (FPSO). They are ship-
shaped platform either with or without propulsion capability, Figure 17.
First application was made in the late 1970s and it was a converted
ocean-going tanker. Converted or purpose-built, FPSOs have a large
payload and storage capacity making them suitable for application in
isolated locations where pipeline transportation cannot be an option.
Single point mooring is the most widely used station-keeping means,
where the platform is allowed to weathervane around the mooring
mechanism. Multi-point moorings have been applied in relatively benign
environment such as West Africa and the Gulf of Suez. Like
semisubmersibles wells are completed at separate locations, either
.subsea or on separate platforms
reservoirs too far away to reach from existing platforms are typically
developed utilizing subsea wells tied back to the host platforms,
providing economical means of field development. Also exploratory
wells, typically plugged and abandoned after a short period of test not
so long ago, are completed subsea and put into production for some
months using drilling vessels equipped with temporary production
facilities or purpose-built well test vessels, providing valuable reservoir
.data for subsequent field development planning
Trees Subsea trees are, like land trees, primary means of flow control
for subsea wells and consist of series of valves and sometimes a flow
control device (choke) along the flow path of produced fluid with
associated controls equipment, Figure 19. Although trees in early days of
subsea development relied heavily on diver assistance in installation and
operation, the trend is toward less reliance and remotely operated
connectors, valves and chokes by means of hydraulics are used
extensively. They are installed by drilling rigs using guidelines established
between a pre-installed guide base structure and a rig for positioning
and orientating. For deep waters where use of guidelines is not practical,
.guidelineless system is available
الصورة العشرين
Subsea Manifolds A manifold consists of appropriately arranged .4.3.2
valves and pipings with associated controls equipment and a structure to
support these components. It allows produced fluid to be commingled
or diverted and injection fluids to be distributed to desired flow paths.
With asubsea manifold, number of flowlines and injection lines between
wells and host platform can be reduced substantially, saving large
amount of investment. Disadvantage is added complexity in not-easily-
accessible subsea environment with implications on maintenance cost. A
manifold can be a stand-alone component or built into a well template,
.Figure 21
21 الصوره ال
Glossary
Casing: Steel pipe lowered into a hole drilled and bonded to formation
.by cement to keep the well safe
Riser: Any pipe with the fluid flow upward in it. In offshore drilling a
marine riser system is used to establish a connection between the rig
and the seabed. In offshore petroleum production, production riser
systems extend from the seabed to the deck of the production platform.
Well completion: A series of work to make a well ready for production
after it has been drilled and tested. Although there are wide variations, it
typically involves installing the production (deepest) casing, perforating
the casing and installing tubing (flow path for produced fluid) and the
Christmas tree. A subsea completion or subsea-completed well is a well
.that sits entirely, that is, up to its Christmas tree, on the seabed
Bibliography
Bourgoyne Jr. A.T., Millheim K.K., Chenevert M.E. and Young Jr. F.S.
(1991). Applied Drilling Engineering. Richardson, TX 75083-3836, USA:
Society of Petroleum Engineers. [This is a good textbook on rotary
drilling engineering.] Gerwick, Jr. B.C. (1986). Construction of Offshore
Structures. Baffins Lane, Chichester, Sussex PO19 1UD, UK: John Wiley &
Sons. [This book gives details of how offshore structures, particularly the
bottom-supported platforms, are constructed.] Silcox W.H., Bodine J.A.,
Burns G.E., Reeds C.B., Wilson D.L. and Sauve E.R. (1989). Chapter 18
Offshore Operations. Petroleum Engineering Handbook (editor-in-chief
H.B. Bladley), pp. 18-1 – 18-52. Richardson, TX 75083-3836, USA: Society
of Petroleum Engineers. [This work provides a good overview of offshore
drilling and production systems and operations.] API Standards and
Publications. 1220 L Street, Northwest Washington, D.C. 20005-4070,
USA. American Petroleum Institute. [The series contain detail standards
and information on rotary drilling method of onland and offshore
operations.] OTC Proceedings. Richardson, TX 75083-3836, USA. Society
of Petroleum Engineers. [The proceedings published yearly provide up-
to-date information on offshore engineering and operations.]
Proceedings of SPE/IADC Drilling Conference. Richardson, TX 75083-
3836, USA. Society of Petroleum Engineers. [The proceedings published
yearly provide up-to-date information on drilling engineering.]
Biographical Sketches
Shoichi Tanaka is professor emeritus of the University of Tokyo in
Tokyo, Japan. He majors in drilling engineering and petroleum
engineering. He holds a Doctor of Engineering in mining engineering
from the University of Tokyo. He was with the University of Tokyo from
.1960 to 1995