INSULATION DATASHEET &

SPECIFICATION
CONTRACTING, SPECIFICATIONS AND QUANTITIES – ECL X21

RAHMA MOHAMED ALI


19015657
SIKASHIELD® P24 PE 4 MM
DATA SHEET
Composition Composition APP modified bitumen

Reinforcing material non-woven polyester fabric

Packaging Roll width 1.0 m (EN 1848-1)

Roll length 10.0 m

Shelf life 12 months from date of production

Storage conditions The Product must be stored in original unopened and undamaged

packaging in dry conditions and temperatures between +5 °C and +35 °C.

Store in a vertical position. Do not stack pallets of the rolls on top of each

other, or under pallets of any other materials during transport or storage.

Always refer to packaging

Appearance and color Top surface Polyethylene film

Bottom surface Polyethylene film

Effective thickness Effective thickness 4.0 mm ± 0.2 mm (EN 1849-1)

Maximum tensile force Longitudinal (MD) 600 N/50 mm ± 120 N/50mm

Transversal (CMD) 400 N/50 mm ± 80 N/50mm

Elongation at maximum Longitudinal (MD) 35% ± 20%

tensile force

Resistance to tear Longitudinal (MD) 150 N ± 45 N

Transversal (CMD) 150 N ± 45 N

Joint shear resistance Longitudinal 500 N/50 mm ± 100 N/50mm

Transversal 350 N/50 mm ± 70 N/50mm


Flexibility at low temperature ≤ 0 °C

Watertightness Method B: 24 hours at 60kPa Pass

Ambient air temperature Minimum +5 °C

Maximum +40 °C

Relative air humidity Maximum 80 %

Substrate temperature Minimum +5 °C

Maximum +40 °C

ITEM DESCRIPTION
Per meter squared / square meter, supply, install and, test waterproofing of reinforced
concrete flat roof, using reinforced Plastomeric bituminous membrane with thickness 4.0 mm
± 0.2 mm on single layer/2 perpendicular layers, manufactured by SIKA or similar.

The item includes the following; clearing and ensuring the concrete surface is ready to be
insulated by curing any possible cracks, patches, bare reinforcement. Then leveling the
brickwork of chords to prepare the slopeto-fall concrete heading to the stormwater drainage
points, horizontal/vertical concrete cove not less than 20 cm in radius.

Besides grooving the parapet to interpolate the vertical membrane. Also, it includes laydown the
hot liquid bitumen under the membrane as the polyester reinforcement melts at +260 °C and
laying the membrane with overlapping not less than 15 cm, as well as, treating the connection
with drainage points as shown in construction drawings.

Item should include slope to-fall concrete with 7cm thick avg. besides all needed accessories and
equipment. This work must conform the site engineer’s instructions as prescribed in Egyptian
Code for Water and Damp proofing, approved product specifications and datasheet.