DBs - Using Experts and FIDIC Time Limits
DBs - Using Experts and FIDIC Time Limits
DBs - Using Experts and FIDIC Time Limits
DAB Use of Experts and Time Limits under the FIDIC Rules: A Case History
Synopsis
The time allowed under the FIDIC Rules for a Dispute Board to give its decision or
recommendation is 84 days1 from the date that the Presiding Member receives a referral from a
Party. The Parties invest in the Dispute Board wide discretional powers under the Rules2 to
adopt inquisitorial methods and to establish procedures including (i) conduct any hearing as it
thinks fit, not being bound by any rules or procedures, (ii) take the initiative in ascertaining the
facts. Depending on the nature of the referral the DAB must determine if it is able to decide the
issue using it own expertise or whether it requires the use of experts for that purpose. It must
adopt procedures suitable to the dispute and avoid any unnecessary delay.3
Subject to the time allowed to deliver its decision the Dispute Board must adopt procedures
suitable to the dispute and avoiding unnecessary delay or expense. This requirement often raises
questions in the mind of the Dispute Board when the amount or time involved in the dispute
becomes a significant proportion of the Contract Amount or of the Time for Completion. It must
weigh the significance of any decision it renders against what each party has at stake.
This article deals with an infrastructure project in an industrially developed country where the
Contractor contracted with a public entity under the FIDIC Red Book. The dispute arose out of
unforeseeable physical conditions in respect of the source of embankment fill. The Employer
eventually varied the work to allow for the use of off-site borrows located at a significant
distance from the Site. The variation order paid the costs of the extra work, but in the mind of
Contractor did not compensate for what it alleged to be significant additional delay and
disruption costs, approximately 15% of the original Contract amount. The Parties were not able
to resolve the dispute which was finally referred to the Dispute Board for a decision.
The Dispute Board weighed the significance of the amount claimed against the time and costs
for giving its decision and decided to avail itself of expert advice for delay analysis and quantum
determination. The Board took significantly longer than 84 days to issue its decision, but the
decision ended the dispute.
This significance of this case history is compared with that of the PGN v CRW JV Singapore
case that currently so popular amongst the dispute resolution community.
The Parties have kindly allowed their case history to be used for this article but preferred that it
be done in a way that would not identify the Project.
1
Sub-Clause 20.4 [Obtaining a Dispute Adjudication Board Decision], paragraph 4.
2
Articles 7 and 8 of the Procedural Rules; Annex to the General Conditions of Contract
3
Article 5 (b) of the Procedures.
The Dispute.
It became apparent early in the Contract that material coming from required excavation and
designated borrow pits near the Site did not satisfy the technical requirements for permanent
embankment work. It was also evident that suitable embankment material was available only at
distances in the order of 40 km. Moreover, the nature of those materials was such to require
different compaction methods for the permanent embankment. The impact on the economy of
Contract caused by this change was significant and there was delay in giving instructions to the
Contractor for the change.
The Contractor duly noticed a claim both for the additional cost to supply material from the more
distant source and place it in the permanent embankment work and for the time it would require
to carry out the varied work. The Employer agreed that there was additional cost of doing the
work and negotiated a variation order over time with the Contractor that was based on the actual
costs incurred.
The Parties did not agree on the additional time requested and the Employer issued an instruction
to the Contractor to submit a revised programme that described the methods it proposed to adopt
in order to expedite progress and comply with the Time for Completion. The Contractor’s claim
for an extension of the Time for Completion was thereby rejected.
The Contractor reacted to that instruction with a request for reimbursement for additional costs
arising out of that instruction. The Contractor claimed for the additional costs of equipment,
material and human resources that were incurred because of the expedited the work. As it turned
out the Employer later granted an extension of the Time for Completion for other concurrent
varied work. The Contractor completed the allegedly disputed work within the extended period
but pursued its claim for additional costs.
The DRB was in place early for this the Project. It conducted more than 13 regular visits to the
Site at about 5 month intervals. It witnessed the problems caused by non-availability of suitable
fill materials as well as the difficulty to identify alternative sources. It assisted the Parties
through discussions and informal advice to reach the agreement on the variation order. It also
4
The Contract Price revalued to 2012 value was about €75 million (US$100 million)
The Referral
The Contractor referred the dispute to the Board during its last visit to the Site and after the
Work was substantially completed. The relief sought by the Contractor with this claim alone
exceeded 15% of the original Contract Price.
The Dispute Board considered its obligation to (i) issue a decision on the referral within 84 days
of the date on which the referral was received by the presiding member of the Board and (ii)
limit the time and the costs to the Parties in making its decision.
The Dispute Board recognized that it would not be able to render a suitably reasoned decision
within the 84 days stipulated by the Contract and it obtained written consent from the Parties to
extend that period as would be required by the procedures established by the Dispute Board. To
have complied with the restrictive time allowed by FIDIC procedures meant that the Board
would utilize its own costly and time consuming expertise to (i) analyse the Contractor delay
analysis and (ii) separate the costs related to the contractor delay events. The work was done
more effectively, with greater certainty and at less cost by its experts.
The sums involved in this dispute were important both to the Contractor and the Employer. The
Board decided to appoint two experts, a delay analyst and a quantum surveyor to review the
The Decision
The decision
The decision was to award the Contractor less than half of the amount it sought.
Conclusion
The Parties accepted the Board decision and the amount awarded was certified by the Engineer
and paid in the next IPC.
Each year the ICC publishes statistics concerning the numbers and values of disputes that are
submitted to its Court of Arbitration. The amount claimed in this example exceeds the average
value of arbitration requests submitted to that body by several orders of magnitude. Had this
dispute gone forward to international arbitration the Parties would have incurred costs (and risk)
in the order of magnitude of the referral amount and it would have taken more than three years to
obtain an award.
Strong arguments can be made that the Dispute Board process is “rough justice” and that the
Board should not exceed the 84 days allowed to it for issuing its decision.
In this case history example the entitlements were also a substantial proportion of the amount
claimed by the Contractor and the Dispute Board would not have been in a position to give a
“reasoned” decision without the aid of the expert advice that it ordered and finally received. The
Parties apparently agreed with this assessment because the dispute was extinguished with
immediate effect by the decision.
5
PT Perusahaan Gas Negara v CRW Joint Operation, SGHC 202 [2010].