Method Statement For Mps
Method Statement For Mps
Method Statement For Mps
SIGNATURE:
2 SCOPE OF WORK
This method statement describes and elaborates the procedures of Wet well Cleaning.
Location: MPS
5 Ventilation Fan 18” with hose 2 For providing fresh air flow inside
110 m3/min. manhole
For securing the staff
Disposable hand globes, Rubber
7 LOT For personal protection of staffs from
or Cotton hand Gloves
virus and bacterial
The following key personnel will be responsible during the execution of work.
5.1 Mechanical/Civil Engineer
He is responsible for work methodology & safety on the project Duties include;
He is Reporting to O&M manager, PM.
Implementing the company Occupational Health Safety.
Stimulating his staff a high level of safety awareness.
Identifying safety training needs for the staff.
Ensuring safe equipment and work atmosphere is provided and maintained.
Leading by good example in front of his staff and all times.
Reviewing and approve the safety reports and initiate rectification where required.
Working team
Working team (Foreman, Technicians, Safety officer)
6 TRAINING REQUIREMENTS
The Staff should have the following training in order to carry out the activity.
Special training for specific staff
HSE site induction training given to all the wet well cleaning team by HSE team.
First aid training given to first aider by third party.
LOTO training given to engineer, foreman, technician and operators by third party.
Firefighting training given to Engineer, Foreman, technician and operator by third party.
Heavy equipment operating given to heavy equipment operator by third party.
Permit to work training given to engineers and foreman by third party.
Confined space training given to all the wet well cleaning team by third party.
AGT (authorized gas testing) given to engineer, foreman, technician and operators by
third party.
SCBA training given to confined space entrants by third party.
Lifting Operation Training given to foreman technician and operators by third party.
ERT-fire drill/Site evacuation (ERT to all the team by third party and fire drill to all team by
HSE team)
Technical training given to all the wet well cleaning team by Civil Engineer.
7.2.1Safety Objective
To ensure all the team, employees and visitors at site safety, health and environment
To complete the wet well cleaning task safely without any personnel injury to the
people.
This will be ensuring by observing safe work procedure and right equipment.
Identify all other interfaces and liaison requirements impacting on the work
activity.
Coordination with operation team
Wet well level managements.
Applicable isolation and other connections.
11.3.1 Pre-Checks
Survey the working area and make sure that site is clear for safe working activity.
Body temperature need to be checked for each staff by infrared personnel
Thermometer.
General Permit, confined space and lifting permits and certificates should be secured
prior to commencement of the activity.
Make sure all the staff received required vaccination.
Make sure all staff wearing biological agent which involve Sewage.
Barricade the area by using warning tape around the working area.
Make sure that the all staffs are wearing the mandatory PPE (subtitle 7.2.2).
Monitor the H2S and CO gas and O2 levels inside the wet well using Multi Gas detector
by lowering the tubing / probe into the wet well.
The acceptable H2S level is from 0 -10 ppm (TWA-10 ppm & STEL-15 ppm)
The acceptable CO level is less than 35 ppm (TWA-35 ppm & STEL-200 ppm)
The acceptable O2 level is from 19.5 to 23.5 %
The acceptable LEL level is 0 %
Safety Officer will continue monitoring the toxic gases present in the wet well and
always there to monitor the people going in and coming out of the confined space and
he will account the people going in and out.
Emergency Rescue Stretcher, SCBA and Safety buoy should be placed near wet well.
Enough drinking water is available at site.
In case of emergency vehicles should be available at the work place.
Tool box Talks shall be conducted.
Necessary communications (walkie-talkie/two way radio) are established.
Make sure that LOTO removed from the penstock and pumps by trained personnel.
Barricade shall be removed from the working area.
Make sure that working area returned into normal environment
WET WELL CLEANING
11.4.1 Procedure
This type of wet well cleaning is for a pumping station where the waste can be removed
completely by entering inside the wet well to do the wet well cleaning.
Ensure Work order is dispatched
The level of sewage water in Wet-well is reduced by closing the pen-stock & running the
pumps in hand mode operation.
Once the water level is reduced to the lower level of the wet well then pumps are
isolated and LOTO (Electrical isolation) is implemented by trained personnel.
Checking and monitoring of H2S, CO, LEL and O2 (toxic gases) concentration in the
wet well is done by using Multi Gas detector.
Continuous ventilation of the wet well at low level to purge out presence of H2S and
other toxic gases.
Workers standing at the top and entry inside the wet well should wear full body harness
compulsorily.
High pressure jet of water is used to clean any debris adhered to the walls, chains,
pumps, ladder, etc. inside the wet well.
After finishing the work, clean all tools, wet well area and debris if any present at the site
area.
Dispose the debris in to the authorized designated area.
Ensure to cancel/close the confined space permit and ensure for all people involved in
the activity are accounted for.
Complete the work order
3. Do they have to use Gas mask?, what is the duration of using mask?
APR (Air-purifying respirator) mask is required
The job and use of mask will be carried out on rotational duration of 20 to 30 minutes.
4. Method of Communication?
Walkie talky or Loud voice depending the depth of the wet well.
5. Rescue Equipment.
Life line
Safety Harness
Tripod.
APR etc
The quotation for this equipment has been requested, expecting feedback anytime soon.
NOTE:
Work time and duration To be schedule by Operation team and Mechanical Engineer.