Quiz Week 8 - 9 - Cost Management - Attempt Review
Quiz Week 8 - 9 - Cost Management - Attempt Review
State Finished
Marks 15.00/20.00
Question 1
Correct
Diana is the project manager for a complex project. Diana suspects that some of her project team
members are filling false claims and having false invoices reimbursed. The invoice charges are
being charged to the project budget. During which of the following processes can Diana confirm
her suspicious regarding her project teams actions?
Select one:
a. Control Scope
b. Validate Scope
c. Control Schedule
d. Control Costs
Correct
Crystal is making a presentation on her projects during a board meeting. Although Crystal knows
that the project is behind schedule and will be at least a month late, she announces that by the
end of her project, her projects total schedule variance will be zero. As the board members do not
understand Earned Value Management (EVM) Crystal explains that the schedule variance is
calculated by subtracting the projects total planned values from the projects total earned value.
What can be concluded from this information?
Select one:
b. Crystal is lying
The correct answer is: Crystal is trying to deceive the board members
Question 3
Correct
Which of the following components of the Project Management Plan is/are specifically considered
during the Contol Costs process?
Select one:
c. Cost Perfoemance Baseline, Cost Management Plan and Activity Cost Estimates
The correct answer is: Both Cost Performance Baseline and Cost Management Plan
Question 4
Correct
Select one:
a. Controlling
b. Budgeting
c. Estimating
d. Sequencing
Question 5
Correct
Which of the following processes develops an approximation of the monetary resources needed to
complete project activities?
Select one:
a. Determine Budget
b. Control Costs
c. Approve Costs
d. Estimate Costs
Incorrect
Which of the following indicates the relationship among the Direct and Manage Project Work,
Control Cost and Determine Budget processes?
Select one:
a. Both the Direct and Manage Project Work and the Determine Budget processes provide inputs to
the Control Cost process
b. The Determine Budget process provides inputs to the Control Costs process but these processes
are not related to the Direct and Manage Project Work process
c. The Direct and Manage Project Work process provides inputs to the Control Costs process which
then provides inputs to the Determine Budget process
d. The Determine Budget process provides inputs to the Control Costs process which then provides
inputs to the Direct and Manage Project Work process
The correct answer is: Both the Direct and Manage Project Work and the Determine Budget
processes provide inputs to the Control Cost process
Question 7
Correct
Select one:
a. The EV measure is always greater than the authorized Planned Value Budget for a component
The correct answer is: The term EV is often used to describe the percentage completion of project
Question 8
Incorrect
The following Gantt chart displays the schedule for telecom site construction project. It contains
seven activities and a hammock activity. The chart also displays various activity metrics.
According to the original plan the first two activities should have been completed along with 50%
of the work on the third activity, Perform Civil Works. However, only the first two activities have been
completed and for some reason, no work has been performed on the third activity. What is the
projects current SPI?
Select one:
a. 2
b. 1
c. 0
d. 0.5
Question 9
Incorrect
Which of the following Depreciation Methods provides for a higher write-off early on as compared
to other methods?
Select one:
b. Sum-of-Years Digits
c. Declining Balance
d. Straight-Line Depreciation
Incorrect
According to the approved plan, Flora should have completed the site inspection, site excavation,
lay foundation, and assemble tower tasks. What is the projects current Cost Variance (CV)
Select one:
a. -1200
b. 7500
c. -7500
d. 1200
Question 11
Correct
In Kims current project, some of the activity costs deviated from the baseline by $150. This seems
to be low but she wants to verify the project documents to see if the deviation is within the
threshold. Where should she look for control threshold information?
Select one:
Correct
Which of the following formulas is used to calculate the EAC forecast for ETC work performed at
the present CPI?
Select one:
b. AC + bottom-up ETC
Question 13
Correct
Which of the following Earned Value measurements is project cost trend indicator?
Select one:
Question 14
Correct
Which of the following is not a tool or technique of the Determine Budget process?
Select one:
b. Historical Relationships
c. Cost Aggregation
Correct
Select one:
a. Hidden cost
b. Discounted cost
c. Unrecoverable cost
d. Depreciated cost
Question 16
Correct
Select one:
b. Agreements
c. Resource Calendars
Question 17
Incorrect
Which of the following will be true about the value of the CPI at the end of any project?
Select one:
a. It would be positive
b. It would be negative
c. It would be zero
d. Cannot be determined
Correct
What is the total approved plan for the project work to which the project execution is compared
known as?
Select one:
b. Cost Variance
c. Management Reserves
Question 19
Correct
Which of the following statements regarding the Budget at Completion (BAC) and the Estimate at
Completin (EAC) is correct for any project?
Select one:
The correct answer is: The BAC is not dependent on the EAC
Question 20
Correct
Which of the following deprecistion methods depreciates the same amount (or percent) each
year by dividing the assets cost by the number of years it is expected to be in service?
Select one:
a. Declining Balance
b. Sum-of-Years Digits
c. Units of Time
d. Straight line
Previous Activity
Jump to...
Next Activity