BOQ
Sub: Fabrication and installation MS staircase at different locations in the campus

Sr. No. DSR 2018 Description of Items Qty Unit Rate Amount

Providing and laying in position cement concrete


1 4.1 of specified grade excluding the cost of centering
and shuttering - All work up to plinth level :

1:3:6 (1 Cement : 3 coarse sand (zone-III): 6


4.1.6 1 cum
graded stone aggregate 40 mm nominal size)

Steel work in built up tubular trusses including


cutting, hoisting fixing in position and applying a
2 10.16 priming coat of approved steel primer, welded and
bolted including special shaped washers etc.
Complete.
10.16.1 Hot finished welded type tubes. 300 kg

Steel work welded in built up sections/ framed


work including cutting, hoisting, fixing in position
3 10.25
and applying a priming coat of approved steel
primer using structural steel etc. as required.

In stringers, treads, landings etc. of stair


10.25.1 cases including use of chequered plate 150 Kg
wherever required, all complete.

13.1 12 mm cement plaster of mix :

13.1.2 1:6 (1 cement: 6 fine sand) 10 sqm

Pointing on brick work or brick flooring with


13.31 cement mortar 1:3 (1
cement : 3 fine sand):

13.31.1 Flush / Ruled/ Struck or weathered pointing 20 sqm

Total