Port Works Design Manual Part 3 Guide To Design of Reclamation Original Current
Port Works Design Manual Part 3 Guide To Design of Reclamation Original Current
Port Works Design Manual Part 3 Guide To Design of Reclamation Original Current
PART 3
Prepared by :
This Port Works Design Manual (PWDM) is a continuously updated version incorporating the
PWDM Corrigenda issued since the PWDM was published. This continuously updated version is
released in e-format only on the CEDD website. This PWDM is to be cited as “PWDM Part 3
(2023). Guide to Design of Reclamation (Continuously updated e-version June 2023). Civil
Engineering Office, Civil Engineering and Development Department, HKSAR Government.”
3
FOREWORD
(Continuously updated e-version Jun 2023)
This continuously updated e-version of the Port Works Design M頤ual has
incorporated the previously issued Corrigenda No. 1/2018 and No. 1/2020 to facilitate the
designers and industry practitioners to carry out coastal design in a more convenient mrumer.
Practitioners ru·e encouraged to comment at any time to the Civil Engineering Office
on the contents of this document, so that improvements can be made to future editions.
FOREWORD
The Port Works Design Manual presents recommended standards and methodologies
for the design of marine works in Hong Kong. It consists of five separate volumes, namely,
Part 1 to Part 5. Part 1 mainly covers design considerations and requirements that are
generally applicable to various types of marine works. Part 2 to Part 5 are concerned with
specific design aspects of individual types of works including piers, dolphins, reclamations,
seawalls, breakwaters and beaches. This Manual supersedes the Port Works Manual
prepared in the 80’s.
This document, Port Works Design Manual: Part 3, gives guidance and
recommendations on reclamation design, covering design considerations, stability analysis,
settlement assessment and monitoring. It was prepared by a working committee comprising
staff of the Civil Engineering Office and Special Duties Office with reference to the latest
local and overseas geotechnical and reclamation publications and experiences in consultation
with the Geotechnical Engineering Office and other Government departments, engineering
practitioners and professional bodies. Many individuals and organizations made very useful
comments, which have been taken into account in drafting the document. An independent
review was also undertaken by geotechnical experts before the document was finalized. All
contributions are gratefully acknowledged.
Practitioners are encouraged to comment at any time to the Civil Engineering Office
on the contents of this document, so that improvements can be made to future editions.
C C Chan
Head, Civil Engineering Office
June 2002
4
Working Committee of Port Works Design Manual : Part 3 [First published Version in 2002]
The document was drafted by the following staff of the Civil Engineering Office :
Ir Lee Wai-ping
Ir Tse Koon-hung
Ir Wong Ching-piu
Assistance and advice were provided by the following staff of the Civil Engineering Office and
Special Duties Office :
Ir Chiu Mau-fat
Ir Ko Wai-kuen
Ir Lam Chi-keung
Ir Law Man-chin
Ir Li Yuen-wing
CONTENTS
Page
No.
TITLE PAGE 1
FOREWORD 3
CONTENTS 5
1. INTRODUCTION 9
1.1 Purpose 9
1.2 Definitions, Symbols and References 10
2. DESIGN CONSIDERATIONS 11
2.1 General 11
2.2 Purpose of Reclamation 11
2.3 Site Investigation 11
2.4 Layout 12
2.5 Formation Level 13
2.6 Reclamation Methods 14
2.6.1 General 14
2.6.2 Drained Method 14
2.6.3 Reclamation Sequence of Drained Method 15
2.6.4 Fully Dredged Method 17
2.6.5 Partial Dredged Method 17
2.6.6 Water Depth 18
2.6.7 Cement Mixing Method 19
2.6.8 Other Soil Improvement Techniques 21
2.7 Fill 21
2.7.1 General 21
2.7.2 Public Fill 21
2.7.3 Marine Fill 23
2.7.4 Crushed Rock 23
2.8 Fill Treatment 24
2.8.1 General 24
2.8.2 Surcharge Preloading 24
2.8.3 Dynamic Compaction 24
2.8.4 Vibrocompaction 25
2.8.5 Specification for Fill Densification 26
2.8.6 Other Fill Treatment Methods 27
6
Page
No.
3. STABILITY 31
3.1 General 31
3.1.1 Factor of Safety 31
3.1.2 Strength of Materials 31
3.1.3 Stability Analysis 32
3.2 Drained Reclamation 33
3.2.1 Stability during Construction 33
3.2.2 Long-term Stability of Drained Reclamation 36
3.3 Dredged Reclamation 36
3.4 Remedial Works 37
4. SETTLEMENT ASSESSMENT 39
4.1 General 39
4.2 Components of Reclamation Settlement 39
4.3 Assessment of Sub-soil Settlement 40
4.3.1 General 40
4.3.2 Settlement due to Primary Consolidation 41
4.3.3 Correction for Construction Period 43
4.3.4 Primary Consolidation with Vertical Drains 44
4.3.5 Primary Consolidation with Surcharge Preloading 44
4.3.6 Settlement due to Secondary Consolidation 45
4.4 Assessment of Settlement within Granular Fill 46
4.5 Calculation of Residual Settlement 47
5. RECLAMATION MONITORING 51
5.1 General 51
5.2 Monitoring Instruments 51
5.2.1 Pore Water Pressure Measurement 51
5.2.2 Settlement 52
5.2.3 Lateral Deformation 52
5.3 Monitoring for Drained Reclamation 52
5.3.1 Instrument Monitoring Locations 53
5.3.2 Monitoring of Stability During Fill Placement 54
7
Page
No.
6.1 General 57
6.2 Piling 57
6.3 Culvert Foundations 57
6.4 Structures and Facilities 58
REFERENCES 61
FIGURES 63
List of Figures 65
Figures 67
1. INTRODUCTION
1.1 Purpose
The purpose of the Port Works Design Manual (the Manual) is to offer guidance on the
design of marine works and structures normally constructed by the Government of the Hong
Kong Special Administrative Region. Such works and structures include public piers, ferry
piers, dolphins, reclamations, seawalls, breakwaters, pumphouses, beaches and associated
marine facilities. The Manual has been written with reference to the local conditions and
experience. Therefore, it may also provide a source of useful data and design reference for
marine works and structures constructed by other organizations or parties in Hong Kong.
The Manual is issued in five separate parts. The titles of these parts are:
The recommendations in the Manual are for guidance only and should not be taken as
mandatory. Compliance with these recommendations does not confer immunity from
relevant statutory and legal requirements. Because of the variable nature of the marine
environment, the design of marine works and structures relies particularly on the use of sound
engineering judgement and experience. Practitioners should be aware of the limitations of
the assumptions employed in a particular theoretical or computational method. Since the
marine environment is a field where active research and development are continuing, it is
beyond the scope of the Manual to cover all analysis and design methods. Practitioners
should be prepared to explore other methods to suit a particular problem and should also
realize that many of the methods will continue to evolve.
This part (Part 3) of the Manual gives guidance and recommendations on the design of
reclamation, covering such aspects as design considerations, stability analysis, settlement
assessment and monitoring of reclamation works. Worked examples are provided in
Appendix D to illustrate the application of the recommended design methods. Readers
should refer to other parts of the Manual on particular aspects, as necessary.
10
The definitions of terms and meanings of symbols for the purpose of this part of the Manual
are given in the Glossary of Terms and Glossary of Symbols at the end of this document.
The titles of publications referred to in this part of the Manual are listed in the reference
section. The reader should consult these original publications for more detailed coverage of
particular aspects. For Works Bureau Technical Circulars (WBTC) which are updated
regularly, reference should be made to their latest issues.
11
2. DESIGN CONSIDERATIONS
2.1 General
This chapter gives comments and guidance on the design of reclamation covering such
aspects as the reclamation layout, formation level, reclamation methods, fill, treatment of fill,
environmental impacts, drainage impacts and so forth.
The design of reclamation should fulfil the requirements of the planned use and programme
for development, particularly with regard to time and settlement characteristics of the
reclamation and foundation materials. The timing of future development, location of future
roads, drains, buildings and areas of open space are of particular importance. Sometimes it
may be necessary to design reclamation for the main initial purpose of beneficial reuse of
public fill. In such circumstances, future land use and development is likely to be known
only in general terms at the time of reclamation design. It is relatively common for planned
use and development of reclamation to change with time, due to changing needs, and account
should be taken of this where possible by designing reclamation for flexibility of use.
Reclamation projects are usually extensive, and problems during or after the construction,
may carry major financial implications. To enable the designer to devise the most
appropriate design, it is essential that site investigation is carried out prior to the design of
reclamation. In addition to normal geotechnical investigations required for marine works,
12
the investigations may need to cover potential sources of fill materials. In-situ and
laboratory testing of soil samples from within the proposed reclamation area should be
carried out to determine the strength, settlement and permeability characteristics of the
underlying soils. Details of site investigation and soil testing are covered in Geoguide 2
(GEO, 2017a) and Chapter 4 of Part 1 of the Manual.
2.4 Layout
The layout of a reclamation project will largely be governed by town planning considerations.
The major factors restricting the extent of reclamation will be the water depth, the need to
maintain fairways, moorings and other marine traffic channels and clearances to the approval
of the Director of Marine, and the environmental implications.
The effects of reclamation on water flow in general, and currents, waves, storm surge
characteristics and sediment transport conditions at and along the shoreline in particular, can
cover a far more extensive area than the area immediately adjacent to the reclamation itself.
The detailed investigations should take this into account.
The effect of the reclamation on the groundwater regime should also be investigated. In addition,
the effects of climate change over the life of the reclamation should be investigated and
incorporated in the design.
Marine-frontage related uses, such as piers, wharves, cargo handling areas, seawater intakes,
stormwater and sewerage outfalls, need to be identified at an early stage. The proposed
13
locations of such structures, areas and facilities will need to be known, at least in general
terms, prior to the detailed investigations referred to above.
Locations of roads, bridges, railways, buildings, major stormwater culverts and sewers, and
their respective tolerance of settlement will influence the choice of fill to be used in different
areas of the reclamation and the proposed reclamation method. Where possible, reclamation
should be designed for full flexibility of land use (see Section 2.2).
A check should also be made to see if there will be any archaeological impact due to the
reclamation.
Before deciding on the formation level for a reclamation project, the following aspects should
be considered:
It is relatively easy in most cases to ensure that the seawall cope level and reclamation level
are higher than the extreme still water level corresponding to a return period of 100 years, or
even 200 years where flooding would cause substantial loss of life and damage to property.
However, it is not practical to design a seawall, even with the addition of a wave wall, to
effectively prevent overtopping from waves during extreme events. A certain degree of
overtopping, particularly with vertical-face seawalls, is to be expected, and the drainage
immediately behind the seawall must be designed to accommodate this if major flooding is to
be avoided. Although wave walls can help to control or reduce extensive overtopping,
careful detailing is required at discontinuities such as piers, wharves, pumphouses and
landing steps to avoid significant overtopping through these areas.
In addition to determining the site formation level, due considerations should also be given to the
14
impact on the drainage provisions of the existing adjoining lands where the formation level of the
reclamation is higher than that of the adjoining lands. Appropriate drainage provisions will need to
be considered to avoid flooding or overloading the existing drainage system due to the level
difference.
In view of the above factors, all reclamations should be considered individually. The
consequences of adopting a particular reclamation level should be fully investigated before
determining the most appropriate level in each case.
2.6.1 General
Two main reclamation methods have commonly been used in Hong Kong, namely the
drained method and the dredged method. The drained method leaves the soft marine deposit
in place, and the consolidation is usually accelerated by the use of vertical drains with or
without surcharge preloading. The dredged method involves the removal and disposal of
soft marine deposit before placing the fill. Both methods are described in this Chapter, with
comments on particular aspects, advantages and disadvantages of each. Removal of
sediment is generally discouraged unless there is strong justification (see WBTC 3/2000 (WB,
2000)). This must be allowed for in the reclamation programme.
In recent years, there is a tendency of not removing the sediment in reclamations, mainly on
environmental reasons. Apart from the drained method, other types of soil improvement
techniques can be considered. These are described in the ensuing paragraphs.
Another method used in the past is the displacement method. This method involves direct
tipping of fill from trucks onto the seabed, without removal or treatment of the marine
deposits. However, this method can result in mud waves and areas with marine deposits
trapped under the fill. Long-term differential settlement can be a problem due to
consolidation of these trapped marine deposits. This method should not be employed unless
the reclaimed land can be left for decades without development.
For reclamation by the drained method, marine deposits and any underlying soft alluvial clay
are left in place. The load applied by placing fill on the seabed causes an increase in the
pore water pressure within the clay and silt layers. This excess pore pressure gradually
dissipates, the loading is transferred to the soil skeleton and settlement takes place. The rate
of dissipation of the excess pore water pressure in the soil (consolidation) depends on the
15
layer thickness, permeability (particularly whether there are inter-bedded sandy layers), and
the loading applied. A thorough site investigation, including careful ground investigation, is
essential in order to ascertain the thickness of the marine deposits and underlying layers, and
how they vary across the site, and the strength parameters and consolidation parameters of
the various layers.
Preloading is often used in combination with vertical drains. Vertical drains are drainage
conduits inserted into compressible soil of low permeability to shorten the drainage path for
pore water in the soil matrix. They enable the pore water to drain horizontally to the
conduits, and then vertically through the conduits to the free draining layer provided on top of
the deposits, and to more permeable underlying soils, where these exist. However, vertical
drains may not be necessary if the marine deposits contain inter-bedded layers of free
draining granular deposits.
Drained reclamation is usually carried out in the following sequence (see Figure 1):
Geotextile may be laid on the seabed to separate the fill from the underlying soft marine
deposits, preventing migration of fines. It also enhances the stability of the underlying
marine deposits in supporting the loading of the reclamation fill.
This blanket should consist of free draining granular material, placed in a series of thin layers
in a controlled manner to avoid disturbing the underlying deposits until a sufficient thickness,
generally 2 m, is achieved. This granular layer works with the vertical drains to enable
drainage from the clayey deposits. It also acts as a capping layer to spread the load from the
fill during the filling operation. If vertical drains are to be installed by marine-based plant,
16
the material for the blanket layer and geotextile should allow easy penetration of the mandrel.
Prefabricated paper or plastic band drains are most commonly used in local conditions
because of their resistance to shearing (Premchitt & To, 1991). They can be applied
economically because of their ease of fabrication, storage and installation. A triangular
pattern of band drains spaced at between 1.5 and 3.0 m is normal. For a typical site with 5 to
10 m thickness of marine deposits, primary consolidation will be completed within one to two
years compared with 10 to 20 years if no vertical drains are used. To commence the
acceleration of consolidation earlier, the band drains are usually installed over water using
special marine plant through the blanket layer of free draining granular material prior to fill
placement.
The following factors should be considered when choosing the type of band drains:
Tensile strength of the drain to withstand the stress induced during installation.
Transverse permeability.
Soil retention and clogging resistance.
Vertical discharge capacity under confining pressure.
Performance in folded condition.
Durability.
General information on the properties and methods of testing prefabricated vertical band
drains are summarized in Appendix A.
Installation of vertical drains can be carried out over water using marine plant or after
reclamation using land plant. The former is usually adopted for reclamation over deep
water whereas the latter is used in shallow water where marine plant access is restricted.
Preboring may be necessary to by-pass obstructions for installation of vertical drains.
Controlled even placement of thin layers of fill on the reclamation site is necessary to avoid
shear failure of the underlying marine deposits and the formation of mud waves. Placement
can be by bottom-dump barges, hydraulic filling or grabbing. An initial thickness of no
more than one metre of fill is usually required with subsequent layers increased as
appropriate. Layers should be staggered where possible, with control being exercised to
ensure a sufficient leading edge for the underlying layer in relation to the layer being formed.
17
In any case, stability analyses should be carried out to check the factor of safety against shear
failure or significant mud wave formation during fill placement. The following need to be
specified:
Reclamation using the drained method requires tight control on site. A detailed method
statement from the contractor is required and close supervision of the filling sequence is
necessary. Instrumentation for monitoring, including piezometers, inclinometers, sub-
surface and surface settlement measurement systems, is essential to ensure the reclamation
stability during fill placement and to check the progress of the settlement. Sampling and
testing of the clay and silt deposits at various stages may be necessary to verify the
assumptions made in the design, to ensure continued stability.
In this method, all marine and alluvial clays or silts are removed by dredging and replaced
with fill. Normally, dredging is stopped when sandy alluvium or weathered rock has been
reached, as determined by detailed ground investigation. The basic method is relatively
simple but can be expensive where thick layers of soft deposits exist. Its main advantage is
that settlement of the free-draining fill will take place more quickly and is more predictable,
but it involves marine disposal of dredged sediments. Such disposal, particularly for
contaminated mud, may be severely problematic. Chemical testing of the sediment is
required to determine the level of contamination and thereby determine whether open sea
disposal is acceptable or whether confined marine disposal or additional treatment is required.
Tests normally comprise the analyses of heavy metal and organic compounds but biological
testing will also be required if the chemical tests reveal that the sediments are contaminated.
Detailed sampling and testing requirements are given in WBTC No. 3/2000 (WB, 2000).
Partial removal of marine or alluvial deposits, leaving the lower, stiffer or stronger deposits in
place reduces the dredging and fill quantities compared to the fully dredged method.
However, it should be noted that better control is required than for full removal for the final
trimming in dredging and for initial fill placement, to avoid future differential settlement.
18
The remaining layer of marine or alluvial deposits will consolidate by vertical drainage
upward through the fill and downward, if the layer beneath the soil is sufficiently permeable.
The construction programme must still allow time for this consolidation and band drains with
preloading may still be required if the available time is short.
The extent of marine or alluvial deposits to be left in place must be decided after
investigation and is subject to detailed design. It will depend on the amount of settlement
predicted to occur after the completion of the reclamation compared to the magnitude of
differential settlement which can be tolerated in the particular situation.
Shallow water areas, with seabed level higher than about –2.5mPD, may pose restrictions to
the above reclamation methods, which may include the following:
Controlled thin layer placement by bottom dumping in the drained method may
not be workable in shallow water because the restricted water depth will
prevent the normal functioning of the bottom opening devices of the dumping
barges. Placement in thin layers by grabbing will be necessary but the
progress will be slower. A diagrammatic comparison of the difference of the
fill placement sequence in deep water and shallow water is shown in Figure 2.
Normally, filling can be executed by bottom dumping up to about –2.5 mPD;
above –2.5 mPD, bottom dumping is not possible because of insufficient water
depth. In deep waters, fill placement above –2.5 mPD may be carried out by
end-tipping directly because the fill already placed by bottom dumping is
usually thick enough to spread out the fill load. In shallow water, however,
the fill layer placed by bottom dumping may not be thick enough that placing
of fill above –2.5 mPD by end-tipping may induce instability. Fill placement
by grab may be adopted but will result in slower progress. Both cases should
be subject to stability analysis and the rate of fill placement should be
controlled to avoid mud waves.
Insufficient water depth may prohibit the access of the marine plant to install
vertical drains over water. In such cases, the vertical drains may need to be
19
These restrictions will affect the reclamation sequence and should be taken into consideration
in determining the method and programme of the reclamation.
The principle of deep cement mixing (DCM) is based on chemical reactions between clay and
chemical agents. Ordinary Portland Cement and Portland Blast Furnace Cement, etc. are the
most commonly used admixture stabilizers. The purpose of mixing chemical agents with the
soil is to improve the stability, strength and stress-strain properties of the soil. The stabilization
mechanism generally involves the following chemical reaction processes :
Cement reacts with the pore water of soft clay to form a series of hydrates.
Hydrates exchange ions with clay particles and form large conglomerates.
Clay particles react with the excess calcium ions from the hydration process and are
bonded together.
The design considerations and design approach of DCM method for the foundation of seawalls
and breakwaters are given in Section 4.5.2 and Section 4.6.2 of Part 4 of the Manual
respectively. For reclamation, designer could consider, apart from conventional reclamation
methods (including drained method and dredged method), using DCM as one of the non-
dredged methods to form land by strengthening in-situ soft marine sediment.
The advantages of DCM method as compared with conventional reclamation methods are :
DCM method solidifies the soft marine sediment by mixing it with cement slurry to
form DCM columns in a shorter time frame to support the seawall and filling materials
above, thus reducing the time required for reclamation. The reclaimed land could be
delivered for early development.
DCM method is an environmentally friendly method as it does not require dredging of
marine sediment and importing materials for filling back the dredged area. DCM
method can also significantly reduce the consolidation settlement arising from
conventional drained method. Hence, the demand for importing fill materials would be
reduced and disposal of dredged marine sediment would also be minimized.
DCM is flexible in application because the amount of stabilizing agent and form
of treatment can be adjusted to suit different soil properties and engineering
requirements.
20
The following considerations should be taken into account in the choice of reclamation method :
Soft deposits may also be strengthened in-situ by vibro-replacement (stone columns) or by soil
mixing techniques including lime columns or any other soil improvement techniques. Other
form of seawall construction methods or combination of methods may also be considered (e.g.
using cofferdam steel cells sinking to hard stratum). Designers should consider the cost
implications and possible effects on piling and excavation in future land development. These
specialist techniques may require detailed assessment to demonstrate their viability.
2.7 Fill
2.7.1 General
Fill for reclamation includes public fill, marine sand fill and crushed rock, but public fill and
marine sand fill are the most commonly used types of fill in local conditions. For most
reclamation works, the choice of fill is largely dependent on availability and cost. In order to
maximize the benefit of available fill sources, flexibility for combining different types of fill
should be allowed in a project. The Public Fill Committee and Marine Fill Committee, under
the chairmanship of the Director of Civil Engineering, should be consulted for the use of fill
and related procedural requirements during the planning of reclamation projects.
Because of the shortage of areas to accommodate the public fill generated by the construction
industry, priority should be given to its use. It is also the government policy to maximize
the use of public fill in reclamation projects. The main advantage of using public fill is the
benefit to the community. Reclamation using public fill provides sites for the disposal of the
inert portion of construction and demolition material from private and public developments
and demolition sites. This ensures that good use is made of such material rather than it
becoming a wasted resource.
Particular aspects to be noted in the design of the reclamation when using public fill are:
The rate of supply of public fill is not easily controllable, being dependent
mainly on programming of engineering works and development projects. It is
quite usual for the number of trucks per day to fluctuate, and the delivery rates
can vary widely from about 1,000 to 15,000 m per day. The impact of the
3
Strict site control is necessary to ensure that public fill does not contain
unsuitable material such as marine mud, household refuse, plastic, metal,
industrial and chemical wastes, animal and vegetable matter and other material
considered unsuitable for reclamation.
Rock and concrete over 250 mm would impede subsequent piling, and has to be
broken down to this size or placed in areas zoned for open space and roads.
The use of public fill will generate a large number of delivery trucks at and
around the entrances and exits of the reclamation site or barging points. The
route of the trucks going to and leaving the site or barging points should be
properly considered to avoid unacceptable disturbance to the existing traffic.
Sufficient space should be allowed on site to cater for queuing of trucks and
adequate traffic signs should be provided to give clear instructions to the truck
drivers. Transport Department, Police, District Office, District Councils and
other relevant parties should be consulted in planning the traffic arrangement.
Where direct land access to the site is not available, or where controlled thin
layer fill placement is required in a reclamation using the drained method,
contract arrangements should ensure that barges are available at all times to
avoid the need for temporary stockpiling of public fill at the barge loading site.
At the reclamation site, public fill will either be bottom-dumped by barges or
placed by grab, depending on the available water depth. Usually, completion
of the reclamation to the required formation level is not possible using marine
plant and direct grab placement, and the use of temporary stockpiles and final
placement of fill using site trucks and spreading plant is common.
Public fill can be directly end-tipped onto the reclamation under the control of
site supervisory staff when the dredged method is adopted or when the fill
thickness or profiles already deposited on site in the drained method is
adequately safe against slip failure or mud wave formation. In either case,
verification of stability by calculation is required. Normally, end tipping can
be carried out in two stages, firstly to a general level just above the high water
mark and later to the formation level of the reclamation.
23
Sampans should be employed to pick up floating material from the water within
the reclamation site. Such material is unsightly and can be hazardous to
shipping if allowed to drift into open waters. Floating refuse containment
booms should be used to surround the site to contain the debris and to facilitate
removal by the sampans.
The use of marine sand fill can be economically viable for a reclamation project where a
marine borrow area is within a reasonable distance of the site and where the size of the
project justifies the use of sophisticated dredgers, which have high mobilization costs. Plant
such as trailing suction hopper dredgers may dredge marine sand fill at relatively low costs,
depending on the thickness of the overburden at the marine borrow area. The rate of
formation of reclamation can be very rapid compared to the use of other types of fill, and
often several dredgers can be used on the same site, if necessary. These dredgers can
deposit marine sand in the reclamation by bottom dumping or by pumping, depending on the
access and water depth available.
The maximum fines content (smaller than 63 m) of the marine fill used in reclamation
should always be less than 30% but for hydraulically placed fill, it is usually limited to about
10%. The specification should suit the reclamation design. If the marine sand is to be
densified by vibrocompaction, the maximum fines content requirement will need to be more
stringent (see Figure 3). This requirement applies to fill as delivered to the reclamation site,
and not necessarily to in-situ material in the borrow area. Sampling on-board dredgers to
check the grading of material is one method to confirm that the required specification for fill
delivered to the site is satisfied. Samples can also be taken at the reclamation site, to check if
segregation of material has occurred during placing, with a view to ensuring that the fines are
well distributed within the reclamation. For proper control of the works on site, the tests for
the suitability of marine fill and the uniformity of the as-placed material should be stated in the
specification.
Crushed rock from local land sources should not normally be used for reclamation in view of
the shortage of public filling capacity, but should be used as foundation materials or
processed to produce aggregate products, as far as possible. If available for reclamation, it is
usually a by-product of works projects involving large quantities of soil or rock excavation and
removal, having a project programme that ties in with that of the reclamation project.
Where crushed rock over 250 mm is used, it should be placed in areas where no building
development will take place, to avoid impeding piling or excavation works in the future.
24
2.8.1 General
Whether the future development plan of the reclaimed land is known to the
designers in the design stage and whether the type, dimension and time of
construction of any structures to be built on the reclaimed land are known.
Cost-benefit and programming considerations.
Effect of the densified fill on future piling, excavation and other development
activities.
Surcharge preloading can be used to accelerate settlement of fill that would otherwise occur
more slowly. Monitoring the fill densification achieved by surcharge preloading is essential.
This can be done by field measurement tests (see Section 2.8.5) and by testing samples
obtained at intervals by drilling. The surcharge should only be removed when the required
settlement or increase in strength has been achieved.
Dynamic compaction involves repeated dropping of heavy weights onto the ground surface.
Large amounts of energy are transferred to the soil in the form of impact force and waves,
particularly shear waves. This results in a densely packed particle arrangement. Dynamic
compaction is suitable for use in most soils except cohesive soil below the water table.
The pounders used for dynamic compaction may be concrete blocks, steel plates, or thick
steel shells filled with concrete or sand, and may range from one or two up to 200 tons in
weight. Drop heights up to 40 m have been used. Dynamic compaction can also be
carried out underwater.
25
The major parameters to be determined in planning a scheme of dynamic compaction are the
extent and depth of treatment possible and the degree of improvement required. The former
is related to the locations and structural characteristics of settlement-sensitive development
on the reclamation as well as the possibility of damage to nearby buildings or facilities due to
the compaction works. The latter normally refers to the required relative density measured
by direct and indirect tests and is related to the required bearing capacity or tolerable
settlement under working load of the proposed structures. A site trial can be performed to
determine the optimal values of these parameters. Verification may be achieved by carrying
out compaction compliance tests (Section 2.8.5).
2.8.4 Vibrocompaction
A centre to centre spacing of 2.5 to 4 m is typical for clean marine sand fill. Compaction
depth of 25 m is common but up to 35 m has been achieved. A compaction trial can be
performed to determine the optimal values of spacing and depth.
Unlike dynamic compaction, which can be used on most types of fill, vibrocompaction is
only applicable to granular materials of certain grading properties. A graph showing the
suitability of materials for vibrocompaction with respect to the grading characteristics is
shown in Figure 3.
Vibrocompaction cannot effectively compact the surface few metres of fill and therefore
separate compaction of the surface layer will be required.
Relative density can be correlated with the results of in-situ tests such as Standard Penetation
Tests (SPT) and Cone Penetration Tests (CPT). Typical correlations between CPT cone
resistance and SPT value with relative density and friction angle of sand, are shown below:
The CPT is usually preferred because it is a relatively more precise test compared to the SPT
and can provide data over the depth of the fill at a much faster rate than the SPT. As a
general indication, an average CPT greater than about 8 MPa should be achieved for areas
designated for roads, drains and box culverts where fill treatment has to be carried out. The
depth/density profile requires careful consideration to avoid over or under specification.
27
The vibro-replacement and soil mixing techniques mentioned in Section 2.6.7 may also be
applied to fill treatment. These techniques are useful where culverts, pipelines or low-rise
structures need to be supported.
The reclamation sequence can be affected by the construction of the seawalls. Some of
these aspects which should be investigated in the reclamation design include:
All reclamation works will induce impact on the environment, the extent of which should be
assessed carefully to determine if mitigation measures are required to minimize the impact.
The potential impacts of a typical reclamation project are:
Marine borrow works – the same as due to dredging works, and the possibility
of reduction or removal of the natural supply of sand to existing beaches.
Land borrow works – noise, dust and smoke generation, and visual impact.
Fill placement – noise, dust and smoke generation, and water quality impact.
Guidance on environmental impact assessment during the planning stage of the reclamation
project, including the approach and assessment methodologies, is given in the Technical
Memorandum on Environmental Impact Assessment Process (EPD, 1997). The
recommendations of the environmental impact assessment study, such as the implementation
of environmental mitigation measures and monitoring and audit programme, may affect the
overall development of the project. Therefore, proper allowance for these factors should be
made when preparing the reclamation programme.
29
2.11 Drainage
A reclamation project may cause adverse impacts on drainage and flooding by altering the
existing drainage paths and regime, or by increasing the burden on the existing drainage
system. Existing drainage outfalls will need to be extended and temporarily diverted away
from the line of the extension while reclamation is carried out. A drainage impact
assessment is also necessary at an early stage of the planning and design in order to assess
potential drainage and flooding problems. It must determine the necessary temporary
drainage diversion and permanent drainage measures to ensure acceptable drainage
performance in areas upstream, adjacent to and inside the reclamation during and after the
construction of the reclamation. Close liaison with Drainage Services Department is
necessary for the drainage impact assessment. For details of drainage impact assessment
study, WBTC No. 18/95 (WB, 1995) should be referred to.
During reclamation, care should be taken to check for existing outfalls, intakes and drains
along the lines of the existing shoreline, particularly at low tide. Any outfalls, intakes or
drains which do not appear on the drawings should be recorded immediately and investigated
with the appropriate authority. Temporary channels should be provided as necessary across
the reclamation as a short term measure to avoid any delay. This aspect should be indicated
in the contract.
30
31
3. STABILITY
3.1 General
The reclamation sequence, dredged level, spacing of vertical drains, magnitude and duration of
surcharging and so forth are largely determined by stability and settlement criteria. This
chapter focuses on the stability of a reclamation and methods of stability analysis.
Settlement is discussed in Chapter 4 of this part of the Manual.
If the factor of safety against slip failure is kept above a minimum level of unity at all stages of
filling, instability should not occur. However, the choice of the factor of safety to be used is a
matter of professional judgement as to the acceptable consequences of failure, in terms of risk
to life and economic consequences. It is wise to allow a safety margin for unknown
factors since ground conditions are variable and ground investigation samples only a very
small portion of the ground. Each reclamation must be assessed on its merits and, where
justified, a higher factor of safety should be used. Reference should be made to WBTC No.
13/99 (WB, 1999) on the choice of factor of safety for temporary works.
Marine and alluvial deposits are variable in grading and a thorough ground investigation is
necessary in order to determine whether layering is present and the grading of the layers.
If the deposits are predominantly soft clay, their behaviour may be predicted by assuming that
they are undrained. This is justified because the permeability is low, and the time for
construction is usually short compared to the time for full drainage. Stability may be
analyzed by a total stress method using an appropriate profile of undrained strength c .u
The field vane shear test is commonly used for the in-situ determination of the undrained
strength c of soft clays, with the application of correction factor ().
u Thus,
c µ(c )
u u FV (3.1)
where (c ) is the measured undrained strength from field vane.
u FV
32
According to Bjerrum (1972), is a function of the plasticity index I (see Figure 4).
p
The plasticity index I can be determined from laboratory tests. The profile of shear
p
strength for each layer of clayey deposit can then be determined from the above relationships.
The undrained shear strength, c , can also be determined from laboratory triaxial tests
u
performed under undrained conditions. The testing procedure can be found in Geospec 3
(GEO, 2017). Shear strengths obtained from laboratory triaxial tests are usually lower than
those from field vane shear tests, due to sampling disturbance. The disturbance can be
reduced by using piston sampling but the vane shear test results are generally considered to be
more reliable, particularly for sensitive clays (GCO, 1987). Cone penetration tests can
also provide a reliable, quick method of investigating the soil structure, as continuous profiles
are obtained. The results of the cone penetration tests can be correlated with the undrained
shear strength; methods of correlation are given in Lunne (1997).
Fill is usually placed in a loose state in a reclamation although it may become densified later
under the weight of the overlying fill layers (including surcharge, if used). The strength of
reclamation fill adopted in the stability analysis should therefore reflect the strength
appropriate to the state of compaction of the fill at the time.
Typical unit weights and friction angles for sand fill and decomposed granite or similar types
of fill for preliminary stability analysis during fill placement are summarised in the
following:
For detailed analysis of the stability of each stage of the reclamation, the methods
recommended in Section 5.3.5 of the Geotechnical Manual for Slopes (GCO, 1984) should be
used.
The geometry of reclamation, including side slope, layer thickness and dimensions of berms (if
any) should be so designed that failure does not occur. The practical verification of this
33
requires checking of the equilibrium of the soil mass along a sufficient number of arbitrarily
selected failure surfaces to find the minimum value of the factor of safety for each
reclamation stage.
The principle of method is illustrated in Figure 5. The factor of safety associated with the
selected failure surface is defined by:
(3.2)
The slip surface in Figure 5 is for illustration only. Designers should consider all possible
slip surfaces, either circular or non-circular ones, in the analysis. Stability analysis is
usually performed using a computer program. Several are available in the market.
The stability of a reclamation during filling is particularly important where the underlying
soft marine and alluvial deposits are left in place. Improper placement of fill on such soil
could lead to failure and have significant programming, financial and life consequences.
Therefore, any proposed reclamation methodology and sequence, as well as subsequent
changes, must be subject to stability analysis before it is executed. Fill placement in
shallow water onto thick marine mud is likely to cause mud wave formation unless it is
carried out carefully, and stability at each interim construction stage should be checked
during the design phase.
The simplified stability analysis method described in this section may be used to provide a
quick preliminary assessment of the stability of the leading edge of the reclamation.
34
Jewell (1987) and Yeo & Woodrow (1992) considered that an embankment on soft clay is
essentially a problem of bearing capacity. Due to the loading from the fill, the clay layer at
the bottom of the embankment experiences both vertical stresses due to surcharge loading
and horizontal stresses. Therefore, the loading from an embankment onto the soft soil
creates not just vertical stress but also an outward shear stress. The combined effect of
vertical stress and the outward shear stress is to reduce the resistance of the foundation to the
applied vertical stresses. If the foundation cannot support the lateral shear stresses, it will
deform laterally. The lateral displacement may lead to cracking of the fill, destroying
whatever contribution the fill strength makes to the overall stability of the embankment.
For an embankment constructed on soft clay of uniform strength and limited depth with
respect to the embankment width (see Figure 6), Jewell (1987) derived the following
expression:
The detailed stability analysis method for checking the stability at each interim construction
stage is covered in Section 3.1.3.
Where used, geotextile is normally laid on the seabed before reclamation fill is placed. It
provides separation between the fill and the underlying marine mud preventing the punching
of the fill into the seabed and helps to prevent the creation of mud waves. However, the
benefits of the geotextile may be negated by improper overlapping or inadequate seaming at
the joints. Close site supervision and careful inspection after laying is required to ensure the
proper functioning of the geotextile.
(4) Monitoring
The principles and methods for analyzing the stability of a dredged reclamation are in general
the same as those of the drained reclamation. Since the soft, compressible sub-soils such as
marine mud or clayey alluvium deposits are removed, the stability during construction is
normally less critical than that of a drained reclamation. However, if there are existing
structures or developments adjacent to the reclamation site, the stability of the temporary
slopes of the dredged surface should be checked to ensure that the factor of safety is adequate
(see Section 3.2.1).
For the long-term stability of seawalls enclosing a dredged reclamation, Part 4 of the
Manual – Guide to Design of Seawalls and Breakwaters should be referred to.
37
If, despite all the precautions described previously, shear failure or significant mud waves
occur during fill placement, remedial works will be necessary. This section describes ways to
rectify the damage.
Site investigation must be carried out first to identify the extent of the failure before deciding
the remedial works to be undertaken. The extent of failure may be assessed by a
combination of the following methods:
Estimation of the scale and extent of mud waves from site observations and
sounding surveys of seabed profile.
Back analysis of reclamation stability based on the loading conditions before
failure and soil parameters from previous site investigations to estimate the
probable location and depth of failure zone.
Carrying out post-failure ground investigation and soil testing, and comparing
soil samples, profile and strength parameters obtained before and after failure.
Since any disturbed material may have a lower remoulded strength, tests such as field vane
shear tests are required to provide appropriate strength parameters for the design of remedial
works. In addition, disturbed mud is generally slower to consolidate than undisturbed mud
and therefore the effect of disturbance on the coefficient of consolidation should be
investigated before starting the design.
Where mud waves are generated, complete removal of all disturbed mud and replacement
with fill is the quickest way of rectifying the situation. The method is often employed to
remove small-scale mud waves generated in reclamation projects. The advantage of the
method is the relatively small settlement in the area of the replacement fill. The
disadvantages are the relatively high cost of dredging the mud, the need for a dumping
ground for the dredged mud and the need for additional fill. Subsequent differential
settlement may occur between the non-disturbed area and the rectified area where mud
disturbed at greater depth is also removed and replaced by fill. This should be checked in
the remedial proposal.
Stability should be checked to determine the factor of safety against slip failure in the
adjacent reclamation if the disturbed marine mud is removed. The settlement and lateral
38
deformation of the reclamation should be monitored to ensure safety during mud removal.
This method involves placing granular fill in thin layers on top of the mud wave and
accelerating the consolidation of the mud with the installation of vertical drains and
surcharging. This method avoids dredging of the disturbed mud and thus reduces the need to
replace the void with fill. The magnitude and rate of settlement should be estimated. A
stability check will be required if surcharge is used to accelerate the rate of consolidation.
As long as sufficient time for consolidation can be allowed in the development programme
for the newly reclaimed land, this is an economical method of rectification, particularly
where the mud wave involves movement at a deeper level.
4. SETTLEMENT ASSESSMENT
4.1 General
This chapter discusses the various components of settlement and gives general guidance on
the principles of calculating the rate and magnitude of settlement. The results of calculation
provide information on the effect of settlement on future land use.
It should be noted that the settlement estimated in design may differ from the actual value
because of the variability of soil properties likely to be encountered in local marine
conditions. The settlement should be verified with field monitoring data. Numerical
computation software may assist in settlement prediction, particularly if the soil strata are
complicated.
Settlement of a reclamation will generally continue for a considerable time after completion of
filling, but at a decreasing rate. Residual settlement is the amount of future settlement of the
in-situ soils and fill expected to occur, from a given time. The given time may refer to the
date of completion of the filling works, the date of handing over the reclamation site to
another party, the scheduled development date of the reclaimed land or any other time.
Hence, when describing the amount of residual settlement, it is necessary to define the start
time.
For the proper assessment of settlement performance it is necessary to understand the various
components contributing to the residual settlement. These settlement components are:
Consolidation is the gradual reduction in the volume of a fully-saturated soil due to the
drainage of pore water. The speed of this process depends on the permeability. In high
permeability soils this process is almost instant but in low permeability soils it continues for a
long time, until the excess pore water pressure has completely dissipated. The initial excess
pore water pressure is equal to the increase in vertical stress applied.
40
Secondary consolidation (creep) is the long-term settlement under constant effective stress.
In clay, it is due to the squeezing out of the water adsorbed on the clay particles. Adsorbed
water is chemically bound to the surfaces of the clay particles, so it is not free to flow under
gravity. As the adsorbed water is squeezed out, the clay particles move closer and rearrange
to a new equilibrium position, resulting in further deformation or compression. There are
conflicting views as to whether secondary consolidation starts as soon as the loading is
applied or after completion of primary consolidation.
Creep is also said to occur in granular fill. Some fill exhibits time-dependent compression
with the rate similar to that of secondary consolidation in clays. The mechanism of such
creep behaviour of granular fill is explained by the crushing of the contact points between the
particles, which results in the reorientation of the soil particles and additional settlement.
4.3.1 General
This section discusses the principles of settlement analysis, based on the classical theory of
Terzaghi, which describes primary consolidation resulting from a change in loading
(dissipation of pore water pressures) and secondary consolidation that takes place
subsequently with no change in pore water pressure. The classical theory assumes one-
dimensional strain and negligible lateral deformation. Since reclamation usually covers a
large horizontal area relative to the thickness of the sub-soil, these conditions are met.
However, the classical theory was derived from observations of thin samples during tests in
the laboratory. In reality, it has been observed in the field that thick soil layers behave
differently to this classical concept. There is no clear separation of the two types of
settlement and the overall result is one of gradually reducing pore pressures and reducing
rates of settlement, and excess pore water pressures may still be observed near the end of
primary consolidation. Hence, computations based on two components of strain, one related
to changes in effective stress and the other time dependent, not operating sequentially but
taking place simultaneously, may be a better model for more accurate prediction of settlement
in thick soil layers. Estimation of pore water pressures will require advanced calculation
methods to cater for the combination of the two components of strain.
41
The ultimate primary consolidation settlement of a soil layer due to an applied loading
depends on the relative magnitudes of the initial effective vertical stress acting on the soil and
the effective preconsolidation pressure, and can be estimated as follows:
42
The primary consolidation settlement of a homogeneous soil stratum at a given time t is given
by the following equation:
If vertical drains are used, the length of the drainage path is shortened and the equations must
be modified (see section 4.3.4).
If preloading is adopted, the applied loading in Equation 4.1 should include that due to the
surcharge load, taking into account its duration of application (see Section 4.3.5).
If the soil properties are variable over the depth, the calculation should be broken down into a
number of layers, each of which represents the properties of the soil at the respective depth.
From Equations 4.1 and 4.2, the residual settlement of a soil layer due to primary
consolidation at time t is given by:
43
In practice, the loading due to fill is not applied to the soil instantaneously but over a period of
time. The calculation of the consolidation settlement achieved within a give time
therefore needs to be corrected for the loading variation during the construction period (t ). c
There are several ways of dealing with this but the simplest is the equivalent load method.
It may be assumed that the load due to the fill increases uniformly throughout the
construction period. Thus the degree of consolidation at time t , the end of the construction
c
period, is the same as if the total load due to the fill had acted constantly for a period of t /2.
c
Hence, at any time after the end of construction, the corrected time for the calculation of the
consolidation achieved is equal to the time from the start of fill placement less half the
construction period (t /2).c
Similarly, at any time during the construction period, the consolidation achieved may be
taken as being equal to that occurring for instantaneous loading at half that time. Since
filling is still in progress, the load acting is not the total load of the fill. Hence, the value of
the consolidation achieved should be reduced in proportion of current load to the total load.
Thus, the primary consolidation settlement at any time t after commencement of fill
placement can be determined as follows:
Settlement = settlement for instantaneous loading (final fill load), computed using t –
0.5t c
44
If the filling progress deviates significantly from the assumption of linear loading increase,
the correction applied to the construction period should be adjusted accordingly. For more
information on consolidation due to time-dependent loading using Terzaghi’s one-
dimensional consolidation theory, reference may be made to Schiffman (1958).
The assessment of the rate of consolidation with vertical drains is given in Appendix B and is
based on the principle that the presence of vertical drains shortens the drainage path within
the soil layer, resulting in faster dissipation of excess pore water pressure (see Figure 8).
Consolidation then takes place by horizontal radial drainage, thereby increasing the
magnitude of the degree of consolidation given in Equation 4.2 and in turn the average degree
of consolidation achieved within a given time. The assessment may need to consider the
following factors, which tend to reduce the effectiveness of the vertical drains:
Well Resistance – Vertical drains have finite permeability with respect to the
surrounding soil, which is known as the “well resistance”. Well resistance
depends on the theoretical amount of water the consolidating soil can expel, the
actual discharge capacity and maximum drainage length of the drain.
The final magnitude of consolidation settlement is theoretically the same as that without
vertical drains. Only the rate of settlement is affected. Secondary consolidation cannot be
accelerated by vertical drains.
Vertical drains and surcharge preloading are often used together to speed up the consolidation
settlement. The surcharge serves to precompress the underlying soils to wholly or partially
eliminate the consolidation settlement that would occur under the anticipated future loading.
45
Since consolidation due to every load increment proceeds independently of the consolidation
due to the preceding and succeeding load increments, S can be found by the principle of
p,t
superposition.
Secondary consolidation of a soil layer at a given time t can be calculated using the following
formula (Carter, 1996):
Reference should be made to Geospec 3 (GEO, 2017b) for the relevant laboratory procedures
of determining C .
46
In the case of a single load application, t may be set at the start of loading. In a reclamation,
0
however, t is not obvious because the fill is usually applied gradually but t may be taken as
0 0
the time at which the load has reached a certain proportion, typically about 90 or 95%, of the
final loading (Carter, 1996). For t , it may be taken as the time when about 90 to 95% of the
1
where t = Time measured from the point at which filling commences (year).
This section describes the principles of settlement analysis for granular fill.
The permeability of granular fill is usually very high compared to the clayey sub-soil.
Hence, the primary consolidation will be complete very soon after fill placement and will not
contribute to the residual settlement in principle.
The creep settlement of granular fill, however, will take place continuously and may be
modelled as a linear relationship with log time by the following formula (Sowers et al, 1965):
where Sc = Creep settlement of the fill which occurs between times t and t
1 2
H = Fill thickness.
α = Logarithmic creep compression rate (%).
From Equation 4.7, and adopting a cut-off time value of 50 years, the residual settlement of
filling materials due to creep after a given time t, Sc,t(residual), is given by:
where t = Time measured from the point at which filling commences (year).
tc = Time for completing fill placement or the construction period (year).
From Equation 4.3 (without preloading) or Equation 4.4 (with preloading), and together with
Equations 4.6 and 4.8, the residual settlement of a reclamation due to the sub-soil and the fill
at time t, S , is:
residual,t
If the soil properties are variable over the depth, the calculation should be broken down into a
number of layers, each of which should represent the properties of the soil at the respective
depth. The consolidation settlement of granular fill may be ignored because it is generally
completed within the reclamation construction period.
Where it is known that development will take place immediately after the completion of
reclamation, it is common to limit the residual settlement at the time of completion of the
reclamation to less than 500 mm, and 300 mm for areas designated for roads and drains. If
48
the development schedule has not been determined during the design stage, the designer
should liaise with relevant government departments or land developers and determine a
suitable time interval after completion of reclamation for calculating the target residual
settlement. In any case, the designer should check with those bodies to see if there are any
special settlement requirements.
For a typical reclamation in Hong Kong where the seabed is underlain by marine and alluvial
clay, the following information may assist the designer to assess the residual settlement:
If the reclamation is near the shore where the thickness of the clay layer is
about 5 to 8 m, it is usually practical to limit the residual settlement arising
from primary consolidation to 50 mm for the drained method with preloading
and a reasonably tight construction programme.
The thickness and properties of the soil, the period of fill placement and fill treatment vary
across a reclamation site. Therefore, it is necessary to estimate the residual settlement in
different portions of the reclamation to account for such variability. Where the presence of
mud lenses is suspected in the underlying strata, additional ground investigation should be
carried out to identify their locations and to determine relevant soil parameters for settlement
analysis.
Where the designer considers that resiltation of clayey or silty particles of the dredged soil is a
problem at a particular site, its effect on settlement should be assessed.
The amount of residual settlement estimated in the design stage should be verified by field
monitoring data (see Chapter 5 of this part of the Manual).
49
The calculation of residual settlement for a reclamation is subject to many variables from
ground conditions to analytical methods and construction processes. Different practitioners
may come up with a different value at the same location due to different assumptions. An
appropriate degree of accuracy of the calculated settlement should be indicated in the design
reports and technical correspondence.
50
51
5. RECLAMATION MONITORING
5.1 General
Instrument monitoring of reclamation provides data for assessing the adequacy of both
the sub-soil and reclamation fill with respect to stability and settlement. This chapter
gives general guidance on the planning of instrument monitoring for a reclamation
scheme and outlines the functions of some typical monitoring instruments. Methods of
interpreting monitoring data for stability control during fill placement and verification
of settlement calculated in the design stage are also discussed.
Techniques for pore water pressure, ground settlement and lateral movement measurement
have improved over the years. Instruments capable of measuring the continuous distribution
of vertical and lateral movement with high precision are now available in the market.
Reference should be made to the specifications of respective manufacturers for different
monitoring instruments and specialist advice should be sought where necessary before
specifying the monitoring instruments in a reclamation project.
It is essential to monitor the pore pressures in a drained reclamation to ensure that the excess
pore pressure generated by fill placement are in line with predictions, and to confirm that the
vertical drains are functioning properly.
Pore water pressure is monitored using piezometers. For further details, Chapter 20 of
Geoguide 2 (GEO, 2017a) should be referred to. Vibrating wire piezometers are usually
adopted for monitoring pore pressures in reclamation. These have a rapid response and are
relatively simple to set up.
52
For monitoring of pore pressure during fill placement, the effect of tidal variation on the
piezometer readings should be checked in order to obtain the excess pore water pressure at a
given time and location. A piezometer may be installed outside the reclamation to provide
simultaneous tidal data for excluding the tidal component on piezometer data taken within the
reclamation (see Figure 9). The fill level at the piezometer location should also be recorded
so that the measured excess pore water pressure can be compared with the total vertical stress
increase due to fill placement.
5.2.2 Settlement
Settlement is an important monitoring parameter for both drained and dredged reclamation.
The magnitude and rate of settlement may be measured by means of settlement plates or
extensometers. Settlement plates, installed either on the seabed, within the fill or at the
surface of the reclamation, measure the settlement by comparing the levels of the plates taken
at different times, with a fixed datum level. If settlement characteristics of individual sub-
soil layers are required, extensometers are more suitable. The settlement of individual sub-
soil layers can be determined by detecting the relative change in the vertical positions of the
steel or magnetic ring targets in the extensometers by a probe.
With prudent planning, instrumentation can be installed before the start of fill placement so
that measurements can be taken prior to and during the course of filling. Instrumentation
should be concentrated at critical areas such as those where the marine mud is thick or
particularly weak. Since lateral deformation of the marine mud, if any, is generally more
prominent at the edge of reclamation, some instrumentation should be placed near the leading
edge of the reclamation where possible in order to effectively monitor the stability.
The location of the instruments may need to be refined after finalizing the working sequence
with the reclamation contractor. Installation of monitoring instruments prior to the
commencement of reclamation may cause obstruction to the movement and operation of
marine plant on the site. There is also no point in putting in instrumentation early if the area
will not be reclaimed until a late stage. Therefore, the locations of the monitoring points
should only be finalized when the reclamation sequence and plant operation are known.
If the instruments are intended to be placed at locations of future surcharge mounds, the
instruments will need to be installed in a manner that allows later vertical extension. In
general, instruments should not be installed in future building areas or other areas where
piling may be required, as the instruments are likely be destroyed. The ideal locations are in
areas zoned for future roads, footpaths, cycle tracks, amenity areas and open spaces.
Instruments may involve underwater installation and may need protection to withstand the
marine environment and fill placement operations. Figure 10 illustrates the set-up of
monitoring instrumentation installed by marine plant prior to the commencement of fill
placement and by land plant after the reclamation is filled up to above water level. For
instruments installed prior to commencement of filling, protection can be achieved by
housing all the instruments of each cluster in a rigid sleeve above the seabed. Fixed
temporary staging should be erected to support and protect the sleeve. The temporary
staging should be rigid and strong enough to ensure that the sleeve can stand above the
seabed in a stable manner. Due care should be exercised to avoid damaging the
instrumentation while placing fill in the vicinity. For instance, grabbing instead of bottom
dumping may be adopted adjacent to the instruments. If installation of instruments by
marine plant prior to commencement of fill placement is not feasible, instruments should be
installed immediately after the reclamation is filled up to above water level so that monitoring
can be started at the earliest opportunity.
54
This section discusses the methods of plotting the collected monitoring data to assist in the
assessment of the interim stability of the reclamation process. However, other site
observations will also be useful indicators of the reclamation stability such as:
Tension cracks appearing at the top and side slope of the reclamation.
Settlement at the centre of reclamation increasing rapidly.
Sounding survey results indicating up and down curve profiles of the seabed
near the edge of the reclamation.
Filling rate increasing suddenly.
Fill being stockpiled on the site excessively.
Monitoring data should be taken at least daily and given to the engineer immediately to
enable any anomalous behaviour to be discovered as early as possible.
Excess pore water pressure (u) can be plotted against the vertical stress (σ) due to the
reclamation fill (γH) (see Figure 11). For a stable reclamation process, the u-σ Plot should
show an increase in pore water pressure which is either smaller than or the same as the
increase in vertical stress in the course of fill placement. If the rise in pore water pressure is
much faster than the rise in vertical stress, action must be taken to avoid failure.
(2) s- δ Plot
H
Settlements of sub-soils at about the centre of the reclamation area (s) can be plotted against
the lateral deformation in the mud layer near the edge of the fill (δ ). Experience reveals
H
that when δ /s increases rapidly, it is an indication of imminent failure of the mud layer
H
(Ye et al, 1997). The line s-δ is straight and inclined at an angle to the s-axis when the
H
vertical stress is small (see Figure 12). However, when failure is imminent, δ will increase at
H
a faster rate than s and the straight line will curve towards the δ - axis.
H
Figure 13 shows the typical relationship between the height of filling (h), time (t) and lateral
deformation (δ ). H During the filling operations, the reclamation level is raised from h to
h+∆h, and the change in lateral deformation ∆δ is measured after time ∆t.
H According to
55
Ye et al (1997), the data set ∆h, ∆δ and h can be used to estimate the maximum allowable
H
Figure 13. When h is small, ∆h/∆δ is large. As h gets larger, the relationship between
H
h/∆δ and h will tend to become linear. If this straight portion is projected towards the h-
H
axis, the intercept will give the predicted maximum height of filling. The height of fill
should not exceed this value until after consolidation of the mud layer (checked by
monitoring pore pressures).
Alternatively, a method developed by Asaoka (1978) also enables utilization of the settlement
monitoring data, through simple graphical means, to verify the settlement due to primary
consolidation calculated in the design stage. The principles and details of application of the
method are given in Appendix C. The results provide additional information for the
designer to assess the settlement condition of the reclamation.
Asaoka’s method has the advantage that it is simple to use. However, it relies very much on
56
the availability of frequent monitoring data. For a reclamation project with a fill placement
duration of about two to three years, seabed settlement monitoring data at a frequency of
about one month is required.
Both the back-analysis method and the Asaoka’s method can be applied to counter check the
results of each method.
The principles described in Section 5.3 above also apply to dredged reclamation. Settlement
is usually the main parameter that is monitored in a fully dredged reclamation in order to
confirm prediction of settlement. For a partially dredged reclamation, monitoring
instruments similar to those in a drained reclamation may be set up to measure the pore water
pressure, settlement and lateral deformation. However, fewer instruments may be required,
depending on the type and thickness of the remaining sub-soils. Data interpretation will be
similar to that for a drained reclamation.
Where the dredged reclamation is carried out adjacent to existing developments or structures,
monitoring instruments should be installed in the existing ground to monitor pore water
pressures and soil movements, and hence stability of these developments or structures.
57
6.1 General
Brief comments on particular aspects of design related to piling, culvert foundations and
other miscellaneous structures and facilities in a reclamation are given below.
6.2 Piling
Obstructions to piling activities at reclamation sites can result in serious cost overruns and
programme delays. The largest rock or boulder encountered when driving piles must be
breakable by impact or be capable of being displaced. For the latter, there must be sufficient
voids in the fill to cope with the pile volume and allow the displacement. Experience has
shown that 250 mm is the approximate upper size limit for boulders within the fill to avoid
major problems with the installation of common pile types such as driven concrete piles, steel
H-piles, steel tubular piles and bored piles.
Permanent steel liners are usually necessary for bored piles to avoid necking, particularly in
crushed rock fill or where pockets of unconsolidated marine deposits are suspected. Special
shoes or reinforced sections or points are normally required for driven piles, particularly in
public fill or crushed rock fill.
The type of foundation to be used for a culvert extension across the new reclamation will
depend on the method of reclamation used and the amount of the residual settlement. To
reduce residual settlement, surcharging may be carried out with surplus fill over a strip two to
three times the width of the culvert and about five to six metres high until settlement has
stabilized.
Where the marine deposits have been fully removed or where the residual settlement has
effectively been completed before culvert construction commences, a nominal crushed rock
or rubble foundation layer will usually be acceptable.
Where the residual settlement is not effectively complete or where variable thicknesses of
marine deposits are suspected, surcharge preloading and fill densification measures can
58
reduce settlement problems. However, it is recommended that special measures are taken to
allow for some differential settlement at the culvert joints. The use of piled foundations
may be considered where differential settlement problems are expected to be particularly
severe, but the initial cost will be relatively expensive, and can result in other forms of
settlement problems, as outlined below.
Normally, culvert outfalls are formed in the seawalls using special concrete outfall blocks.
The difference in settlement between the seawalls and the reclamation will cause differential
movement at the junction with a piled culvert. In addition, differential settlement will also
occur along each side of a piled culvert, as the adjacent reclamation continues to settle.
For carriageways and pedestrian walkways constructed on newly reclaimed land, differential
settlement may cause non-uniform deformations and hence affect the serviceability. These
effects can be mitigated by using flexible pavement that allows future overlay.
To avoid the possibility of differential settlement, buildings constructed on reclaimed land are
usually supported on a piled foundation. The possible effects of negative skin friction on
the pile due to settlement must be taken into account in the design. The magnitude of the
negative skin friction at a particular site will depend on the pile characteristics, fill
characteristics, pile movement and the settlement since completion of the pile. Other types of
foundation, such as a raft or floating foundation, may be considered for low-rise buildings.
For underground drainage and sewerage pipes built in reclamation areas, the effect of
differential settlement may be mitigated by the use of flexible joints, particularly for the
connections between the pipes or ducts entering buildings. The adoption of several short
pipe lengths and flexible joints adjacent to buildings will allow the pipes to accommodate
quite severe differential settlement. The design should ensure that adequate fall is
maintained in gravity sewers after settlement is complete.
59
When designing structures and facilities to be sited on a new reclamation, reference should be
made both to the settlement calculation and the settlement data recorded during the course of
reclamation. Additional ground investigations may also need to be carried out after the
completion of reclamation to obtain the necessary soil parameters for the design. Close
consultation and liaison between the design office, client and maintenance authorities are
necessary throughout various stages of the project.
60
61
REFERENCES
GCO (1984). Geotechnical Manual for Slopes. Geotechnical Control Office, Hong Kong.
GEO (2017b). Model Specification for Soil Testing (Geospec 3) (Continuously Updated E-
Version released on 29 August 2017). Geotechnical Engineering Office, Civil
Engineering and Development Department, HKSAR Government, 324 p.
Jewell, R.A. (1987). The mechanics of reinforced embankments on soft soils. Report No.
OUEL 1694/87, University of Oxford, UK.
Kitazume, M. and Terashi, M. (2013). The Deep Mixing Method, CRC Press, Taylor & Francis
Group, 410p.
Lunne, T., Robertson P.K. and Powell, John J.M. (1997). Cone Penetration Testing in
Geotechnical Practice. Blackie Academic and Professional, UK, 312p.
62
Schiffman, R.L. (1958). Consolidation of Soil under Time-dependent Loading and Varying
Permeability. Proceedings of the Thirty-seventh Annual Meeting, Highway
Research Board, Washington, D.C., pp 589-616.
Sowers, G. F., Williams R.C. and Wallace T. S. (1965). Compressibility of Broken Rock
and Settlement of Rockfills. Sixth International Conference on Soil Mechanics
and Foundation Engineering, Vol. II, Montreal, Canada, 1965, pp. 561-565.
Suzuki, Y. (1982). Deep Chemical Mixing Method using Cement as Hardening Agent.
Proceedings of the International Symposium on Recent Developments in
Ground Improvement Techniques, Bangkok, pp 299-340.
Wai S.K and Lam W.T. (2001). A review of design methods for prediction of primary
consolidation of the marine deposits in Hong Kong. Proceedings of the
International Conference on Construction, Hong Kong, Vol.1: 168-178.
WB (1995). Works Bureau Technical Circular No. 18/95 – Drainage Impact Assessment
Process for Public Sector Projects. Works Bureau, Hong Kong.
WB (1999). Works Bureau Technical Circular No. 13/99 – Geotechnical Manual for
Slopes – Guidance on Interpretation & Updating. Works Bureau, Hong Kong.
Ye, S.L., Han, J., Ye, G.B. (1997). Foundation Treatment and Underpinning Technology
(Second Edition). China Construction Industry Press (In Chinese).
Yeo, K.C. and Woodrow, L.K.R. (1992). Design of embankment on soft ground. ILT’92
ON POLD/Gaga/November 1992.
63
61
FIGURES
62
64
65
63
LIST OF FIGURES
Figure Page
No. No.
11. u – σ Plot 71
73
12. s – δH Plot 71
73
13. Typical Relationship between Height of Fill (h), Time (t) and Lateral 72
74
Deformation (δH)
66
64
65
67
2 Formation level
+++++++++++++++++++++++++++++++++++++++++++++++++
+ + ++ + ++ + ++++ + ++ + ++ + ++ + ++ + + + ++ + ++ + ++ + ++ + ++ + + + ++ + +
+ ++ + ++ + ++ + + + ++ + +~ + ++ + ++ + ++++ + ++ + ++ + ++ + ++ + + + ++ + +++
++++++++++++++++++++++++++++++++++++++++++++++++
+++++++++++++++++++++++++++++++++++++++++++++++++
++++++++++++++++++++++++++++++++++++++++++++++++
+++++++
++++++
++++++++
++++++++
++++!4) Reclamat'1on F'1ll +
· ++++++++
++ ++++++
++++++++++
++++++
+++++++++++++++++ T+TTTTTTTTT++++++++++++++++++++
++++++++++++++++++++++++++++++++++++++++++++++++
+++++++++++++++++++++++++++++++++++++++++++++++++
{1) Geotextile ++++++++++++++++++++++++++++++++++++++++++++++++
+++ +++ +++ +++++ +++ +++ +++ +++++ +++ +++ +++ +++ +++++ ++++
-~, ~..:~-. !. ~:..::. .~ . :·.~-~-'-t: .:!: -~:·+.-.~/>t.~'~)+ "'++d+ +;jol+++k +t+;·t~~.-.-t. t ·~·.~.:~.-~ .·~ .~. t·.~- ~: ~ ·~. t. t- . . ., Seabed
'l· ~"'-:.t::A ·1·~,, .··~ ;,al!__t:l an__!L_ ... ,, ~~- -~<..Jcc.;_l···+ .. . ·, -"-
1 I I I I I I I I I I
1 1 Marine Mud 1
I
1 ...-13) Vertical Band Drain
.,., .. Ill
Notes:
1. Laying of geotextile on the seabed.
2. Deposition of blanket layer.
3. Installation of vertical drains by marine plant.
4. Controlled thin-layer placement of reclamation fill.
100 100
90
/ /
90
80 I 80
70 I I I 70
60 D le B A I 60
50 I / 50
40
I V 40
30
I / I 30
I I
20
10
0
Clay
--
Silt
- ---- ,
Sand Gravel
V
I
20
10
0
Zone B: The soils in this zone are ideally suited for vibrocompaction. They have a fines content of less than 12%.
As for the soils of zone A, the in-situ soil flows towards the vibroprobe during compaction, so that no
backfill has to be added from the top, providing the resulting settlements of the ground are tolerable.
Depending on the initial density and the required densification, settlements due to vibrocompaction
are between 2% and 15% of the thickness of the treated layers.
Zone C: Zone C is still suitable for vibrocompaction, but the required compaction time is drastically increased
compared to zone B. This happens because the surplus water does not drain fast enough from the
compacting soil.
A compaction is only possible by adding backfill from the surface, since the in situ soil does not
flow by itself towards the vibroprobe.
1.2
1.0
,LL 0.8
0.6
yH
aCu
c.--\.--
r 1
~UUU 1
I I
I D I
I
--- --
I
~--------------------1
I
Virgin
compression
E
Recompression Slope= compression ratio, CR
Expansion
log er'
er ' · Effective Stress
E : Strain
-,..--
- ,·
2. Soft deposits may lie within impermeable strata such as stiff alluvial clay.
time
~
Piezometer installed at Point X 0 outside reclamation site
Px,
~
"
~
~
TL TL
"'Q_
"
a;
;:
"'0
a_
r r time
Day X
Average excess pore water Average of the pore water pressure recorded by
pressure at Point X1 on Day x piezometer at x1 between time (t +Tc) and (t +24+ Tc)
- Average of the pore water pressure recorded by
piezometer at x0 between time t and (t+24)
Legend:
Notes:
3. Piezometer outside the reclamation is installed for the purpose of eliminating the tidal effect on the
piezometer reading taken inside the reclamation.
_rGeote xtile
Seabed
_sz__ ..!. .L
Marine /Alluvial Depo sit
Collapsible inclinometer
and extensometer casing
Pneumatic piezometer 'Y.___ Sliding coupling with mu~i prong
anchor with magnet
Inclinometer probe
Probable actions:
~--1" Increase monitoring frequency
• Reduce filling rate
• Stop filling
0 8H
.----------~~
8
s - Settlement
Towards failure
s Safe
0 h
(b) :~ -h Plot
APPENDIX A
Notes:
(1) All testing methods refer to American Society for Testing and Materials (ASTM).
(3) None of the following items shall break before reaching the stipulated tensile strength.
• Drain core.
• Drain filter fabric.
• Seam of the filter fabric.
(4) The ASTM D4632-91 Test shall be carried out using full width jaws on full width of
prefabricated vertical band drains.
(5) Frequency of quality control test shall be one test for 50,000 m length of drain installed.
78
76
D4632-91: Standard Test Method for Breaking Load and Elongation of Geotextiles (Grab
Method)
D4716-87: Standard Test Method for Constant Head Hydraulic Transmissivity (In-Plane
Flow) of Geotextiles and Geotextile Related Products
D4571-93: Standard Test Method for Determining Apparent Opening Size of a Geotextile
79
77
APPENDIX B
CONTENTS
Page
No.
TITLE PAGE 77
79
CONTENTS 79
81
B.1 General 81
83
B.4 References 83
85
80
82
83
81
B.1 General
This appendix gives guidance on the principles of calculating the average degree of
consolidation for a homogeneous soil stratum with or without vertical drains. When a
vertical load is applied, an initial uniform excess pore pressure is assumed generated
instantaneously throughout the soil stratum. This excess pore pressure will dissipate
gradually or almost instantaneously, depending on the permeability of the soil and the
drainage conditions at the boundaries of the stratum, by vertical drainage through the soil to
the horizontal boundaries and/or by radial drainage into pre-installed vertical drains. The
average degree of consolidation indicates how much of the imposed load is transferred to the
effective stress in the soil (with 100% meaning full transfer), defined by:
ui − ut
Ut = ×100% (B1)
ui
Terzaghi’s theory of one-dimensional consolidation predicts the excess pore pressure under
vertical drainage alone. Based on Equation B1, Terzaghi’s theory gives the following term
for the average degree of consolidation due to vertical drainage:
∞
2
Uv = 1− ∑ 2
exp(−M 2Tv ) (B2)
m=0 M
∞
2 Mz
U v,z = 1 − ∑ sin exp(−M 2Tv ) (B2a)
m=0 M
dr
H
Reference may also be made to Lee et al (1992) for more accurate assessment of the degree
of consolidation for layered deposits.
The classical solution is analogous to that described in Section B.2 but flow is horizontal and
radially inwards towards each drain. Barron (1948) arrived at the solutions for the excess
pore pressure at any radial distance from the drain and at any time during consolidation.
Based on Equation B1 and the assumption of equal vertical strain, the following expression
can be established for the average degree of consolidation due to horizontal drainage:
− 8Th
U h = 1 − exp[ ] (B3)
F(n)
ch t
where Th =
D2
ch = Coefficient of horizontal consolidation.
D = Diameter of equivalent cylinder of soil drained by each vertical
drain.
= 1.13 × drain spacing for square grid
= 1.05 × drain spacing for triangular grid
85
83
F(n) is a function mainly relating to drain spacing and size, and the extent of soil disturbance
due to drain installation (smear effect). It has more than one version as addressed in detail
in Barron (1948) and Holtz et al (1991). The basic form of F(n) for ideal drains with no
smear effect can be expressed as:
n2 3n 2 −1
F (n) = 2 ln n − (B4)
n −1 4n 2
where n = D/d’
d’ = Drain diameter.
= drain circumference / π
Regarding well resistance, the effect depends on the permeability of the vertical drains and
the surrounding undisturbed soil as well as the drain diameter. Different versions of a
modified form of Equation B3 that take into account the effect of well resistance (and smear
effect) may be found in Hansbo (1981) and Onoue (1992).
The presence of vertical drains does not prevent the vertical drainage of water in the normal
way. In reality, both horizontal and vertical drainage take place simultaneously. This can
be taken into account using the relationship suggested by Carillo (1942):
U f = U h + U v − U hU v (B5)
where Uf is the average degree of consolidation under combined vertical and horizontal
drainage.
B.4 References
Barron, R.A. (1948). Consolidation of Fine Grained Soils by Drain Wells. Transactions of
the American Society of Civil Engineers, Vol. 113: 718-724.
Carillo, N. (1942). Simple Two and Three Dimensional Cases in the Theory of
Consolidation of Soils. Journal of Maths and Physics, Vol. 21 (1).
86
84
Lee, P.K.K., Xia, K.H. and Cheung, Y.K. (1992). A Study on One-dimensional
Consolidation of Layered Systems. International Journal for Numerical and
Analytical Methods in Geomechanics, Vol 16, pp 815-831.
APPENDIX C
CONTENTS
Page
No.
TITLE PAGE 85
87
CONTENTS 89
89
C.1 General 89
91
C.3 References 92
90
LIST OF FIGURES 93
91
90
88
91
89
C.1 General
This appendix describes the method, namely Asaoka’s graphical method, which can be used
to verify the primary consolidation settlement using the field monitoring data of settlement.
s(t) = a(1 − be −ct ) where a, b and c are constant, and c > 0 (C1)
the discrete values of s(t) at equal time intervals of ∆t can be characterised by the following
recurrence equation:
According to the solutions for both Terzaghi’s one dimensional theory of consolidation and
Barron’s theory of radial consolidation, the primary consolidation settlement at time t and s(t)
can be expressed in the form of Equation C1 as below:
π 2c t
8 − v2
s(t) = s∞ (1− 2 e 4 H )
π
Terzaghi: (C4)
π cv ∆t
2
−
Therefore, β1 = e 4H 2
8cht
−
s(t) = s∞ (1− e D 2 F (n)
)
Barron: (C5)
8ch ∆t
−
Therefore, β1 = e D 2 F (n)
The values of the ultimate primary consolidation settlement, s∞ , can be readily obtained
using the common methods of solving this type of equation. The graphical method
suggested by Asaoka (1978) to find the ultimate primary consolidation settlement using field
measurement data is illustrated in Figure C1. This is based on the linear relationship
between si-1 and si given in Equation C2. The intersection of the si-1 ~ si line ( si = β 0 + β1si−1 )
with another line si-1 = si will give the ultimate primary consolidation settlement (s∞).
In case of multi-stage loading, the line si = β 0 + β1si−1 will be moved up as shown in Figure
C2. When the settlement is relatively small compared with the thickness of soil layer, the
shifted line should be almost parallel to the initial line because β1 should be independent of
the applied load.
C.3 References
LIST OF FIGURES
Figure Page
No. No.
APPENDIX D
WORKED EXAMPLES
98
96
99
97
CONTENTS
Page
No.
TITLE PAGE 97
95
CONTENTS 97
99
D.3 Example 3 – Monitoring of Pore Pressure for Stability during Fill Placement 113
115
Given
1. A reclamation site has marine deposits of average undrained shear strength 5.0 kPa and
thickness of 10.0 m with a water depth of 10.0 m.
2. Unit weight of reclamation fill is 19.0 kN/m3.
3. The factor of safety for the leading edge should not be less than 1.2.
Task
Determine the minimum length of the leading edge if the first layer of fill to be placed is
3.0 m thick.
Solution
Equation 3.3 may be applied for preliminary analysis. The length of the leading edge of the
reclamation is taken as the length from the toe to the crest of the embankment Le in the
equation.
The minimum length of leading edge can therefore be calculated using Equation 3.3 as
below:
Therefore,
− 2.8836
(1+ )Le
(1.2)(8.9)(3.0) Le
= 4+
5.0 10.0
Le = 27.0 m
Given
1. The loading variations of a small reclamation project, which involve filling to final
formation level, application of surcharge preloading, removal of surcharge preloading
and application of future imposed load, are shown in Figure D1.
2. Vertical drains are installed before fill placement and the programme of reclamation is
assumed as follows:
Table D2.1
Reclamation Profile
Seabed level -8.0 mPD
Mean sea level +1.3 mPD
Final formation level +4.5 mPD
Surcharge preloading thickness 5.0 m
Fill data
Unit weight, γfill 19.0 kN/m2
Logarithmic creep compression rate, α 1.0%
104
102
Task
Approach
Preloading by surcharge load with band drain installation is applied to accelerate the
consolidation settlement. The marine deposit is subject to time-dependent loading as shown
in Figure D1. The loading due to reclamation fill is taken to be increased linearly and the
non-uniform loading pattern is schematised as uniform loading pattern.
The marine deposit is divided into 10 sub-layers in the calculation and the degree of
consolidation is calculated for each sub-layer. The primary consolidation settlement is
obtained by summing up the settlement of each sub-layer.
Band drains are installed before commencement of filling and their function is assumed
normal throughout the reclamation period and the surcharging period. The compression
ratio, CR, is assumed to be constant for the whole marine deposit stratum and also remain
constant in the process of primary consolidation. If the soil is variable, the depth should be
represented by soil layers with different CR with reference to site investigation results.
N.B.
a. Only settlements in marine deposit and reclamation fill are considered and settlement in
other soil stratum is neglected. In real case, settlement of all soil strata, including the
alluvium clay layer, should also be considered.
105
103
b. The designer shall decide the most appropriate schematization for the loading sequence.
c. Alluvium sand is assumed underlying the marine deposit. As such, double drainage
condition can be assumed.
Settlement estimation
(1) Final primary consolidation settlement due to reclamation fill and future imposed load
The final formation level of the reclamation is +4.5 mPD after removal of surcharge
preloading. Taking into account the settlement, which is initially assumed to be 3.0 m (it
should be adjusted based on subsequent calculated settlement), the total effective stress
increment due to the loading of reclamation fill is given by:
Depth of fill below MSL = +1.3 mPD - (-8.0 mPD) + 3.0 m = 12.3 m
Depth of fill above MSL = +4.5 mPD - 1.3 mPD = 3.2 m
The primary consolidation settlement due to the loading of reclamation fill and future
imposed load of each sub-layer (without surcharge preloading) is calculated as follows:
Table D2.2
Total
Initial
effective
z effective Settlement
Sub-layer stress
(mPD) stress (m)
increment
(kN/m2)
(kN/m2)
1 -8.5 2.95 190.3 0.53
2 -9.5 8.85 190.3 0.39
3 -10.5 14.75 190.3 0.33
4 -11.5 20.65 190.3 0.29
5 -12.5 26.55 190.3 0.26
6 -13.5 32.45 190.3 0.24
7 -14.5 38.35 190.3 0.22
8 -15.5 44.25 190.3 0.21
9 -16.5 50.15 190.3 0.20
10 -17.5 56.05 190.3 0.19
Total 2.87
106
104
The final primary consolidation settlement due to the loading of reclamation fill and future
imposed load, Sp(final), is estimated to be 2.87 m. This amount is close to the initial assumed
value of 3 m and therefore recalculation is not made in this example.
(2a) Degree of consolidation due to the loading of reclamation fill (with vertical drains) at the
end of the 9.5th month (see Figure D1)
9 1
t = 10 − − = 5 months = 0.42 years
2 2
cv t 1.5 × 0.42
Tv = = = 0.025
d2 52
(for double drainage, d = 10.0/2 = 5.0 m)
Equation B2a is applied to calculate the degree of consolidation for each sub-layer of the
marine deposit as below:
Table D2.3
2 Mz
sin exp(− M 2Tv ) with z (m) =
m M M H dr
0.5 1.5 2.5 3.5 4.5 5.5 6.5 7.5 8.5 9.5
0 0.5π 0.187 0.543 0.846 1.067 1.182 1.182 1.067 0.846 0.543 0.187
1 1.5π 0.111 0.241 0.172 -0.038 -0.217 -0.217 -0.038 0.172 0.241 0.111
2 2.5π 0.039 0.039 -0.039 -0.039 0.039 0.039 -0.039 -0.039 0.039 0.039
3 3.5π 0.008 -0.001 -0.006 0.009 -0.004 -0.004 0.009 -0.006 -0.001 0.008
sum 0.344 0.821 0.974 0.999 1.000 1.000 0.999 0.974 0.821 0.344
ui 0.656 0.179 0.026 0.001 0.000 0.000 0.001 0.026 0.179 0.656
2(5 + 100)
d’ = = 66.8 mm
π
D
n= = 23.7
d'
n2 3n 2 − 1
F (n) = ln n −
n2 − 1 4n 2
= 2.42
From Equation B3,
− 8Th
U h = 1 − exp[ ]
F (n)
− 8 × 0.25
= 1 − exp[ ]
2.42
= 0.56
calculated as below:
Table D2.4
z
Layer ui
(mPD)
1 -8.5 0.849
2 -9.5 0.639
3 -10.5 0.571
4 -11.5 0.561
5 -12.5 0.560
6 -13.5 0.560
7 -14.5 0.561
8 -15.5 0.571
9 -16.5 0.639
10 -17.5 0.849
(2b) Effective stress increment at the end of the 9.5th month (see Figure D1)
The marine deposit is subject to different degree of consolidation at different depth. The
calculation of the primary consolidation settlement for the first sub-layer is illustrated as an
example as follows.
108
106
The initial effective stress at the center of the first marine deposit sub-layer is given by
The first estimate of settlement occurs at end of 9.5th month is taken to be 1.9 m (it should be
adjusted based on subsequent calculated settlement). Taking into account the effect of
settlement in the change of effective stress increment (larger portion of reclamation fill is
submerged below seawater level), the effective stress increment due to the loading of
reclamation fill at the centre of the first sub-layer is given by:
Depth of fill below MSL = +1.3 mPD - (-8.0 mPD) + 1.9 m = 11.2 m
Depth of fill above MSL = +4.5 mPD - 1.3 mPD - 1.9 m = 1.3 m
From Equation 4.1a, the primary consolidation settlement in the first sub-layer (H = 1.0 m for
each sub-layer) due to the loading of reclamation fill is given by:
Table D2.5
Effective
Initial Settlement at
z stress
Layer effective stress the end of 9.5th
(mPD) increment
(kN/m2) month (m)
(kN/m2)
1 -8.5 2.95 105.6 0.45
2 -9.5 8.85 79.5 0.29
3 -10.5 14.75 71.1 0.22
4 -11.5 20.65 69.7 0.19
5 -12.5 26.55 69.7 0.16
6 -13.5 32.45 69.7 0.14
7 -14.5 38.35 69.7 0.13
8 -15.5 44.25 71.1 0.12
9 -16.5 50.15 79.5 0.12
10 -17.5 56.05 105.6 0.13
Total 1.96
The primary consolidation settlement due to the loading of reclamation fill at the end of 9.5th
month is estimated to be 1.96 m and is close to the initial estimate of 1.9 m. Therefore,
recalculation of the effect of settlement on the change in effective stress increment is not
carried out in this example.
(2c) The degree of primary consolidation due to reclamation fill and surcharge preloading
(with vertical drains) at the time of surcharge removal (end of 22nd month)
1
t = 13 − = 12.5 months = 1.04 years
2
cv t 1.5×1.04
Tv = = = 0.062
d2 5.0 2
For rough estimation, Equation B2a is assumed valid to calculate the degree of consolidation
for each sub-layer of the marine deposit. They are calculated as below:
110
108
Table D2.6
2 Mz
sin exp(− M 2Tv ) with z (m) =
m M M H dr
0.5 1.5 2.5 3.5 4.5 5.5 6.5 7.5 8.5 9.5
0 0.5π 0.171 0.496 0.773 0.974 1.079 1.079 0.974 0.773 0.496 0.171
1 1.5π 0.049 0.106 0.076 -0.017 -0.095 -0.095 -0.017 0.076 0.106 0.049
2 2.5π 0.004 0.004 -0.004 -0.004 0.004 0.004 -0.004 -0.004 0.004 0.004
3 3.5π 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
sum 0.224 0.606 0.844 0.953 0.988 0.988 0.953 0.844 0.606 0.224
ui 0.776 0.394 0.156 0.047 0.012 0.012 0.047 0.156 0.394 0.776
Note :
Strictly speaking, Equation B2a is not valid as the excess pore water pressure is not constant
throughout the marine deposit layer. The excess pore water pressure, ue, at depth z after
time t is given by:
n=∞
nπz nπ z n 2π 2 c v t
2d
1
u e = ∑ ∫ u i sin dz sin exp(− )
n=1 d 0 2d 2d 4d 2
Alternatively, the method developed by M. Carter for Macau International Airport can be
adopted to determine the time curve for the degree of consolidation. For details, see pp 35-
40 in Transactions, Volume 3, Number 1, the Hong Kong Institution of Engineers.
− 8Th
U h = 1 − exp[ ]
F (n)
− 8 × 0.63
= 1 − exp[ ]
2.42
= 0.88
calculated as below:
Table D2.7
z
Layer ui
(mPD)
1 -8.5 0.973
2 -9.5 0.927
3 -10.5 0.899
4 -11.5 0.886
5 -12.5 0.881
6 -13.5 0.881
7 -14.5 0.886
8 -15.5 0.899
9 -16.5 0.927
10 -17.5 0.973
(2d) Primary consolidation settlement due to reclamation fill and surcharge preloading (with
vertical drain) at the time just immediately after surcharge removal (end of 22nd month)
The first estimate of settlement occurs at end of 22nd month is taken to be 3.0 m (it should be
adjusted based on subsequent calculated settlement). The effective stress increment due to
the loading of reclamation fill at the centre of the first sub-layer is given by:
Depth of fill below MSL = +1.3 mPD - (-8.0 mPD) + 3.0 m = 12.3 m
Depth of fill above MSL = 5.0 m + 4.5 mPD - 1.3 mPD – 3.0 m = 5.2 m
The effective stress increment if all pore pressure is dissipated at end of 22nd month:
Effective stress increment at end of 9.5 months = 105.6 kN/m2 (see Table D2.5)
As only 97.3% pore water pressure is dissipated at end of 22nd month (see Table D2.7),
therefore
From Equation 4.1a, the primary consolidation settlement in the first layer (H = 1.0 m for
each sub-layer) due to the loading of reclamation fill and surcharge preloading (with vertical
drains) is given by:
The settlement for the primary consolidation settlement due to reclamation fill and surcharge
preloading (with vertical drains) at the time of surcharge removal (end of the 22nd month) for
all the sub-layers are calculated as follows:
Table D2.8
Initial Effective stress Settlement at
z
Sub-layer effective stress increment the end of 22nd
(mPD) 2 (kN/m )2
(kN/m ) month (m)
1 -8.5 2.95 205.5 0.54
2 -9.5 8.85 198.9 0.40
3 -10.5 14.75 194.4 0.33
4 -11.5 20.65 192.5 0.29
5 -12.5 26.55 191.9 0.27
6 -13.5 32.45 191.9 0.24
7 -14.5 38.35 192.5 0.23
8 -15.5 44.25 194.4 0.21
9 -16.5 50.15 198.9 0.20
10 -17.5 56.05 205.5 0.19
Total 2.90
The total consolidation settlement due to reclamation fill and surcharge preloading (with
vertical drains) at the end of the 22nd month is estimated to be 2.9 m.
113
111
Note : The settlement at the end of the 22nd month is equal to 2.9 m which is very close to the
initial estimate of 3.0 m. Further recalculation is therefore not required in this
example.
As the effective stress increment in the marine deposit is greater than that due to the future
loading, the marine deposit is considered over-consolidated. A rebound will occur after
removal of surcharge loading. The change in settlement will then follow recompression
curve when the future imposed load (20.0 kN/m2) is applied on the reclamation.
Effective stress due to self weight of marine mud (at centre of soil layers)
= 5.0 x (16.0 - 10.1) = 29.5 kN/m2
Depth of fill below MSL = +1.3 mPD - (-8.0 mPD) + 2.9 m = 12.2 m
Depth of fill above MSL = +4.5 mPD - 1.3 mPD = 3.2 m
(Surcharge removed to formation level +4.5 mPD only)
The order of the maximum recompression, when the rebound is fully developed after a
certain period of time, can be approximated by:
σ v0 '+∆σ v
S max,recompression = H.RR.log( )
σ v0 '
29.5 + 169.4 + 20
= 10.0(0.06) log( )
29.5 + 169.4
= 25 mm
The residual settlement due to primary consolidation is therefore equal to about 25 mm.
N.B. The future imposed load will be applied shortly (2 months later) after the removal
of the surcharge loading. As a result, the rebound will not be fully developed. The order
of recompression should be smaller than 25 mm in principle.
114
112
Due to the primary settlement, the thickness of the reclamation fill is taken to be 15.5m.
The residual settlement of reclamation fill due to creep at end of 22nd month:
tc
50 −
S c,t (residual) = Hα log( 2)
tc
t−
2
50 − 9/ 2/12
= 15.5× 0.01× log( )
22/12 − 9 / 2 /12
= 237 mm
D.3 Example 3 – Monitoring of Pore Pressure for Stability during Fill Placement
Given
A piezometer installed in the marine deposit layer revealed abnormalities during the fill
placement works. Increase of excess pore water pressure was found larger than the
predicted value as shown in Figure D2. Pause of filling works was considered necessary
(see Section 5.3.2).
The dimensions of vertical drains were the same as those in Example D.2. The coefficient
of consolidation (horizontal) was taken as 1.5m2/year.
Task
Estimate the time required (t) for the excess pore water pressure to fall back to the normal
magnitude.
Approach
(1) Define the abnormal excess pore pressure as the initial excess pore pressure (uo).
(2) Define the target normal excess pore pressure (ue).
(3) Determine the required degree of consolidation (Uh) for dissipation of excess pore
pressure from uo to ue.
(4) Back calculate the time factor (Th) from the required Uh.
(5) Obtain the actual time t required from Th.
Solution
Neglecting vertical drainage, average degree of consolidation required to dissipate the above
pore pressure is given by:
5.1
Uh = = 0.255
20
116
114
The value of F(n) in Example D.2 was used because the dimensions and layout of vertical
drains were the same. Therefore, F(n) = 2.42.
Therefore,
D 2Th 2.1(0.09)
t= = = 0.13 year
ch 1.5
i.e. Time required for the excess pore pressure to fall back to the normal magnitude is about
2
1 months.
3
117
115
LIST OF FIGURES
Figure Page
No. No.
GLOSSARY OF TERMS
Adsorbed water. A soil particle carries an electrical charge, which attracts ions to neutralize
its net charge. Such attracted ions, which are weakly held on the particle surface
and can be readily replaced by other ions, are termed exchangeable ions. The water
attached to the exchangeable ions attracted to the soil surface is called adsorbed
water and is not free to flow under gravity, unlike the pore water.
Blanket layer. A layer of free draining granular material placed on top of the seabed in a
drained reclamation. It is used primarily for spreading the load of fill placed on top
of it and to provide a filter layer to prevent coarser material being punched into the
soft marine deposits. If vertical drains are used, it also provides a drainage layer
that ensures vertical drainage from the underlying marine deposits.
Compression ratio. Slope of the virgin compression line in a strain-log effective stress
curve.
Displacement method. An old reclamation method involving direct tipping of fill from
trucks onto the seabed without dredging away or treating the underlying soft
deposits.
Drained reclamation. Reclamation with the soft deposits left in place with or without
surcharge preloading and/or vertical drains.
Dredged reclamation. Reclamation with the soft deposits removed before the fill is placed.
Effective preconsolidation pressure. The maximum effective vertical stress that has acted
on a soil layer in the past.
Excess pore water pressure. The increase in pore water pressure above the final or steady-
124
state value.
One-dimensional (1-D) strain. A type of consolidation in which deformation and water flow
are all in one direction and the deformation in orthogonal directions is considered to
be zero. It is generally applicable to reclamation works where the thickness is
small compared to the lateral extent.
Recompression ratio. Average slope of the recompression line in a strain-log effective stress
curve.
Residual settlement. The amount of remaining settlement due to primary consolidation and
secondary consolidation (or creep) of the sub-soils and fill that would occur from a
given time onwards, after the completion of filling works.
Secondary consolidation. Long-term settlement of clay that occurs under constant effective
stress (thought to be due to squeezing out of the adsorbed water and rearrangement
and/or deformation of clay particles).
Smear effect. Effect of reduced permeability of the soil surrounding a vertical drain due to
the disturbance caused by the installation of the vertical drain.
Surcharge preloading. A ground treatment method, which can both accelerate the
consolidation of sub-soil layers and densify the fill, by placing surcharge (usually
additional fill) temporarily on top of the reclamation.
Vertical drains. Vertical drainage conduits (such as band drains) or wells (such as sand
drains) installed within the soils at spacing closer than the drainage distance for
vertical flow, which shorten the drainage path and hence accelerate the consolidation
125
process.
Vibrocompaction. A fill densification method for granular soils, which involves penetration
and controlled retraction of a vibrating tool in the soil.
Well resistance. The finite permeability of vertical drains with respect to the surrounding
soil.
126
127
GLOSSARY OF SYMBOLS
γ Unit weight
δH Lateral deformation
Cc Compression index
CR Compression ratio
Cr Recompression index
Dr Relative density
e Void ratio
F Factor of safety
Ip Plasticity index
l Length of vertical slices along the selected surface in slip surface analysis
RR Recompression ratio
s Settlement
Sresidual,t Residual settlement of a reclamation due to the sub-soil and fill at time t