H-6745 00 Mef 00 081 DC
H-6745 00 Mef 00 081 DC
H-6745 00 Mef 00 081 DC
MODIFICATIONS TABLE
A M.SUBRAMANIAN HARSH GHOGARE VINOD SANATOO 4th SEPTEMBER 2014 FIRST ISSUE GFE
INDEX
1. PURPOSE
2. SCOPE
3. SAFETY PRECAUTION
4. PREPRATION
ERECTION PROCEDURE
6. ERECTION OF RUNNER
7. TRAIL ASSEMBLY OF HEAD COVER, SHAFT SEALSUPPORT & GUIDE BEARING SUPPORT
10. FINAL ASSEMBLY OF WICKET GATE, OPERATING RING AND ITS MECHANISMS
1. PURPOSE
The propose of this document is to define general erection guide lines to be followed at site by Erection
team, General assembly drawings are the final reference for installation.
Note: This Erection Procedure can be changed by Erection Supervisor at site based on site condition.
2. SCOPE
3. SAFETY PRECAUTION
To be ensured by Client :
3. No activities are going above working fronts to avoid any object falling.
7. All the gas cylinders opening are properly tight and chained to avoid any fire.
• Alstom will also ensure above applicable safety precaution in their working area during execution.
4. PREPARATION
Client to ensure all bench marks. Unit axis (X & Y) and Elevation.
Alstom to ensure that all bench marks are punched on properly fixed plates to avoid any
Misalignment during the course of execution.
ERECTION PROCEDURE
- After completion of 4th Stage concrete (Spiral Case and upper Pit liner) remove all bracing from upper and
lower pit liner.
- Dismantling of Dummy distributor from stay ring and keep it on service bay to use for second unit spiral
case testing.
- If necessary, perform grinding on Stay ring ID to achieve the required radius dimension, in consents with
engineering.
- Measurement of height between DT top and Stay Ring to determine the cutting of extra length of DT.
- At pit - installation of wedging washer on Stay Ring bottom flange and determine the thickness of washer
, machining of washer as required for adjusting horizontality and elevation of Bottom ring, and tack
welding of wedging washer on Stay Ring .
- Check horizontality at washer along with before & after machining of washer.
- Align the bottom ring w.r.t Unit Centre Line and elevation.
- Install the fixing bolts between Cone and bottom ring and lift the cone and clamp with Bottom Ring .
- Check the alignment of DT cone w.r.t Centre Line & Bottom Ring.
- Fixing of weld clamp on DT cone and DT, and welding with DT and DT Cone.
- Fixing of back plate , welding with DT cone and apply Silicon on DT side.
- Dismantle Bottom Ring from DT Cone. (Before dismantling of Bottom ring, drill and ream with Stay Ring
and DT Cone.
- Lowering of Bottom Ring on Stay Ring and clamping with Stay Ring.
- Check the alignment of Bottom Ring w.r.t centre Line & Elevation.
- Install “O” ring between Stay Ring and Bottom Ring with seal retaining plate and clamping.
- Fill Belzona N*1111 inside clamping ring holding bolts and cleaning to maintain hydraulic profile.
6. ERECTION OF RUNNER
- Prepare 08 nos. of wedge for runner erection on DT cone. (Will keep Runner elevation -25mm from design
elevation)
7. TRAIL ASSEMBLY OF HEAD COVER, SHAFT SEALSUPPORT & GUIDE BEARING SUPPORT
- At pit - installation of wedging washer on Stay Ring Top flange and determine the thickness of washer ,
machining of washer as required for adjusting horizontality and elevation of Head Cover, and tack welding
of wedging washer on Stay Ring .
- Check horizontality at washer along with before & after machining of washer.
- Lower Head Cover on Stay Ring and alignment of Head Cover with Bottom ring and runner.
c) Distributor Height.
d) Gap Between Upper Face Plate & Wicket Gate upper face.
- Lowering of Inflatable Seal Support on Head Cover Flange, Centering and pining with head cover.
- Lowering of Guide Bearing Support on Head Cover flange, Centering and Provisional Pinning with Head
Cover.
- After trial Assembly dismantled Guide Bearing Support, Inflatable Seal Support and Head Cover.
- Install seal , Bronze seal Sector and inner and outer seal clamp to Bottom Ring and Head Cover.
- Lowering all wicket gate on bottom Ring with “U” seal and “O” ring and keep the wicket gates in Closed
position.
- Lowering of Head Cover on Stay Ring upper flange. ( Close/protect all opening on Head Cover to prevent
falling of any material between Runner and Head Cover.)
c) Distributor Height.
d) Gap Between Upper Face Plate & Wicket Gate upper face.
- Install “O” ring between Stay Ring and Head Cover with seal retaining plate and clamping
- Fill Belzona N*1111 inside clamping ring holding bolts and cleaning to maintain hydraulic profile
- Installed all upper Housing on Head Cover clamp with head cover with screw and dowel pin.
- Centering/ clamping of regulating ring with head Cover, check the clearance at vertical and horizontal
sectors.
Note: Operating Ring Mechanism components at turbine pit before Shaft Free.
At Service Bay:
- Cleaning of Shaft.
- Installed handling device as per drawing and put Shaft in vertical position.(H-6745 00 MEF 80006LD)
- Assembly of guide bearing oil pot around shaft and Seal welding/ NDT.
AT Pit:
- Lowering Turbine Shaft on Runner for coupling. (respect R-R mark on flange before coupling)
Note: Transfer the Centre line & shaft Elevation on Pit Liner and record for reference.
- Lower and keep secure all turbine heavy components on head cover.
10. FINAL ASSEMBLY OF WICKET GATE, OPERATING RING AND ITS MECHANISMS
- Lowering of assembly of Wicket Gate Lever and thrust washer on upper housing.
- Installation of Wicket Gate handle on Wicket Gate lever , install breaking pin and clamp with special
stud.
- Adjust the Wicket Gate clearance by adjusting screw at top and Bottom.
- Installation of counter thrust ring with strippable shims and adjust the Gap with thrust washer and clamp
with upper housing.
- Check the gap between counter thrust ring and thrust washer.
- Close all Wicket Gate and fixed with rope and pull -lift.
- Installation of Link between Wicket Gate handle and regulating ring with offset pin and link pin .
- Installed wearing plate on Shaft and Secure with bolt as per torque.
- Lower inflatable seal support assembly on Head Cover and clamp with Head Cover.
- Check the radial Gap between seal holder and wearing ring.
- Lower all Shaft Seal component and keep secure at Head Cover.
- Assembly of Sealing ring with movable Ring. ( Don’t forget copper implant and pin to assemble)
- Lower and assemble Fixed Support on Inflatable seal support. ( Install “U” seal and “O” ring )
- Assemble two thrust block in diametrical opposite position on movable ring and drill and rim with
movable ring .
- Assemble all thrust block on movable ring with deflector and ensure clearance between tensile rod and
clamp with movable ring.
- Assemble Springs , Special Washer and Screw and set the Spring height.
- Installation of Shaft seal Cooling water coupling on movable ring as per Drawing no. H6745 00 MEF 70
07LD.
- Installation of pressure taping connector and pipe as per drawing no. H6745 00 MEF 70 14 LD.
- Install RTD from movable ring to Tank. As per drg. H674500 MEF 48 001 LD.
- Installation of cover.
- Centering of TGB support with Shaft. (put in place provisional dowel pin )
Turbine Guide Bearing Assembly after Turbine and Generator coupling & Run out
- Lift the oil pot and secure with Shaft before start Shaft Seal assembly.
- Install Guide Pad Support on TGB support and clamp with TGB support.
- Lower and Assemble oil pot with Bottom cover and clamp with bolt .
- Install “O” ring on Bottom Cover and lift the complete assembly and clamp with TGB bottom with bolts.
- Install Guide Bearing pads on pad support, Guide pad pins , hex bolt, threaded cylinder, wedge locking
plate, nut & Taper wedge .
- Adjust gap with taper wedge on all 08 nos. of pad by adjusting taper wedge.
- Installation of Instrumentation as per drawing no. H 6745 00 MEF 40 003 LD. (RTD, Level Indicator,
moisture detector etc)
- Assembly of sealing cover with lower diaphragm , centering, clamping and doweling with TGB support.
- Assembly of cooling oil hose pipe with ‘O” ring and locking with lock plate.
- Assembly of upper bearing cover with upper diaphragm , centering, clamping and doweling with TGB
support.
Sketch No: - 9
Refer IS No : 48,49,50,51,52,53,54 & 55
- Installation in the recesses of the handling tool of Servomotor as per drawing No. H6745 00 MEF 80
016LD
- Lower and installed Servomotors without Adjusting washer to the base plate. (Use soft wedge)
- Alignment of Servomotors . ( Offering –up the servomotor in respect to distributor in closed position)
- Check alignment.
- Dismantled Servomotor, install adjustable washer after machining, re- install Servomotor and Clamp
with Base plate.
- The prestressing of the distributor and the control of good working of lock will be carried out during test.
- Before Generator top Shaft Lowering, installation of Central Pipe with “O” ring and clamp, drill /rim for
dowel.
- Installation of Piping.
- Installation of Instrumentation.
b) Centering at TGB.
Control sheets
Reference Drawing