Dear Sir,
Please go ahead for pitching as sample.
Dear Sir,
Submitting you the revised MS of Stone Pitching work along with approved JSA for your kind
approval. We have incorporated the following comments in the revised MS. Please approve the same
to start the work.
Biranchi Mohanty
Assistant Manager-Quality (BU-Railways)
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you
recognize the sender and know the content is safe.
Dear Sir,
Please add a few points such as
https://outlook.office.com/mail/inbox/id/AAQkAGNkOTkwNjA1LTcwZDUtNDA5ZC1hNjA5LThiYzgyMWIyY2FmZAAQACjtqKYkKxxJvZw9%2FVafd… 1/3
1/8/24, 4:50 PM Mail - Biranchi Mohanty - Outlook
You can proceed for a sample slope pitching demonstrating in any one of the bridges for
approval.
Dear Sir,
Refers to the above, please find attached MS, checklist & JSA for your review and approval. Kindly
approve the same to start the activity at site.
Biranchi Mohanty
Assistant Manager-Quality (BU-Railways)
This Email and any attachments therewith are for the sole use of the intended recipient(s) and may
contain confidential and privileged information. If you are not the intended recipient, please notify
the sender immediately and destroy / delete this message or copies thereof and any attachments
therewith. Any unauthorized use, disclosure or copying of this message and the attachments
thereto (in whole or part), in any manner is strictly prohibited and may constitute unlawful act.
While KEC takes reasonable precautions to protect its IT Systems, the recipient acknowledges that
emails could be illegally intercepted, corrupted, lost, destroyed, arrive late or incomplete or contain
viruses and in such an event KEC will not be liable for any errors, omissions, viruses, damages in the
contents of such message and attachments therewith.
This Email and any attachments therewith are for the sole use of the intended recipient(s) and may
contain confidential and privileged information. If you are not the intended recipient, please notify
the sender immediately and destroy / delete this message or copies thereof and any attachments
therewith. Any unauthorized use, disclosure or copying of this message and the attachments
thereto (in whole or part), in any manner is strictly prohibited and may constitute unlawful act.
While KEC takes reasonable precautions to protect its IT Systems, the recipient acknowledges that
emails could be illegally intercepted, corrupted, lost, destroyed, arrive late or incomplete or contain
https://outlook.office.com/mail/inbox/id/AAQkAGNkOTkwNjA1LTcwZDUtNDA5ZC1hNjA5LThiYzgyMWIyY2FmZAAQACjtqKYkKxxJvZw9%2FVafd… 2/3
1/8/24, 4:50 PM Mail - Biranchi Mohanty - Outlook
viruses and in such an event KEC will not be liable for any errors, omissions, viruses, damages in the
contents of such message and attachments therewith.
https://outlook.office.com/mail/inbox/id/AAQkAGNkOTkwNjA1LTcwZDUtNDA5ZC1hNjA5LThiYzgyMWIyY2FmZAAQACjtqKYkKxxJvZw9%2FVafd… 3/3
METHOD STATEMENT FOR STONE PITCHING WORK AT BRIDGES
Objective
The method describes about the stone pitching work at Bridge approach slopes beside the
curtain wall on both end.
Document Reference
Responsible Person
Site Engineer
Site Supervisor
Material
Boulder 300mm size
Crusher dust (10mm & 6mm mixed) as backing material
Mortar 1:6
Concrete of M15 grade Leveling Course
Machinery
Excavator
Dumper
Wooden Rammer
Procedure
1. Boulders of regular size of 300mm & Stone dust shall be ready at site. Before stone
pitching, the formation behind the return wall to curtain wall shall be dressed to
maintaining at a slope 1:1.5 as mentioned in the drawing. The slope shall be
compacted by manual ramming.
2. In order to prevent escape of the embankment material through the voids of the stone
pitching a layer of 100 to 150mm thick 10mm & 6mm mixed crusher dust as backing
material shall be laid over the embankment material. In addition, this layer enables
greater stability and friction for settlement of boulders firmly without rolling off from top.
5. Strip PCC with M20 grade PCC shall be done from sides to confine and to prevent
Boulder sliding. Curing of strip PCC and mortar shall be done by water sprinkling for
7days.
We shall make a sample stone pitching at any of the bridges.
6. FQP vide document no. Doc no- H-W020-600-E-QC-GN-037 & attached Checklist shall be
maintained for records.
Package:- Phase-2
Drawing No.:
1 Materials availability