MOS Plastering

The document provides a method statement for plastering works at an airport terminal project. It outlines the objectives, organization, manpower, materials, equipment, methodology, environmental issues, quality control, and safety measures for the plastering scope of work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
341 views7 pages

MOS Plastering

The document provides a method statement for plastering works at an airport terminal project. It outlines the objectives, organization, manpower, materials, equipment, methodology, environmental issues, quality control, and safety measures for the plastering scope of work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Document No : TBR-P-PM-MS-01

Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

METHOD STATEMENT :
PLASTERING WORKS

JOB TITLE:

DESIGN AND BUILD FOR THE PROPOSED


OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH
AIRPORT, IPOH, PERAK DARUL RIDZUAN

Prepared by Signature

TERAS BUDI RESOURCES SDN BHD

Reviewed by Process Owner Signature

Effective Date
11/03/2024

1
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

INDEX

1.0 OBJECTIVE

2.0 PROJECT ORGANISATION

3.0 MANPOWER LIST

4.0 MATERIAL LIST

5.0 MACHINERY AND TOOLS

6.0 METHOD OF STATEMENT (METHODOLOGY)

7.0 ENVIROMENTAL ISSUES

8.0 QUALITY ASSURANCE & QUALITY CONTROL

9.0 SAFETY MEASUREMENT

10.0 FINAL REPORT

11.0 APPENDIX

2
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

1.0 OBJECTIVE:
This work method statement covers outline procedure for Brickworks for DESIGN AND BUILD
FOR THE PROPOSED OPTIMIZATION OF TERMINAL FACILITIES AND ITS ASSOCIATED
WORKS AT SULTAN AZLAN SHAH AIRPORT, IPOH, PERAK DARUL RIDZUAN.

2.0 PROJECT ORGANISATION:


Company Name MALAYSIA AIRPORT SDN BHD
MALAYSIA AIRPORTS CORPORATE OFFICE,
Address PERSIARAN KORPORAT KLIA,
64000 KLIA, SEPANG,
SELANGOR DARUL EHSAN
Contact Person
Position
Contact Number

3.0 MANPOWER LIST


Below is the list of manpower involved in this scope of work:
No. Name Designation Initial

1. Site Agent

2. Site Supervisor

3. Workers

4.

5.

6.

7.

4.0 MATERIAL LIST (SDS required for any chemical need to be used)
Below is the list of materials that will be used in this scope of work:

No. Material / Chemical


Model / Brand

3
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

Wallcrete
1.
Quick skim
2.
Fine sand
3.
Water
4.

5.

6.

5.0 MACHINERIES AND TOOLS


Below is the list of machinery and tools that will be used in this scope of work:

Production
Machineries / Tools Working Hours / Day
No Rate / Unit / Day

Drum mixer
1.
Wheel borrows
2.
Lifting Slings
3.
Spirit Plumb Level
4.

Trowel
5.
String
6.
Long Timber trowel
7.

4
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

6.0 METHOD OF STATEMENT (METHODOLOGY)

The sequence of the work for the plastering can be summaries follows:

a) Prior to the plastering work, the wall surfaces must be free from fungus, ready to receive
the plaster.

b) The wall surface also must be spray with water if clay brick built the walls. The purposed is
to prevent wall plaster from crack if wall is too dry and serve to clean a layer of dust.

c) The ratio of cement sand mortar mixer for cement plaster is 1:6

d) The plasterwork shall follow upon the completion of wall. The plastering thickness shall be
in accordance specification.

e) Tools as such straight edge, scoop, sponge, brush and other small tools are used to
flatten/smoother the plasterwork.

f) All the sanitary pipe and M&E piping shall be installed before plastering work start.

g) Before applying first coat, setting out work for plaster wall shall be carried out to mark the
plaster thickness. Marker peg and angle bead (A3-5-S) shall be install.

h) Site supervisor is to check the marker peg is properly level and the vertically of the angle
bead. Submit inspection form to C.O.W for inspection before proceed with plastering
works.

i) Mix cement mortar in mix of 1:6. The plasterer shall use the marker as the refence point
and apply in two coats generally to a thickness of 20mm. 1st coat for plain surface to be
rough plastered. After adequate harden of the plaster surface, 2nd coat to be smooth finish
for external wall using sponge.

j) If the plaster wall is without enclosure surround Polythene sheet or canvas be used to
prevent the traffic or rainwater from enters to the wall surface.

7.0 ENVIRONMENTAL ISSUES

7.1 Environmental Aspect, Impact & Control Measures.

The airside activities that will be carried out during the operation stage and the potential
environmental impact that may occur is summarized with mitigation measures in the following
table.

5
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

Activities Aspects Potential Impact Proposed Mitigation


Inspection/Operation Routine inspection Oil/lubricant Perform oil/lubricant
and maintenance spillage replacement with funnel
and spillage container.
Fuel filling Perform fuel filling by using
funnel and spillage
container.

Mobilisation Moving in and out Smoke emission Ensure vehicle


maintenance is done as
per schedule
8.0 QUALITY ASSURANCE & QUALITY CONTROL

8.1 Contractual Requirements


As per Tender Document requirement.

8.2 Inspection & Reporting :


i) Site Diary
ii) Test Form

8.3 Follow up & Evaluation


Shall refer to our Standard Operation Procedure.

9.0 SAFETY MEASUREMENT


i. All work is prohibited to start before receiving Permit to Work (PTW) by the Building Owner/
Project Owner.
ii. All site worker is compulsory to attend safety induction from the project authorities to ensure
that all worker is aware of site requirement.
iii. Use the proper tool for the job. Worker needs to avoid the first impulse to use whatever tool
(or object) is around you to get a work task done. Using the wrong tool for the job can result
in an injury or damage to the tool which can lead to an injury in the future.
iv. Always wear the proper PPE for the work task. All worker is obligated to ware complete
Personal Protective Equipment (PPE) such as safety helmet, coverall, safety shoes and etc.
v. Working areas must be secured by preventing unauthorized access by using barrier and
signs.
vi. All worker is to make sure chemicals are properly labelled and stored. Improper labelling and
storage can lead to injuries or property loss due to fires, corrosion, etc.
vii. All workers need to stay alert of any potential hazards such as dangerous substance and
confined spaces, so that measures can be developed to eliminate and minimize the risks.
6
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

viii. All the workers must ensure that the working area is cleaned and is in safe condition after the
work is completed.

10.0 FINAL REPORT (types of report)

1) Photo Progress Report

2) Request for Inspection

3)

11.0 APPENDIX (if available i.e. drawing, plan, catalog etc.)


List down the necessary document and attached together with method statement.
1)