Method Statement For Installation of GRE Piping
Method Statement For Installation of GRE Piping
Method Statement For Installation of GRE Piping
PROJECT:
Document No:
Project Code/No:
Client:
Consultant:
Date of Issue:
Status
WCL WCL
Rev. Date
Name: Name: Name: Name:
MichaelNicodemus ……………….. ………………..
Project ……………….. ………………..
Manager
Rev.00 Site Engineer Initial
Sign. Sign. Sign. Sign.
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. DEFINITION
4. REFERENCE DOCUMENT
5. SAFETY
6. RESPONSIBILITIES
9. DOCUMENTATION
10. ATTACHMENTS
1. PURPOSE
The purpose of this method is to implement responsibility for the installation of the
It serves to define the methods and processes to be adopted to ensure all GRE piping
2. SCOPE
This method statement covers the installation, jointing, documentation and safety
measures will be taken for GRE piping systems for fire water pipe spool on whole pipe.
Erection of GRE pipe spool and pressure testing of all piping systems will be conducted
3. DEFINITION
5. SAFETY
SITE SAFETY
All safety procedures as covered by Standard Construction Specification SC-
S-35 will be strictly adhered to.
1) All workers shall wear appropriate personnel protective equipment
while executing the project
2) Electrical cables shall be properly arranged to avoid damage and
possible current leakage.
7. SAFETY PRECAUTIONS
The following safety precautions shall be observed when using GRE products.
No on line work shall be carried out during a pressure test. Leaking joints
shall only be repaired after the pressure has been fully released.
All Safety Precaution shall be kept in accordance with the job hazard analysis
for the GRE piping as attached documents.
8. R E S P O N S I B I L I T I E S
6) Ensures that all installation tasks are carried out as per specification
Design department of Project Control Team. The design department of the project
Isometric piping drawings, As-Built drawings and the compilation of piping test
packages.
Manager
Civil construction manager is responsible for the excavation and back filling
Materials control
End protection of piping components shall remain in place during handling and
transportation. Pipes and fittings shall be handled with care and protected from impact.
Throwing, dropping, bumping or hitting the pipes and the fittings are prohibited. Pipes
shall not be dragged or pushed over sharp objects. Forklift trucks may only be used for
transporting pipes, provided that the forks are padded with carpeting or some other
suitable soft material. Pipe will not rest on the floor of the container where nails, studs
or other, Pipe will not rest on the floor of the container where nails, studs or other sharp
objects might damage it. Pipes shall be laid on wooden sleepers. The pipe should be securely
fastened directly over the timbers with tie downs such as nylon straps or ropes. Steel wire
ropes or others sharp material shall not be used which might cause damage. No other
materials should be loaded on the top of the pipes. Pipe drop or walk or stand on it shall is
Loading
Pipes, fittings and prefabricated spools shall be transported by suitable trucks. These
trucks shall have flat floors. The materials manager shall check for and remove any
Materials shall be secured by using wooden supports. These supports shall have
minimum width of 10cm GRE pipe shall betide in place using soft straps. Chains or steel
The support distances shall not exceed 2.5 m. The width of the supports shall be a
minimum of 10e m . W h e n pipes are inserted one inside the other), the support
Flanges shall be secured against sliding. Flanges shall only be loaded on their sealing
or polyethylene netting.
Pipes and spools shall be lifted by using cloth belts with a minimum 2 times of lifting
weight and shall be lifted at two points, using the largest diameter of the
The truck bottom shall be with wood or thick matting to protect the
G R E pipe from damage. Side loading trucks shall be the preferred type of
vehicle for transportation’s pipes are handled by a forklift truck, the forks shall
Unloading
The unloading of material is the responsibility of the materials control team unless
2) Nylon or cloth hoisting belts with a minimum 2 times of safety load shall be used.
4) Ensure that nylon or cloth hoisting belts are always put round the widest part.
5) Pipes shall be unloaded one at a time when sling belts are used.
6) Each part is carefully loaded and shall be inspected on site in order to ensure that no
For pipe and components supplied with machined parts, the Manufacturer shall apply
external and internal closed end machined parts protectors to protect the ends and all
exposed machined parts of the pipe, coupling and fittings from damage under normal
handling and transportation. For machined parts connections, the end protectors shall
also protect the end face and the outer surface of the bell-end to prevent chipping and
impact damage. Machined parts protectors shall exclude foreign matter such as dirt
from the ends. Protector material shall be plastic and contain no compounds capable of
damaging the machined parts or making the protectors adhere to the machined parts.