NP Corrosion Management Procedure
NP Corrosion Management Procedure
1. Introduction
The North Pars gas field was discovered in 1963. The field is located in Persian Gulf, 120 km south of
Bushehr, about 10 to 15 km from the coast line of the Persian Gulf at the depth of 4000 m (in water
depths of 2-30 m). According to the latest master development studies for the field, the field area is
approximately 500 km2 and the Gas initially in place (GIIP) is estimated to be about 1614 BCM (109
m) or 57 TCF (1012 ft3):
A dry reservoir fluid composition as shown on the following table will be utilized for study. The dry
fluid will be saturated with water at the operating temperature.
Components Mole%
Water 0
N2 1.7
CO2 4.96
H 2S 0.66
C1 89.24
C2 2.28
C3 0.51
iC4 0.12
nC4 0.13
iC5 0.06
nC5 0.04
C6 0.06
C7 0.069
C8 0.029
C9 0.013
C10 0.009
C11 0.007
C12 + 0.117
Component Concentration
(mg/lit)
Sodium & Potassium 95,000 ± 25,000
Parameter Value
The corrosion study will consist of using flow assurance results based on wet sour gas transfer
pipelines from four unmanned platforms with free water separation and waste water treatment. The
sour gas will be transferred by 32” offshore and onshore pipelines to the existing gas plants in Pars
Site area.
Upstream ESDV pig receiver at onshore arrival deck; it corresponds to sealine outlet.
Hydrate and corrosion inhibition are required for transfer pipeline (i.e. MEG injection in offshore with
MEG regeneration and return from intermediate onshore facilities). Following figure shows a simple
representation of one typical platform and the transfer pipeline.
3.6 Assumptions
· Natural reservoir depletion scenarios will be followed per flow assurance study results
· Offshore wellhead platforms (WHP), designed for HP mode only (125 barg) for each phase
30
20
10
-10
Elevation (m)
-20
-30
-40
-50
-60
-70
-80
-10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
Thousands
Distance (m)
NP1 NP2 NP3 NP4
The pipeline has been complexified based on an average profile indicator (PI) of 65. The profile
indicator of 65 has been estimated based on previously laid pipeline for South Pars phases. The next
figure shows the complexified and discredited pipeline profile which is used for the hydraulic analysis.
Subject: North Pars Gas Field Development. Corrosion Study for Offshore and Onshore Pipelines
Scope of Work.
Memo no: OG220701-NRG-NP-MEMO-011-001
Date: May 16th 2023
20
0
Elevation (m)
-20
-40
-60
-80
0 20 40 60 80 100 120 140
Thousands
Distance (m)
The results of the flow assurance reports are (will be) based on the complexified profile.
Subject: North Pars Gas Field Development. Corrosion Study for Offshore and Onshore Pipelines
Scope of Work.
Memo no: OG220701-NRG-NP-MEMO-011-001
Date: May 16th 2023
The following figure shows the liquid hold up and the required pressure for a range of gas flowrates (100 to 1000
MMSCFD) at offshore in winter and summer conditions for an arrival pressure of 81 barg at onshore facilities.
NP # 1 ( 1 x 32in - Multiphase)
30 140
Thousands
28 130
26 120
24 110
22
20
90
18
80
16
70
14
60
12
50
10
8 40
6 30
4 20
2 10
0 0
100 200 300 400 500 600 700 800 900 1,000
As shown on above figure, liquid hold in the pipeline starts increasing drastically for gas production
flowrates below 500 MMSCFD meaning that pipeline will start to enter the unstable zone for
flowrates below 500 MMSCFD. This phenomenon for South Pars pipelines was observed at flowrates
below 200 MMSCFD. The main difference between South Pars and North Pars pipelines is large low
point in the pipeline bathymetry which is prone to collect a lot of liquid at low gas flowrates.
The slug catcher at onshore facilities shall be designed for the largest expected liquid volume during
different operational modes. Most of the time pigging operation results in the largest liquid volume
and is the governing case for slug catcher design. The liquid hold-up in the pipeline is a very good
estimation of the liquid volume that will be generated during pigging. The corresponding hold-up for
500 MMSCFD gas flowrate is roughly 4200 m3. This value would substantially increase (~12500 m 3) if
the pipeline is operated at 300 MMSCFD. Based on the issued production profile at the tail end of
production the gas flowrate will drop to about 300 MMSCFD and hence the slug catcher would need
Subject: North Pars Gas Field Development. Corrosion Study for Offshore and Onshore Pipelines
Scope of Work.
Memo no: OG220701-NRG-NP-MEMO-011-001
Date: May 16th 2023
to accommodate the corresponding pigging liquid volume (liquid hold-up). Designing slug catcher for
such a large volume would require a very large plot space and a big investment.
To avoid having a large slug catcher at onshore, it was recommended to have provisions in place on
each platform to be to comingle the produced gas from different NP platforms in one pipeline to avoid
operating the pipelines below 500 MMSCFD. The recommended provisions are;
Consider extra riser on two the platforms to bring the riser from other two
Design necessary subsea tie-piece and topside valves to comingle the production from two
platforms.
For corrosion study and management, following concept will be assumed to avoid significant liquid
hold up, pigging requirements for MOL.
4. Scope of Work
The scope of work will initially review the results of Document NM-NP-0000-ON-ME-000-
1201-0001-02 North Pars Gas Field Development Corrosion Study for Offshore and Onshore
Pipeline. Corrosion study and material selection and corrosion allowance determination will
be performed by Larkton Ltd. Focus of work is on internal corrosion threats
All viable corrosion threats and mechanisms will be identified and evaluated based on the
provided service data. Assessment will include normal operating conditions as well as
anticipated upset conditions. The internal corrosion rate will be estimated based upon the
operating data provided. Corrosion analysis software will be provided by Larkton - CM.
Larkton are a very experienced and respected integrity Corrosion engineering contractor,
globally renowned and industry leading.
Corrosion mitigation, such as corrosion inhibitor, maintenance pigging will be taken into
account. On the basis of the outcome of the corrosion rate and the design life required the
material selection and corrosion allowance will be determined. The Report will outline the
corrosion management measures that are necessary with the recommended material
Subject: North Pars Gas Field Development. Corrosion Study for Offshore and Onshore Pipelines
Scope of Work.
Memo no: OG220701-NRG-NP-MEMO-011-001
Date: May 16th 2023
selection, and that are realistic for existing facilities, also the recommended corrosion
monitoring regime in line with good practices.
The Report will outline the corrosion management measures that necessary with the
recommended material selection, and that are realistic for existing facilities, also the
recommended corrosion monitoring regime in line with good practices.
As part of the study methodology the scope shall consider the lessons learned from the South
Pars export pipeline issues recently highlighted. Concerns to the life of the pipeline and
subsequently material selection have arisen due to an increase in the level of inerts now being
produced in the gas stream. These are different from initial well test data results as given in
the BOD.
The scope of work will initially compare the current South Pars Corrosion Management
system and assess its adequacy to protect the pipeline through the life of the field based on
the current changes in the production well composition. It is expected that the higher CO2
and H2S levels advised currently will bring material change to the current pipeline Corrosion
Management system. This potential for change shall be taken in to consideration for the
North Pars project.
The scope of work will initially review the results of Document NM-NP-0000-ON-ME-000-
1201-0001-02 North Pars Gas Field Development Corrosion Study for Offshore and Onshore
Pipeline. A Corrosion Management Philosophy will be produced to adequately protect the
export pipeline through the life of the field based.
· Corrosion study
· Material selection
· Corrosion allowance definition
· Corrosion Inhibitor fluids and philosophy on injection rates.
· Establish pigging philosophy, establish adequacy of CI cover to internal wall of
pipeline.
Subject: North Pars Gas Field Development. Corrosion Study for Offshore and Onshore Pipelines
Scope of Work.
Memo no: OG220701-NRG-NP-MEMO-011-001
Date: May 16th 2023
The final outcome will be a Corrosion Management Philosophy that can be used to support
the current BOD and operating procedures as necessary.
Data collection,
Corrosion Management Philosophy.
Corrosion Management Philosophy.
Issue of philosophy documents.