Project Scheduling II
Project Scheduling II
Management
Project Scheduling
PDM & PERT
Samantha Manawadu
1.0 Precedence Diagramme
• A Precedence Diagramming Method (PDM) is a graphical representation
technique. It shows the inter-dependencies of activities and is used in
schedule development. The other name for this technique is Activity on
Node (AON).
• PDM is more flexible than AON or AOA networks because PDM allows the
overlapping of concurrent activities. Additionally, almost all
commercially available microcomputer-based project management
systems are based on PDM.
Precedence Diagrammes
Precedence
1. Mandatory Dependency
are those that are inherent in the nature of the work being
done. They are involved physical limitations and are also called
hard logic
Ex: on a construction project, it is impossible to erect
superstructure until after the foundation has been built.
Type of Dependencies in PDM
2. Discretionary Dependency
Ex. you can construct the four walls in any sequence. However, if
constructing them in a certain sequence is beneficial you build
them in that order.
Here, you can change the sequence of activities as per your preferred
logic.
Type of Dependencies in PDM
3. External Dependency
4. Internal Dependency
These are dependencies are within the control of your project
or organization.
Ex. you cannot get a resource until it is free from another
project.
Dependency (Activity) Relationships
Finish-to-start- Most common. The earliest the next activity can begin
is when a certain activity is completed.
Ex. In this case, the first activity (A) is Plastering wall and the second
activity (B) is painting. You cannot start painting the wall until the
Plastering wall is finished
Dependency (Activity) Relationships
Start-to-start- Is used to show how the start of one activity triggers the
start of a successor activity.
• Suppose you have to apply a coating on a wall, but the wall must be
cleaned in order to apply it.
• Therefore, one team will clean the wall and second team will coat it.
Both activities can start simultaneously.
Dependency (Activity) Relationships
Finish-to-finish- Necessary for the initial activity to remain ahead of its
successor activity. Completion is contingent upon completion of its
predecessor.
For example, let us say you are moving into a new home and your old home
has to be demolished. In this case, you cannot move into your new home until
it is ready. Hence, the second activity (construction of the new home) must
be finished before the first activity starts (moving into a new home).
Dependency (Activity) Relationships
Graphical presentation of Precedence
Node
PDM Example
2.0 Programme Evaluation and Review
Technique ( PERT)
• The Project Evaluation and Review Technique, commonly abbreviated
PERT, is a statistical tool, used in project management. It was developed
for the U.S. Navy Special Projects Office in 1957 to support the U.S.
Navy's Polaris nuclear submarine project. An early example was, it was
used for the 1968 Winter Olympics in Grenoble, France.
• Most likely or modal time (Tm); the time required if the activity is
repeated a number of times under essentially the same conditions.
2
p o
σ 2
6
1 A,B,D,E,G,H,J,k 4.82
2 A,B,D,E,G,I,J,K 4.96
3 A,C,F,G,H,J,K 2.24
4 A,C,F,G,I,J,K 2.38
Calculating the Probability of Completing the Project
in Less Than a Specified Time
• When you know:
• The expected completion time
• Its variance
• You can calculate the probability of completing the project in “X” weeks
with the following formula: