Exercise3 Solution

The document discusses four tasks related to aperiodic scheduling algorithms. Task 1 examines Earliest Deadline Due scheduling for a given task set. Task 2 examines Latest Deadline First scheduling with precedence constraints. Task 3 examines Earliest Deadline First scheduling with arrival times and deadlines, and analyzes adding a new task. Task 4 examines Earliest Deadline First scheduling for a task set with precedence constraints.

Uploaded by

aditya jindal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
179 views9 pages

Exercise3 Solution

The document discusses four tasks related to aperiodic scheduling algorithms. Task 1 examines Earliest Deadline Due scheduling for a given task set. Task 2 examines Latest Deadline First scheduling with precedence constraints. Task 3 examines Earliest Deadline First scheduling with arrival times and deadlines, and analyzes adding a new task. Task 4 examines Earliest Deadline First scheduling for a task set with precedence constraints.

Uploaded by

aditya jindal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

Institut für

Technische Informatik und


Kommunikationsnetze

Prof. Lothar Thiele

Embedded Systems - HS 2020

Sample solution to Exercise 3


Date : 4./6.11.2020

Aperiodic Scheduling

Task 1: Earliest Deadline Due


Check whether the Earliest Deadline Due (EDD) algorithm produces a feasible schedule for the following
task set, given that all tasks are synchronous and arrive at time t = 0.

J1 J2 J3 J4
Ci 3 6 2 4
Di 8 15 3 11

Solution for Task 1:

EDD (Earliest Deadline Due) is a scheduling algorithm that minimizes the maximum lateness. The
Jackson’s rule says that given a set of n independent tasks, any algorithm that executes the tasks in
order of non-decreasing deadlines is optimal with respect to minimizing the maximum lateness.
Assumptions about the task set for applying EDD:
- tasks have same arrival times (synchronous arrivals)
- tasks are independent
EDD is non-preemptive. The EDD produces a feasible schedule given in Figure 1.
5

0
0 2 4 6 8 10 12 14 16 18 20

Figure 1: EDD schedule.

The tasks are scheduled in the order of non-decreasing deadlines as follows: J3 , J1 , J4 , J2 .

1
Task 2: Latest Deadline First
Given the precedence graph in Figure 2 and the following table of task execution times and deadlines,
determine a Latest Deadline First (LDF) schedule. Is this schedule feasible?

J1 J2 J3 J4 J5 J6 J7 J8
Ci 3 4 2 3 3 2 2 1
Di 5 8 11 15 12 18 19 20

J5

J1 J2 J4 J6 J7

J3 J8

Figure 2: Precedence graph.

Solution for Task 2:

LDF (Latest Deadline First) is a scheduling algorithm that minimizes the maximum lateness. It assumes
synchronous task activations and is non-preemptive.
The algorithm to produce an LDF schedule proceeds in two stages: firstly, a precedence graph is con-
structed. Going from tail to head: among the tasks without successors or whose successors have been
all selected, LDF selects the tasks with the latest deadline to be scheduled last. At runtime, tasks are
extracted from the head of the queue: the first task inserted in the queue will be executed last.
The queue of tasks scheduled with LDF is as follows: J1 − J2 − J3 − J5 − J4 − J6 − J7 − J8 . The LDF
schedule is presented in Figure 3. On Figure 4 you can find a sketch of how the LDF algorithm proceeds.

Figure 3: LDF schedule.

2
J5
J5

J1 J2 J4 J6 J8
J1 J2 J4 J6 J8

J3 J7
J3 J7

J5
J5

J1 J2 J4 J6 J8
J1 J2 J4 J6 J8

J3 J7
J3 J7

J5 J5

J1 J2 J4 J6 J8 J1 J2 J4 J6 J8

J3 J7 J3 J7

J5

J1 J2 J4 J6 J8

J3 J7

Figure 4: The LDF algorithm proceeds as depicted (figures left to right)

3
Task 3: Earliest Deadline First
In the following table, five tasks with arrival times, execution times and deadlines are given.

J1 J2 J3 J4 J5
ai 0 2 0 8 13
Ci 3 1 6 2 3
di 16 7 8 11 18

(1) Determine a Earliest Deadline First (EDF) schedule. Is this schedule feasible?

(2) At time t = 3, a new task Jx arrives with execution time Cx = 2 and deadline dx = 10. Can you
guarantee the schedulability of the task set with this new task?

Solution for Task 3:

EDF (Earliest Deadline First) is optimal in the sense of feasibility (it minimizes the maximum lateness
under following assumptions: scheduling algorithm is preemptive, the tasks are independent, and may
have arbitrary arrival times). The Horn’s rule says that given a set of n independent tasks with arbitrary
arrival times any algorithm that at any instant executes the task with earliest absolute deadlines among
the ready tasks is optimal with respect to the maximum lateness.

(1) The EDF schedule is feasible, and the respective schedule is shown in the Figure 5.

J5

J4

J3

J2

J1

0 2 4 6 8 10 12 14 16 18 20

Figure 5: EDF schedule

(2) The arrival of a new task Jx at time point t = 3 still maintains the schedule feasible. We can
check this by computing ahead the finishing times of the tasks (with respect to the interesting
time points). In the analysis, we consider the tasks in order of increasing deadlines.
We assume an on-line scenario, i.e. in the schedulability test we consider only tasks currently present
in the system. The test is performed every time a new task arrives.
From the schedule in the preceding sub-problem, we know that before task JX arrives at time t = 3
we have:
- tasks J1 , J2 and J3 are feasible
- task J2 finishes before its deadline at t = 3
That is, up to t = 3 all active tasks in the system are feasible.
At t = 3 we have three tasks in the system: J1 , J3 and the new task, Jx . For them we perform
the schedulability test:

Put f0 = t = 3 (We have absolute deadlines in the problem specification)


Task J3 : f1 = f0 + c3 (3) = 3 + 4 = 7 ≤ 8 (ok)

4
Task Jx : f2 = f1 + cx (3) = 7 + 2 = 9 ≤ 10 (ok)
Task J1 : f3 = f2 + c1 (3) = 9 + 3 = 12 ≤ 16 (ok)
Thus, at t = 3 all tasks in the system are feasible.
The next task to arrive is J4 . It arrives at t = 8. At t = 8, we have thee active tasks: Jx , J4 and
J1 . The schedulability test at t = 8 proceeds as follows:
Put f0 = t = 8
Task Jx : f1 = f0 + cx (8) = 8 + 1 = 9 ≤ 10 (ok)
Task J4 : f2 = f1 + c4 (8) = 9 + 2 = 11 ≤ 11 (ok)
Task J1 : f3 = f2 + c1 (8) = 11 + 3 = 14 ≤ 16 (ok)
Thus, at t = 8 all tasks in the system are feasible.
Finally, task J5 arrives at t = 13. At t = 13, we have two active tasks: J1 and J5 . The schedulability
test at t = 13 proceeds as follows:
Put f0 = t = 13
Task J1 : f1 = f0 + c1 (13) = 13 + 1 = 14 ≤ 16 (ok)
Task J5 : f2 = f1 + c5 (13) = 14 + 3 = 17 ≤ 18 (ok)
Hence, the whole schedule is feasible. It is given in the figure below:

Jx

J5

J4

J3

J2

J1

0 2 4 6 8 10 12 14 16 18 20

Figure 6: EDF schedule (with Jx )

Task 4: Earliest Deadline First – Star


Given are seven tasks A, B, C, D, E, F, G with following precedence constraints:

A −→ C, B −→ C, C −→ E, D −→ F, B −→ D, C −→ F, D −→ G

All tasks arrive at time t0 = 0, have a common deadline d = 20 and the following execution times:

A B C D E F G
Ci 3 2 4 3 2 5 1

(1) Construct the precedence graph for this task set. Then, modify the release times and deadlines so
that EDF∗ can be used for its scheduling.

(2) Determine a resulting EDF∗ schedule. For this schedule, compute the average of all response times
of the tasks.
(3) Assume the additional precedence constraint E −→ A. Is there still a feasible schedule for the
above task set? Justify your answer.

5
Solution for Task 4:

EDF∗ schedules tasks with precedence constraints. Release time and deadline of individual tasks are
modified such that all the precedence constraints are satisfied. By doing this, the scheduling problem is
transformed into a problem without precedence constraints, which can then be handled by a "normal"
EDF scheduler.
There are several points to take into consideration while modifying tasks’ release times and deadlines:
Release time modification:
- task must start the execution not earlier than its release time
- task must start the execution not earlier than the minimum finishing time of its predecessors
Deadline modification:
- task must finish within its deadline
- task must finish not later than the maximum start time of its successors

(1) The precedence graph for the given task set is:

A C

B D

The modified release times and deadlines are:


A B C D E F G
ri∗ 0 0 3 2 7 7 5
d∗i 11 11 15 15 20 20 20

In particular, the release time modification proceeds as follows:


∗ = r , r∗ = r
for initial nodes {A, B} set rA A B B
rC∗ = max{r , max{r ∗ + C , r ∗ + C } = max{0, max{3, 2}} = 3
c A A B B
rD∗ = max{r , r ∗ + C } = max{0, 0 + 2} = 2
D B B
rF∗ = max{rF , rC ∗ + C , r ∗ + C } = max{0, 3 + 4, 2 + 3} = 7
C D D
rE∗ = max{r , r ∗ + C } = max 0, 3 + 4 = 7
E C C
rG∗ = max{r , r ∗ + C } = max 0, 2 + 3 = 5
G D D
The deadline modification proceeds as follows:
for the terminal nodes {E, F, G} set d∗E = d∗F = d∗G = 20
d∗C = min{dC , d∗E − CE , d∗F − CF } = min{20, 20 − 2, 20 − 5} = 15
d∗D = 15
d∗A = 11
d∗B = 11
(2) One resulting EDF∗ schedule, based on the modified release times and deadlines, is presented
below.
The response time of a task is defined as the difference between its finishing time and release time.
Therefore, the average of all response times for the above schedule is computed as follows:
7
1X 5 + 2 + 12 + 8 + 20 + 18 + 13
tr = (fi − ri ) = = 11.14
7 i=1 7

6
JG

JF

JE

JD

JC

JB

JA

0 2 4 6 8 10 12 14 16 18 20

Figure 7: EDF∗ schedule

Note that for the computation of a task’s response time we consider its original (not modified)
release time. Note also that there are different correct schedules, and the corresponding response
times may be different.
(3) No, the task set is no longer schedulable. Under the new conditions, the constraints among tasks
A, C and E introduce a cycle in the precedence graph. As a result, none of the three tasks can be
executed as first and therefore, no feasible schedule exists.

Task 5: Earliest Deadline First – Star


Given are eight aperiodic tasks, J1 to J8 , with their arrival times, deadlines, and execution times as
shown in the table below. Task precedence constraints are as follows:

J1 → J2 , J2 → J3 , J3 → J4 , J5 → J6 , J6 → J7 , J6 → J8 , J2 → J7 , J7 → J4 , J8 → J7 .

J1 J2 J3 J4 J5 J6 J7 J8
ri 0 3 4 0 0 2 0 2
di 3 8 15 15 10 10 10 11
Ci 1 3 3 3 1 1 2 1

(1) Construct the precedence graph.


(2) Using the EDF∗ algorithm, modify the arrival times and deadlines of the tasks in order to make
the tasks schedulable under EDF. Enter the modified arrival times and deadlines in Table 1.
Table 1: Modified arrival times and deadlines

J1 J2 J3 J4 J5 J6 J7 J8
ri∗
d∗i
Ci 1 3 3 3 1 1 2 1

(3) Assume that the application is executed on a dual-core platform. At any time t, both cores execute
the two ready tasks (ri∗ ≤ t) with earliest deadlines (Note: A single task cannot be executed on
two cores simultaneously). Using the arrival times and deadlines obtained in (2), construct an EDF
schedule in Figure 8.

7
Core 1

Core 0

0 1 2 3 4 5 6 7 8 9 10 11 12
time

Figure 8: EDF schedule for part (3)

(4) Now assume that the application is executed on a quad-core platform with the same scheduling
rule (4 cores execute the four ready tasks with earliest deadlines). Will executing on the quad-core
platform reduce the completion time of the application? Justify your answer with an explanation.

Solution for Task 5:

(1) The precedence graph:

J1 J5

J2 J6

J8

J3 J7

J4

(2) The modified arrival times and deadlines:

J1 J2 J3 J4 J5 J6 J7 J8
ri∗ 0 3 6 9 0 2 6 3
d∗i 3 8 12 15 6 7 10 8
Ci 1 3 3 3 1 1 2 1

(3) There are several solutions since the tasks can run either on core 0 or core 1, and one can be seen
in Figure 9. Makespan of all solutions should be 12.

(4) No. J4 cannot be started earlier than time 9. Therefore, the minimum finish time of the application
is 12 (the finish time for the dual core platform).

8
J5 J8 J3 J4 Core 1

J1 J6 J2 J7 Core 0

0 1 2 3 4 5 6 7 8 9 10 11 12
time

Figure 9: One solution for part (3)