Method Statement Waterproofing

The document provides a method statement for cementitious waterproofing of wet areas. It outlines the purpose, scope, responsibilities, materials, logistics, health and safety, execution steps, and attachments for the waterproofing work. The execution section describes surface preparation, mixing, application of two coating layers, curing, integrity testing, and protection layer installation.

Uploaded by

Kanul Riyaz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views6 pages

Method Statement Waterproofing

The document provides a method statement for cementitious waterproofing of wet areas. It outlines the purpose, scope, responsibilities, materials, logistics, health and safety, execution steps, and attachments for the waterproofing work. The execution section describes surface preparation, mixing, application of two coating layers, curing, integrity testing, and protection layer installation.

Uploaded by

Kanul Riyaz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

METHOD STATEMENT for CEMENTITIOUS WATER PROOFING

Owner

Owner’s Engineer

Project Title

LPG Tank Maintenance

Space for stamping

FOR APPROVAL
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A For Approval

Description Current Revision


Cross Checked
Department Name Date Signature

Contractors

Replaces Derived from Project Document Code


- -
Responsible dept. Created by Checked by Approved by Format
Construction A4
Originator Document Type Document Status
Method Statement FOR APPROVAL
Title, Subtitle : METHOD Originator Document No.
STATEMENT for CEMENTITIOUS
WATER PROOFING
Rev. Date Lang. Sheet
A En -7
Contents

1. PURPOSE

2. SCOPE

3. DEFINITIONS

4. REFERENCES

5. RESPONSIBILITIES

6. TOOLS AND EQUIPMENTS

7. MATERIALS

8. LOGISTICS

9. HEALTH AND SAFETY

10. EXECUTION

11. ATTACHMENTS
1. PURPOSE :

The purpose of this Method Statement is to outline the detailed procedure to be followed during the
application of Cementitious Waterproofing Coating of Wet Areas.

2. SCOPE :

The purpose of this method statement is to describe the procedures, sequence and responsibilities
for the installation of cementitious waterproofing coating, system is executed as per project
specification and safety requirements throughout the progress of works.

3. DEFINITIONS :

Employer : OAKS Hotels


Main Contractor : Brothers Gas
UNEC Authority / Jurisdiction : Dubai Development Authority (DDA)
MST : Method Statement
ITP : Inspection and Test Plan
RA : Risk assessment

4. REFERENCES
Volume 3.1 Employer’s Requirement Dubai Development Authority (DDA) rules and regulations
Project Safety and Quality plan Project Specification Approved Materials submittals

5. RESPONSIBILITIES :

a) ARK Site Engineer will organize the manpower, materials, plant and equipment needed for the paint
works as per Main Contractor’s Programme.
b) ARK Site Engineer will hold daily tool box talks for the coating workers.
c) ARK Site Engineer will ensure that all safety measures are implemented as per the Main
Contractor’s Safety Procedures.
d) Inspection Requests and Check Lists will be initiated by the ARK Site Engineer and will be Handed
Over to Main Contractor’s QC Engineer.
e) Floor coating will be directly supervised by ARK Foreman.
f) Main Contractor’s QC Engineer will conduct the Inspections and Request Consultants for Inspection
and Approval.
g) MEP Coordinator will arrange the MEP Clearance Inspections prior to coating where required.
6. TOOLS AND EQUIPMENTS :

a) Scale
b) Cement bucket
c) Mixing machine
d) Hammer
e) Steel brush
f) Paint brush
g) Notch trowel

7. MATERIALS

a) As per Approved Material Submittals

"SikaSeal 105" from Sika or "MasterSeal 550" from BASF or "Planiseal 288" from Mapei, Two-
component modified cementitious waterproof coating, 2mm thick.

8. LOGISTICS:

A. Access / Egress

a) All products have a shelf life of 12 months if stored in cool, dry store, away from sources of heat, in
the original unopened packing. It should be stored horizontally, not more than one pallet high.
b) Do not puncture, cut, drill, heat or weld uncleaned drums. Store in original containers. Storage one
common facility, keep ignition sources away _ Do not smoke. Use only in explosion protected area.
c) Follow the project safety procedures and regulations while leading and off-loading the material at
the job site.
d) All materials should be inspected by QC prior released from store and to be used at site.

B. Traffic Management

a) Refer to updated logistics plan to determine the suitable access. Any change to this access roads are
provided with directional signs.
b) UNEC will provide traffic aides/ flagmen around the site as required to ensure that flow of traffic is
controlled.
c) All workers and operators shall be inducted on the HSE rules and regulation of the project. E.g.
speed limit, HSE regular equipment inspection, PPE, etc.

9. HEALTH AND SAFETY

All the safety measures are covered separately in the project HSE plan. However, a specific Risk
Assessment (RA) is attached to this submittal to cover all identified risks of this activity
10. EXECUTION :

A. GENERAL

• The Preparation and application procedure should be in strict accordance with the content of this
method statement and approved waterproofing shop drawing details.

B. SURFACE PREPARATION

• Prior to the cementitious installation all the unauthorized individuals must be prevented from
having access to the work site Pre-wet evenly the surface
• Before any commencement of waterproofing works, surfaces will be examined by IKK, in order to
ensure that there are no conditions which could adversely affect the performance of the
Waterproofing System.
• The receiving surface should be dry, clean, sound, smooth, free of loose particles and sharp edges,
oil and grease, detrimental to the membrane.
• If any irregularities to the surface are noticed, the surfaces must be repaired before any membrane
application. If using a formwork, only light grinding will be required on the overall surface; most of the
grinding works will be focused on formwork panel joints and/or tie rods holes. Otherwise, any uneven
surface receiving membrane will have to be plastered.
• The surface must be mechanically prepared by means of concrete grinder or high pressure water
jetting, to achieve a rough surface in order to allow a mechanical key and to improve the adhesion of
the coating to the substrate as per manufacturer recommendation.
• Saturate absorbent surfaces thoroughly. The surface should be in saturated surface dry condition
prior to the application.

C. Mixing:

• Stir the liquid then pour into mixing vessel. Slowly add the powder while mixing with a low speed
drill, by controlling the amount of powder, the consistency can be adjusted, depending on the
application type. Mix for at least 3 minutes, until a homogenous mixture, free from lumps is achieved.
Do not add water under any circumstances. D. Coating Application:
• Apply first coat of "SikaSeal 105" or "MasterSeal 550" or "Planiseal 288" cementitious waterproofing
in the same direction using stiff brush.
• Let the first coat dry (as per data sheet) proceeding with the second coat.
• Slightly pre-wet the first coat in case of longer waiting times. Then brush on the second coat in
crosswise direction to the first coat, to reach a total average thickness of 2mm. E. Pipe penetration
treatment:
• Ensure all pipes are clean, dry and free of all rust, oils, grease or other deleterious coatings.
• Apply a mortar cantsrip around the pipe, then the cementitious coating will be applied over it and
extended over the pipe in two coats. F. Curing:
• Once fully cured proceed to water test. G. Integrity Test:
• Seal all drains and water discharge outlets prior to water test.
• Perform water test by flooding the completed areas with 2” minimum water head level for a period
of 48 hours without any interruption. H. Prevision of Repair Works in Case of Water Leakage
• Clean the damaged area and remove any dust and other small particles around the affected area.
• Re-apply "SikaSeal 105" or "MasterSeal 550" or "Planiseal 288" to correct deficiencies as per
manufacturer recommendation and allow curing time. I. Installation of Protection Layer:
• Depending on bonded or un-bonded screed requirements, a protecting layer of polyethylene sheet
1000 gauge including protection screed shall be applied over the waterproofing layer.

11. ATTACHMENTS
Inspection and Test plan Checklist
Risk Assessment CONSTRUCTION PLAN