DAILY PROGRESS REPORT

DATED: 11.04.2024
ATHENA VEDANTA LIMITED
2X600 MW POWER PLANT, SAKTI (C.G)

APRIL 2024 MONTH MILESTONES

1 HP and both LP Turbine dismantling and condition assessment (UNIT #1)

2 Both TDBFP erection (UNIT #1)

3 400kV switchyard DC system commissioning

MANPOWER MOBILIZATION
PLANNED BY PLANNED BY
CONTRACTOR ACTUAL BY 11.04.24 REMARKS
10.04.24 15.04.24
POWERMECH PROJECTS LTD 81 gate pass & medical under process, 378 gate
378 481 715
(MECHANICAL) pass done

POWERMECH PROJECTS LTD 31 gate pass & medical under process, 90 gate
60 91 135
(ELECTRICAL) pass done

130 gatepass done,4 gate pass & medical under


MACAWBER BEEKAY LTD 110 125 160
process

GRAND TOTAL 548 697 1010

ACTIVITIES AT SITE
MANPOWER
CONTRACTOR ACTIVITY START DATE END DATE REMARKS
ENGAGED

Paradeep Port Material shifting to site


J M BAXI 18-Feb-24 May-24 10 182 trailers unloaded
(approx. 4390 tons out of 9894 tons)

POWERMECH PROJECTS LTD TG BUILDING 7

All breaker buffers were


HT switchgear readiness 02-Apr-24 10-Apr-24 0 changed.Panels testing to be
done.
ESS Panels cleaning and
tightness done.Circuit breaker
ELECTRICAL LT switchgear readiness 09-Apr-24 15-Apr-24 7 testing completed.CT and VT
testing under progress.CRM
testing completed.
Battery charger(1/2) overhauling
U#1 Battery Charger overhauling &
02-Apr-24 0 completed.DCDB relay testing
maintenance
under process.

POWERMECH PROJECTS LTD SWITCHYARD 7

Readiness of ACDB 21-Mar-24 29-Mar-24 ACDB charged through


construction power.

Charging of Lighting transformer and MLDB 27-Mar-24 30-Mar-24 Lighting transformer and MLDB
charged.
(6/6)Bay marshalling kiosk are
Charging of Bay marshalling kiosk 01-Apr-24 05-Apr-24
charged.
(4/6)bays overhauling
Readiness of circuit breaker 06-Apr-24 28-Apr-24 3 completed.overhauling of balance
2bays is under progress

(52/80)testing and condition


Readiness of earth pit 02-Apr-24 28-Apr-24 0 assessment completed.Balance to
be completed by 28-04-2024.

ELECTRICAL PDB inspection, cleaning & rectification 01-Apr-24 03-Apr-24 0 PDB panel charged.

48V battery charger 1&2 are


ready and battery charger-2 is
charged.DCDB of 48V
48V DC system 04-Apr-24 25-Apr-24 1
charged.Overhauling of 48V
battery bank-2 completed and
charging is under progress.
220V battery charger 1&2 are
ready.DCDB of 220V is ready for
220V DC system 04-Apr-24 25-Apr-24 2
charging.Ovehauling of 220V
battery bank is under progress.

Switchyard Area cleaning 03-Apr-24 30-Apr-24 1 under progress

POWERMECH PROJECTS LTD BOILER AREA 8

Light-200ns are installed and in


working condition.Lighting done
ELECTRICAL Boiler Area Light Fittng and Installation 02-Apr-24 18-Apr-24 8
upto 33mtr.

POWERMECH PROJECTS LTD BOP AREA 6

Dismantling
ELECTRICAL Cooling tower Dry type transformer
10-Apr-24 15-Apr-24 6 completed.Transportation
dismantelling
arrangement is under progress.

POWERMECH PROJECTS LTD POWER TRANSFORMER 6

GT#1 Inspection, condition assessment 02-Apr-24 15-Apr-24 2


under progress
ELECTRICAL UAT Inspection,condition assessment 08-Apr-24 16-Apr-24 4
under progress

Housekeeping in Trafo yard 02-Apr-24 10-Apr-24 0


Completed

POWERMECH PROJECTS LTD TG BUILDING 73

LP Turbine -1&2 dismantling work 09-04-2024 20-04-2024 10


under progress

EOT-1 Load test 03-Apr-24 06-Apr-24 completed

TDBFP A&B Blue Matching 04-Apr-24 15-Apr-24 10

House Keeping in all areas 29-Mar-24 continuous 12

Hard Barrication Work Under Progress In


27-Mar-24 15-Apr-24 10 safety points
TG 07 Mtr. Area.
Hard Barrication Work Under Progress In
29-Mar-24 15-Apr-24 9 safety points
TG 13 Mtr. Area.
Turbine & Auxiliaries Cleaning Under
MECHANICAL 19-Mar-24 continuous 8
Progress
Scaffolding Arrangement For Cold
28-Mar-24 12-Apr-24 completed
Secondary Duct
Vertigo Test Structure Fabrication
29-Mar-24 10-Apr-24 completed
completed
Valves fitup, dismantling For Auxiliary
Steam Header Line At TG 7 Mtr. For 8 29-Mar-24 continuous 6
nozzles

Lube oil piping small boure fitup under


11-Apr-24 20-Apr-24 8
progress

Scaffolding Arrangement Under Progress


29-Mar-24 12-Apr-24 Completed
For Auxiliary Steam Header Line

POWERMECH PROJECTS LTD BOILER AREA 40

70% of work completed and


Welding of Toe Guard from 8 mtr to 13 mtr 04-Apr-24 13-Apr-24 6
balance is under progress.

Welding of Toe Guard from 13mtr to 27 mtr 13-Apr-24 17-Apr-24 0 work started.

Scaffolding work and Cleaning is


FD fan diffusor dismantling work 10-Apr-24 15-Apr-24 6
started

MILL A,B,C Classifier body door opening


11-Apr-24 13-Apr-24 4 Door opening done
completed for inspection
MECHANICAL
MECHANICAL Coal piping beam shifted from yard to site
for bed preperation to start coal piping 11-Apr-24 11-Apr-24 4 bed rediness is started
assembly

Duct welding and scaffolding work of cold duct welding work,Fit-up and
03-Apr-24 16-Apr-24 8
secondary duct scaffolding work under progress

winch fixing done electrical


Winch installation 10-Apr-24 13-Apr-24 8
connection under progress

ESP Pass A - A1 & A2 Field door opening


Field Level 04 nos door open and
for inspection & inspection under progress
11-Apr-24 20-Apr-24 4 lighting fixing work is under
in field A1.
progress

POWERMECH PROJECTS LTD BTG YARD AREA 26

Material Segregation & Structure Material


20-Mar-24 continuous 12
Shifted From Yard

MECHANICAL Btg Yard Area devegetation under


20-Mar-24 10-Apr-24 5
progress.
Devegetation Under Progress In Boiler
20-Mar-24 10-Apr-24 9
Area And Sunil Hitech Yard

POWERMECH PROJECTS LTD DM PLANT AREA

MECHANICAL Dm Plant House Keeping completed 20-Mar-24 10-Apr-24


completed

POWERMECH PROJECTS LTD DM PLANT AREA 4

C&I DM plant PLC testing is under progress 12-Apr-24 15-Apr-24 4

POWERMECH PROJECTS LTD IDCT AND CW PUMPHOUSE 22

Cooling tower -1 scaffolding preparation for


03-Apr-24 30-Apr-24 7
3 fields out of 22 fields

Cooling Tower -1 Dewatering completed 22-Mar-24 10-Apr-24


completed

Cooling Tower-1 Area cleaning 03-Apr-24 12-Apr-24 1

MECHANICAL Cooling Tower-1 basin cleaning 09-Apr-24 15-Apr-24 5


under progress
Inspection completed.gears are
CW Pumphouse gantry crane inspection & found in damaged condition and
02-Apr-24 13-Apr-24 7
overhauling they need to be taken out for
condition assesment.
CW Pumphouse Dewatering Under Water inside CW duct removal
29-Mar-24 2
Progress with 02 No Hp Pump under progress.

POWERMECH PROJECTS LTD STORE & OFFICE WORK 16

PMPL Container Offices revamping 18-Mar-24 15-Apr-24 8

MECHANICAL Abir Staff Office Housekeeping Work


18-Mar-24 continuous 4
Under Progress.
PMPL Store Area Housekeeping Work
18-Mar-24 continuous 4
Under Progress.

AHP 51

Vaccume pump motor-6nos and


vaccume pump-3nos cleaning
Bottom Boiler Vacuum Pump Motor completed.Vaccume pump-3nos
04-Apr-24 14-Apr-24 9
Overhauling cleaning is under progress

100 kw motor-6nos freeness


Inspection and assessment of motor at done,blower-4nos freeness done,
11-Apr-24 15-Apr-24 6 20kw motor-5nos freeness done.
recyclic pump house

Motor inspection work in BA slurry pump All motors(20nos) physical


06-Apr-24 12-Apr-24
house inspection done.

Devegatation and housekeeping 22-Mar-24 continuous 13

Material shifting and house keeping work in


24-Mar-24 22-Apr-24 7
AHP store yard
Stacking and sorting of material at AHP
15-Mar-24 14-Apr-24 12 under progress
store yard
Power cable,glanding dressing
Cable laying work from SS-6 to AHP store done.Old construction power
10-Apr-24 17-Apr-24 4
yard cable cutting,dismantling and
shifting done

CHP 48

Available idlers are fixed.Structure


Crusher house 4A/4B conveyor Idler cleaning under progress and
06-Apr-24 10-Apr-24
MACAWBER BEEKAY LTD shifting and fixing same shall be completed by 15-04-
2024.

Crusher 1,2,3,4 gear coupling


inspection done and crusher rotor
freeness is under
Ring granuator crusher overhauling work at progress.Crusher 1,2,3,4
09-Apr-24 13-Apr-24 13
CHP crusher house inspection door opening and
cleaning going on.Physical
inspectionof all crushers shall be
completed by 13-04-2024.

14nos spare pulley DE&NDE side


bearing and plumber block
CHP storage yard 11-Apr-24 12-Apr-24 10 removing work done and 4nos
head pulley NDE side bearing and
plumber block removing done.

Dewatering work is carrying out


Dewatering in Wagon tippler,truck Hopper, with sump-2nos at wagon tippler
24-Mar-24 26-Apr-24 1
TP#1 and track hopper.Sump pump-1no
fixing at TP#2 is under progress

Electrical lighting rectification 22-Mar-24 continuous 3

Cable laying and fixing from DB to TP-2 11-Apr-24 11-Apr-24 4 Cable laying done

Material shifitng and house keeping work in


24-Mar-24 15-Apr-24 17 under progress
CHP

LP Turbine work

Ducting area welding under progress Battery overhauling in progress Electrical panel checking work
DM plant PLC Power on
AHP vaccume pump overhauling Pulley Removal work in CHP