DPR - 11 04 2024
DPR - 11 04 2024
DPR - 11 04 2024
DATED: 11.04.2024
ATHENA VEDANTA LIMITED
2X600 MW POWER PLANT, SAKTI (C.G)
MANPOWER MOBILIZATION
PLANNED BY PLANNED BY
CONTRACTOR ACTUAL BY 11.04.24 REMARKS
10.04.24 15.04.24
POWERMECH PROJECTS LTD 81 gate pass & medical under process, 378 gate
378 481 715
(MECHANICAL) pass done
POWERMECH PROJECTS LTD 31 gate pass & medical under process, 90 gate
60 91 135
(ELECTRICAL) pass done
ACTIVITIES AT SITE
MANPOWER
CONTRACTOR ACTIVITY START DATE END DATE REMARKS
ENGAGED
Charging of Lighting transformer and MLDB 27-Mar-24 30-Mar-24 Lighting transformer and MLDB
charged.
(6/6)Bay marshalling kiosk are
Charging of Bay marshalling kiosk 01-Apr-24 05-Apr-24
charged.
(4/6)bays overhauling
Readiness of circuit breaker 06-Apr-24 28-Apr-24 3 completed.overhauling of balance
2bays is under progress
ELECTRICAL PDB inspection, cleaning & rectification 01-Apr-24 03-Apr-24 0 PDB panel charged.
Dismantling
ELECTRICAL Cooling tower Dry type transformer
10-Apr-24 15-Apr-24 6 completed.Transportation
dismantelling
arrangement is under progress.
Welding of Toe Guard from 13mtr to 27 mtr 13-Apr-24 17-Apr-24 0 work started.
Duct welding and scaffolding work of cold duct welding work,Fit-up and
03-Apr-24 16-Apr-24 8
secondary duct scaffolding work under progress
AHP 51
CHP 48
Cable laying and fixing from DB to TP-2 11-Apr-24 11-Apr-24 4 Cable laying done
LP Turbine work
Ducting area welding under progress Battery overhauling in progress Electrical panel checking work
DM plant PLC Power on
AHP vaccume pump overhauling Pulley Removal work in CHP