Drive 5 PMP Questions and Answers
Drive 5 PMP Questions and Answers
A manager and the head of engineering discuss a change to a major work package. After the meeting, the
manager contacts you and tells you to complete the paperwork to make the change. This is an example of:
A-) Management attention to scope management. B-) Management planning. C-) A project expediter position.
D-) A change control system.
The answer is C. In this situation, the project manager acts as the secretary of the project and does the
paperwork. So this is an example of a project expediter position where the project manager does not have any
authority and power. The project manager only does paperwork.