This document describes the method of procedure for integrating a new eNodeB
into TZ Tigo LTE network. Activities include powering on the eNodeB, hardware
check before integration, health check before integration, upgrading SW to L14B,
loading 3 Sectors and 3 Cells configuration scripts, features and parameters
setting, and the post health check after integration.
OSS Definition
Chao Xu O
Approved Checked Date Rev Reference
CU
2.2 Role Timetable ofContact
Events Phone number
Project Manager Harold Tibanyenda +255 712800024
GSC China
Role Contact Phone number
Power on RBS
Network Integration
Upgrade SW to L14B
OSS Definition
Concluding Activities
Chao Xu O
Approved Checked Date Rev Reference
3 Pre-requisites
3.1 Pre-Check
Check Description
Radio and Support System cables are connected correctly on the eNodeB as per installation
procedure.
Upgrade Package taken on-site, Rollout Management Board decide the Final SW level.
Check Description
Element Manger and Integrate RBS downloaded from eNodeB and installed on PC
(http://169.254.1.10/em/index.html). The Element Manager will be installed on your PC during the
first eNodeB Integration. Please refer to CPI Document “Installing an Element Management
Application”, 37/1543-LZA 701 6004 Uen B (Note: Version 1.5.0_12 of the Java Runtime
Environment (JRE) is needed.
Confirm FileZilla FTP Server has been installed on PC. Make sure FTP Service has been
unlocked.
4 Implementation
Chao Xu O
Approved Checked Date Rev Reference
Step Description
Click “Services” on the left pane, make sure “FileZilla Server FTP server” in-service.
NOTE: FileZilla FTP Server is optional, other FTP server can be chosen in this step.
Step Description
Chao Xu O
Approved Checked Date Rev Reference
1 Verify RRUS cables are plugged into the appropriate connection points in the DUL and that
Ethernet cable is plugged in the appropriate connection between DUL and local router.
Note: There are only one CPRI cable connected to DUS per secter (one AIR11),
so there are only 3 CPRI cable connected to DUS, and the ARUS(Inside AIR11)
will be cascaded.
2 Power on the RBS if not already done. Refer to CPI document “Installing RBS”.
3 Check optical indicators on the RBS HW; ensure that the green power indicators are on. If
there are any indications of faulty hardware follow the appropriate OPI to fix. If there are
still issues contact NIC for advice on how to further proceed.
1 Connect an Ethernet cable from your PC to the eNodeB local Ethernet port (LMT).
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 6 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
NOTE: This will be under Start -> EM Applications -> RBS Element Manager.
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 7 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
4 From the RBS Element Manager application log into the rbs by entering the following IP
address in the “Address” field in the bottom, left corner:
169.254.1.10
Chao Xu O
Approved Checked Date Rev Reference
moshell 169.254.1.10
lt all
trun DAR020_TN.mo
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 9 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
This step should be done on site, after this script run completed, do a connectivity check
from eNodeB or call integration team to check the connectivity by remotely.
Notes: the following steps can be done on site and also can be done by remote
integration, if the connectivity is ok, the integrator can do the following activities
via OSS remotely.
4.3 SW Upgrading
Rollout Management Board should decide which SW level the new eNodeB will
be upgraded. According to the RAN solution design, the SW L14B R36AJ will be
used for TZ Tigo LTE trial project
Way1: Apply to the 6 trial FDD sites which already upgraded to L14A IP4.
alt
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 10 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
Check the basic CV SW version, choose the appropriate Upgrade Package according to
Upgrade Path.
secmode –s
Chao Xu O
Approved Checked Date Rev Reference
secmode –f u
cr SwManagement=1,UpgradePackage=CXP102051%12_R15AC
Chao Xu O
Approved Checked Date Rev Reference
Chao Xu O
Approved Checked Date Rev Reference
10 Confirm upgrade
cvcu
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 14 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
13 Alarm Check Post-upgrade, compare with alarms got before upgrade, if something
exception happens, call NIC engineer to report the issue.
Alt
14 Repeat this section “SW Upgrading” until eNodeB runs at the required SW level.
trun DAR020_RN.mo
After this step done, the ARUS, sectors and Cells should be configured, as well
as MME.
run 4_Intra_relation.mos // this script will configure the intra cell relation
run 5_fdd_mimo_ret.mos // this script will configure the RET for antenna tilt
run sup_master_single.mos // this script the SUP configuration to monitor the FAN.etc.
Notes: After above scripts completed, need to configure the inter cell relation between
eNodeBs, and this script will be provided later according to the cell relation design.
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 15 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
get licensing=1$
Put license key file into FTP server, eNodeB can access this file. ZIP file should be
3 unzipped to xml file.
Check the logical name for each eNodeB if it is compliant with design doc.
4
get ManagedElement=1 logicalName
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 16 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
Then check LKF has been imported successfully, check attribute “fingerprint” is the correct
one.
get licensing=1$
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 17 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
Inv
Please refer to the attachment for the sites defined into OSS.
Chao Xu O
Approved Checked Date Rev Reference
1 From the Element Manager window click on the drop down menu circled in the picture
below and select “Containment (MOM based)”.
Ensure that the “logicalName” is the correct name for the RBS site that you are integrating
as is circled in the picture below.
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 19 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
Note: Doing this step will cause the Node to radiate. Please be mindful of this when
doing this step and take any necessary precautions to ensure no one is harmed by
the radiation.
From the Element Manager window click on the drop down menu circled in the picture
below and select “Radio Network”.
PATH:
Right click on the cell to list all the available actions and choose “Lock/Unlock” circled in
the picture below
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 20 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
From the drop down menu select “UNLOCKED” and then select the “Set” button as circled
in the picture below
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 21 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
Then select the “Refresh Values” button as circled in the below picture.
NOTE: Verify for all the cells in the eNodeB that the “operationalState” becomes ENABLED. If
not contact the NIC for advice on how the further proceed.
Ericsson Internal
TZ L14B NEW SITE INTEGRATION 22 (23)
Prepared (also subject responsible if other) No.
Chao Xu O
Approved Checked Date Rev Reference
From the task bar click on Alarm, then click Alarm List.
Chao Xu O
Approved Checked Date Rev Reference
> alt
9 Call NIC and have them verify site status and alarms. Once they have verified from the
NIC that the site is integrated correctly this procedure is complete.
5 Post Implementation
Check Description
Log files from this procedure are collected, this include integration log file from section 4.2 to 4.4.
NIC has been contacted and the have accepted the site as Integration Completed
Any outstanding items (eg. Missing cables, incorrect feeder connection), please note down and
contact with NIC.