2016 Design Examples
2016 Design Examples
1. Two identical bar racks; mechanically cleaned, = 75°; bar spacing (clear) = 2.5
cm;
Qpeak = 1.321 m3/sec; Q max = 0.916 m3 /sec; Qave = 0.441 m3 /sec
Velocity through rack at Qpeak = 0.9 m/sec
Velocity through rack at Q max = 0.6 m/sec
Velocity through rack at Qave = 0.4 m/sec
Diameter of the conduit = 1.53 m;
slope of the conduit = 0.00047 m/m; velocity at Q peak = 0.88 m/sec; depth of flow in the
conduit at Qpeak = 1.18 m
A. Design bar racks
1.Compute bar spacing’s and dimensions of the bar rack chamber
Use peak wet weather flow for the rack chamber design.
Clear area through rack openings = Qpeak/vmax = 1.321 m3/sec 0.9 m/sec = 1.47 m2
3. Compute the actual depth of flow and velocity in the rack chamber at Q peak
2 2
𝑣1 𝑣2
Energy equation 𝑍1 + 𝑑1 + = 𝑍2 + 𝑑2 + + ℎ𝐿
2𝑔 2𝑔
2 2
𝑣1 − 𝑣2
ℎ𝐿 = 𝐾𝑒 ( )
2𝑔
The chamber floor is horizontal; Z = 0; the invert of the incoming conduit = 8 cm above the
2
reference datum; K = 0.3
e
Flow 1.321
𝑉= = = 𝟎. 𝟖𝟑𝒎/𝒔 < 𝟎. 𝟗𝒎/𝒔
Net area at the rack 1.25∗1.28
May redesign with 48 or 49 clear openings. The width of the chamber will be reduced and higher
velocity through the screen will be encountered.
1 𝑉 2 − 𝑣2 2 1 0.832 − 0.592
ℎ𝐿 = ( )= ( ) = 𝟎. 𝟎𝟐𝟓𝒎
𝐶 2𝑔 0.7 19.62
𝑊 4⁄3 49 ∗ 10 4⁄3 0.832
ℎ𝐿 = ( ) ℎ𝑣 sin = 2.42 ∗ ( ) 𝑠𝑖𝑛75° = 𝟎. 𝟎𝟐𝟒𝒎
𝑏 50 ∗ 25 19.62
6. Compute the flow depth and velocity in the rack chamber below the rack Depth and velocity in
2 2
𝑣2 𝑣3
the chamber 𝑑2 + = 𝑑3 + + ℎ𝐿
2𝑔 2𝑔
At 50% clogging of the rack, the clear area through the rack is reduced to half and the headloss
through the rack is obtained from the energy equation
2 2
𝑣́ 2 𝑣3
𝑑́2 + = 𝑑3 + + ℎ𝐿
2𝑔 2𝑔
’ ’
Assume outlet channel do not change. i.e., d = d and v = v
3 3 3 3
1 𝑉𝑒𝑙𝑜𝑣𝑖𝑡𝑦 𝑡ℎ𝑟𝑜𝑢𝑔ℎ 𝑟𝑎𝑐𝑘 𝑜𝑝𝑒𝑛𝑖𝑛𝑔 2 − 𝑣́ 2 2
ℎ50 = ( )
0.7 2𝑔
1.321 2.114
Velocity through rack openings at 50% clogging 𝑣 = ́ =
1.25∗0.5∗𝑑́2 𝑑́2
1.321 0.76
v2 ́ = =
1.74 ∗ d́2 d́2
2 2 2
(0.76⁄d́2 ) 0.612 1 (2.114⁄d́2 ) − (0.76⁄d́2 )
d́2 + = 1.25 + + ( )
19.62 19.62 0.7 19.62
Solution:
1) Assume surface settling rate = 40 m3/m2 .d
Therefore, the surface area of the tank = Q/Vo = 20000 / 40 = 500 m2
2) Length of tank (L) = A/W = 500/ (2*6) = 41.7 (42 m) (For two tanks)
3) Detention time and overflow rate at average flow
Tank Volume = 4* 2 (42*6) = 2016 m3
Overflow rate = Q/A = 20000/2(6*42) = 39.7 m 3/m2.d
Detention time = Vol/Q = (2016*24)/20000 = 2.42 h
4) Detention time and overflow rate at peak flow
Overflow rate = Q/A = 50000/2(6*42) = 99.2 m 3/m2.d
Detention time = Vol/Q = (2016*24)/50000 = 0.97 h
The scour velocity is
=
Horizontal velocity for peak flow = Q/A = 25000/(2*6*3.5) = 595.24 m/d = 0.0069 m/sec
Which is < 0.063 m/sec, Hence O.K.
TSS removal rate R = t/(a+b.t) = 2.1/(0.0075+0.014*2.1) = 56.9%
At peak flow = 437.5/12500 = 0.84 h
TSS removal = 0.84/0.0075+0.014*0.84 = 43.61%
3. Designing a long-rectangular settling basin for type -2 settling: A city must treat about
15000 m3/d of water. Flocculating particles are produced by coagulation, and a column
analysis indicates that an overflow rate of 20 m/d will produce satisfactory removal at a depth
of 3.5 m. Determine the size of the required tank.
SOLUTION:
1- Compute surface area (provide two tanks at 7500 m3/d each)
Q= vs . As
7500 m3/d =As × 20 m/d
As =7500/2= 375 m2
2-Select a length- to-width ratio of 3/1, calculate surface dimensions:
w× 3w= 375 m2 Width=11.18 say 11 m Length= 33.54 say 34 m
Design of Sedimentation Basins
3- Check the retention time:
T=volume/flow rate =(11m× 34m× 3.5m) /(7500 m3/d × 1 d/24h) =4.19 h
4-Check horizontal velocity: Vh =Q/As =(7500 m3/d× d/24h)/11m× 3.5m = 8.1 m/h
5-Check weir overflow rate. If simple weir is placed across end of tank, overflow length will 11 m
and overflow rate would be:
7500m3/d× 1d/24h× 1/11m =28.4 m3/h.m
Five times this length will be needed
4.Designing a circular settling basin: Using the data in above example, determine the
diameter required for settling basins.
Solution:
1- Again providing two tanks, the surface area is calculated as before As =375 m2
Design of Sedimentation Basins
2- The diameter is calculated by
πd2/4 = 375 m2 d=21.85 say 22 m
Y = 0.5 kg / kg
kd = 0.05 1 / day
Assuming an MLSS concentration of 3,000 mg/L and an underflow concentration of 10,000 mg/L
from the secondary clarifier, determine ;
B. The mass and volume of solids that must be wasted each day
Solution
B. The mass and volume of solids that must be wasted each day
C. The recycle ratio
6. A prefabricated package plant is to be used to treat the wastewater from a resort area
consisting of 550 individual family residences. The average occupancy has been
estimated to be 2.9 persons per residence. Use a flow of 230 L/person.day and a daily
peaking factor of 2.5 for flow, BOD 5 and SS. Use an hourly peaking factor of 4 for
sizing the sedimentation facilities. Select the type of package plant and size the
principal components of the plant. Effluent BOD 5 concentration of the process must
be or lower than 30 mg/L.
Solution...