Chapter 08 - Questions
Chapter 08 - Questions
Chapter 08 - Questions
Exercise 8A-1
Target Industries manufactures a mold-formed dog dish made out of plastic. The standard quantity of
material input is 2.2 L of a liquified petroleum product with a standard cost of $1.76/L. In 2021 Target
produced 8,000 dog dishes consuming 16,400 L of the input material at a cost of $30,340.
Determine
a. the direct material quantity variance (include U or F)
(301/LO8.2/medium)
Exercise 8A-2
On average, Target’s standard is to produce one dog dish for every 15 minutes of labour, with a
standard labour cost of $24/hour. In 2021, workers logged 2,400 hours at a cost of $50,400 in the
production of 8,000 dog dishes.
Determine
a. the direct labour efficiency variance (include U or F)
(304/LO8.3/medium)
Exercise 8A-3
Maximum Machining Company applies manufacturing overhead to its products based on actual machine
hours used. The standard is based on budgeted variable manufacturing overhead of $400,000 for the
production of 80,000 units requiring a total of 160,000 machine hours. In 20X2, the actual variable
manufacturing overhead cost were $394,680 using 171,600 machine hours to produce 78,000 units.
Determine
a. the variable manufacturing overhead spending variance (include U or F)
(307/LO8.4/medium)
End of Chapter “A” Chapter 8: Standard Costing Problems (Long Questions)
Problem 8A-1
Barracuda Industries has the following incomplete information available regarding its budgeted and
actual variable costs for 20X1 and their variances. Barracuda allocates variable manufacturing overhead
on the basis of machine hours.
Required:
a. Please complete the table based on the information that is provided. The grey-shaded cells
must be solved first and can be solved based on information that is provided. The second group
to be solved have green-shaded backgrounds. After these are solved, others will follow.
Standard
Variance costs at
Actual Costs Name Standard Variance standard
at actual Amount costs at actual Name amounts
quantity (F/U) quantity Amount (F/U) (budget)
Direct Materials
$3,120,000
Total Variance: $60,000 U
Direct Labour
Rate Efficiency
Variance Variance
$64,000 F $80,000 U
Total Variance:
Var. Mfg. Ovrhd
Efficiency
Variance
-
Total Variance:
b. Based on the information provided, suggest at least one possible explanation for one of the
variances of each variable cost component.
(401/LO8.2,3,4/Difficult)