FM I Chapter 6
FM I Chapter 6
Long-term investments are also called capital budgeting. The term capital refers to the fixed
assets used in production, while a budget is a detailed plan of projected cash flows during some
future period. Thus, the capital budget of the firm outlines the planned expenditures of the fixed
assets, and capital budgeting is the whole process of analyzing projects whose returns are
expected to extend beyond the period of one year and deciding which project should be included
in the capital project. Capital budgeting expenditures include expenditures for land, building,
equipment, and for permanent additions to working capital associated with plant expansion, for
advertising and promotion campaigns, and for research and development programs.
1.1. Process to Capital Budgeting
Therefore, the net cash flows from the project during the final year of the project's life comprise
of the operating cash flows, the proceeds from the sale of the used assets, and the recovery of net
working capital.
This topic is concerned with the ranking of projects for the decision of whether or not they
should be accepted for inclusion in the capital budget. It is assumed that projects to be covered
in this topic are equally risky. All cash flows are assumed to occurs at the end of the designated
year. Generally, the project evaluation techniques are classified into two categories. These are:
1. Non-Discounted cash flow technique: They are called the traditional techniques because
they do not consider the time value the time value of money concepts in ranking investment
proposals. Two methods are included under the traditional technique, namely the payback
period and the accounting rate of return.
a) The payback period: - The payback period is the number of years that is required for the
business firm to recover from the project the amount of the initial investment in total. If
the cash flows from the project are in an annuity form, the payback period can easily be
determined by dividing the initial investment by the annual cash flow in the annuity. That
is,
Payback period (in years) = Initial investment
Annual Cash flows
When the cash flows from the project are not in an annuity, the payback period is computed as
follows:
Unre cov ered Cost
Payback period = year before full recovery + Annual flow during the next year
To illustrate the computation of the payback period when the cash flows from the project is an
annuity form, suppose the project requires an initial investment of Br. 24,000 and the annual
after-tax cash flows of Br. 6,000 for five years. The payback period is, therefore,
Pay back period = 24,000/6000 = 4 years
This is to mean that the initial investment amount of this particular project will be recovered with
in the first four years of the project life (i.e. 6,000 for four years is 24,000).
To illustrate the computation of the payback period when the cash flows from the project are not
in an annuity form assumes the project requires an initial investment of Br. 60,000. The after-tax
cash flows from the project are Br. 8,000 during year 1, Br. 15,000 during year 2, Br. 22,000
during year 3, Br. 20,000 during year 4, and year 5 each. To determine the payback period, we
first need to compute the cumulative cash flows of the project.
2. It ignores the time value of money which is an important variable that demands
consideration in evaluating the desirability of a given project.
b) The Accounting Rate of Return (ARR): The accounting rate of return (ARR) is the rate
of return that is calculated by dividing the projects expected annually net profit by the
average investment outlays. The average investment outlays, on the other hand, are
computed by dividing the sum of original cost of the project and the salvage value of return
(ARR) can be expressed with an algebraic equation as follows.
To compute the accounting rate of return (ARR) for this project, first we have to determine the
average investment and the annual depreciation amount.
Average investment = (70,000 + 6000)/2 = Br. 38,000
Annual depreciation = (70,000 - 6,000)/4 = Br. 16,000
Then compute the new profit for each year during the four years.
Year 1 Year 2 Year 3 Year 4
Income before depr. & taxes 40,000 42,000 36,000 50,000
Less: Annual depreciation 16,000 16,000 16,000 16,000
Income before taxes 24,000 26,000 20,000 34,000
Less: Income taxes (40%) 9,600 10,400 8,000 13,600
Net Income 14,400 15,600 12,000 20,400
Then we compute the average Net Profit during the four years.
That is:
Average net profit = (14,400 + 15,600 + 12,000 + 20,400)/4
= 15,600 Birr
Hence, ARR = Average Annual net profit = 15,600 = 0.41 or 41%.
Average cost of investment 38,000
This is to mean that for an average of 1 Birr invested in this project, there is an average return of
41 cents in the form of net profit per year over the entire four years of the life of the project.
The accounting rate of return method of project evaluation, like the payback period method,
ignores the timing of cash flows or the time value of money. Moreover, the accounting rate of
return ignores the fluctuations of the cash flows over the life of the life of the project as it
assumes an average cash flows every during the project's life.
2. The Discounted Cash flow (DCF) Techniques: The discounted cash flow techniques are
other methods of evaluating and ranking investment project proposals. These techniques
employ the time value of money concept
a) The discounted Payback period
The discounted payback period is defined as the number of years that is required to recover the
amount of money invested in a project at the beginning after discounting the future cash flows to
their present values. Discounted payback period is computed in the same manner as that of the
regular payback period except the discounted cash flows are used in the case of discounted
payback period. The expected future cash flows are discounted by the project's cost of capital.
To illustrate suppose that a given capital budgeting alternative is expected to have an initial
investment of Br. 30,000 and the life of 5 years. The after-tax cash flows from the project during
years 1, 2, 3, 4 and 5 are Br. 15,000, 18,000, 12,000, 20,000, and 22,000 respectively. The cost
of capital (the required rate of return) is 10 percent. What is the discounted payback period for
this project?
To answer this question, first we have to compute the discounted cash flows and the cumulative
cash flows for each year. Hence, the discounted cash flows and the cumulative cash flows year
by year are show as follows.
Year Cash flows Discount Factor Present Value Cumulative CF
1 15,000 0.9091 13,636 13,636
2 18,000 0.8265 14,877 28,513
3 12,000 0.7513 9,016 37,529
4 20,000 0.6830 13,660 51,189
5 22,000 0.6209 13,660 64,849
As you can see from the cumulative discounted cash flows the discounted payback period for
project is between 2 and 3 years. The exact payback period (discounted) can be computed as:
Discounted Payback period = 2 years + (1,487/9,016) years
= 2 years + 0.16 years = 2.16 years
= or 2 years + (0.16) (12 months)
= 2 years and 2 months.
It requires the project a period of 2 years and 2 months to recover its initial net investment taking
the time value of money into account.
b) The Net Present Value (NPV) Method
The net present value (NPV) method is an investment project proposal evaluating and ranking
method using the net present value, which is the difference between the present values of future
cash inflows and the present value of cash outflows, discounted at the given cost of capital, or
opportunity cost of capital.
In order to use this method properly, the following procedures are followed.
1. Find the present value of each cash flow, including both inflows and out flows
2. Sum the discounted cash inflows and the discounted cash outflows separately.
3. Obtain the difference between the cash inflows and the sum of the cash outflows.
Decision Rule for the Net Present Value (NPV) Method: f the projects are independent, the
projects with positive net present values are the ones whose implementation maximizes the
wealth of shareholders. Hence, such projects should be accepted for implementation. If the
projects, on the other hand, are mutually exclusive, the one with the higher positive NPV should
be accepted leading to the rejection of the projects with lower positive NPV. Projects with
negative NPV should not be considered for acceptance in the first place.
To illustrate assume that a given project is expect to have an initial investment of Br. 40,000
and project life of 5 years. The annual after-tax cash flow is estimated at Br. 12,000 for each one
of the five years. Using the required rate of return of 10 percent, What is the net present value
(NPV) of the project? How do you judge the acceptability of this project?
In order answer these question, it is wise to identify the cash inflows and outflows. In the case of
this project, there are annuity cash inflows of 12,000 every year for five years and a single cash
out flow of 40,000 at time zero.
The present value of the annuity cash inflows is:
Present value of annuity = (12,000) )(Annuity factor)
The annuity factor given the period of 5 years and discount rate of 10 percent is 3.791
substituting the factor I the equation above
PVA = (12,000) (3.791) = Br. 45,492
Or Present Value of Annuity is:
( 1−(1 .1)−5
0.1 )
= 12,000 x 3 .791=Br . 45,492
Since the project makes the net present value (NPV) of positive Br. 5,492, it should be accepted.
To further illustrate the NPV method, consider the following mutually exclusive project
alternatives, together with their cash flows.
The required rate of return on both projects is 12 percent. Then, evaluate these projects using the
net present value method.
The evaluation of these two projects requires the computation of the net preset values for both
projects. The net present value (NPV) for project A is:
Since the two projects are mutually exclusive, the one with the higher NPV has to be accepted.
Thus, project A is selected as its NPV is higher than that of project B.
Step 2: Find the IRR by looking along the appropriate line (year) of the present value of
annuity table until the column which contains the critical discount factor (i.e. the discount
factor computed under step 1) is located.
To illustrate assume that a project has a net investment of Br. 20,000 and annual net cash
inflows of Br. 5,200 for five years. What is the IRR of this project? In order to answer this
question, we need to follow the two steps discussed above.
Then, compute the sum of the absolute values of the NPV's obtained:
The absolute sum of the NPVs = |226| + |-288| = 226 + 288 = 514
Thus,
Pr esent Value of Smaller rate
IRR = Smaller rate + Absolute Sum of NPV (larger rate - smaller rate)
226
IRR = 9% +514 (10 - 9) = 9% + 0.44 = 9.44% or
Pr esent Value of l arger rate
IRR = Larger rate - Absolute Sum of NPV (larger rate - smaller rate)
288
IRR = 10% - 514 (10 - 9) = 10% - 0.56 = 9.44%
When the cash inflows from the project are not in an annuity form, IRR is calculated through an
iterative process or through "trial and error". It may be difficult to identify from which discount
rate to start. A good first guess can be made by estimating the discount factor.
In general, the following procedures are used to calculate the IRR of the non-uniform net cash
flows.
Step 1:Find the estimated discount factor. In fact, if the fluctuations I the cash inflows
is very large, the estimated discount factor doesn't not help you much in
locating the IRR in the present value of annuity table.
Estimated discount factor = Net investment
Average cash inflows
Step 2:Look at the present value of annuity table to obtain the nearest discount
rate for the estimated discount factor determined in step 1.
Step 3:Calculate the NPV using the discount rate identified in step 2.
Step 4:If the resulting NPV is positive, choose the higher discount rate and repeat the
procedure. Choose the lower discount rate if the NPV is negative, and repeat
the same procedure until you find the discount rate that equates the NPV to
zero.
To illustrate assume a project that has an initial investment of Br. 40,000 and the following net
cash inflows:
Year 1, Br. 15,000; year 2, 10,000; Year 3, 10,000; year 4, 15,000; and year 5, 15,000. What is
the IRR of this project.
In order to estimate the discount factor, you need to give weight to the cash flows over the life
of the project. Larger weights should be given to the cash flows towards the beginning of the life
of the project than to the cash flows that occur towards the end of the project life.
Hence,
Year Weight Cash flow x weight
1 5 75,000
2 4 40,000
3 3 30,000
4 2 30,000
5 1 15,000
15 190,000
By looking up in the present value table for annuity, the approximate the discount factor of 3.158
online 5 (n=5) is 18 percent. Thus, the starting point of the iterative process is 18 percent. The
NPV of the project using the discount rate of 18 percent is:
As per the above calculations, NPV is negative when the discount rate of 19 percent is used and
positive when the discount rate of 18 percent is used. Thus, the IRR for this project falls
between 18 percent and 19 percent. If the exact IRR is needed, the interpolation method is can
be used. That is:
Step 1: Compute the sum of the absolute values of the NPV's obtained:
The absolute sum of the NPVs = |270| + |-640| = 270 + 640 = 910
Thus,
Pr esent Value of Smaller rate
IRR = Smaller rate + Absolute Sum of NPV (larger rate - smaller rate)
270
IRR = 18% +910 (19 - 18) = 18% + 0.3 = 18.3% or
Pr esent Value of l arger rate
IRR = Larger rate - Absolute Sum of NPV (larger rate - smaller rate)
640
IRR = 19% - 910 (19 - 18) = 19% - 0.7 = 18.3%
The rational for the IRR method is that the IRR on a project is its expected rate of return. If the
IRR of a given investment project exceeds the cost of the funds used for financing the project
(cost of capital), there is the remaining surplus after paying for the capital, and this surplus adds
up on the wealth of the shareholders of the firm. Therefore, selecting the project whose IRR
exceeds its cost of capital increase the share holders' wealth. On the other hand, the project with
the IRR less than the cost of capital imposes an unnecessary cost on current shareholders. The
return from the project will to cover even the cost of capital.
Decision Rules for IRR
A project whose IRR is greater than its cost of capital, or Required Rate of Return (RRR) is
accepted and whose IRR is less than the RRR of the project is rejected.
Profitability index is the ratio of the present value of the expected net cash flow of the project
and its initial investment outlay.
Pr esent Value
PI = Initial Investment
Profitability index provides or measure of profitability in a more readily understandable terms. It
simply converts the NPV criterion into a relative measure.
Decision rule:
When BCR Decision rule
>1 Accept
=1 Indifferent
<1 Reject
Illustration:
The project which has a cost of capital of 12%, initial investment and cash flows are given below
Project Year 0 Year 1 Year 2 Year 3 Year 4
A (100,000) 25,000 40,000 40,000 50,000
From the above example project A is accepted using profitability index because its PI is greater
than that of project B. However, NPV of project B is greater than that of the NPV of project A.
Thus, even though the profitability index of a project is a very useful tool, it should not be used
as a decision rule when mutually exclusive projects for different size are being considered.
0 1 2 3 4 5 6
Project A (40,000) 10,000 12,000 15,000 11,000 9,000 11,000
Project B (30,000) 12,000 14,000 13,000 - - -
The two projects are incomparable. Thus, according to replacement chain approach, project B
will be repeated in three years. Assuming that annual cash flows and the discount rates will not
change. Thus, if project B is repeated, its year 4, year 5, and year 6 cash flows are Br. 12,000,
Br. 14,000, and Br. 13,000 respectively. In this way, the two projects have the same life. If
project B is repeated, its cash flows will be:
0 1 2 3 4 5 6
(30,000) 12,000 14,000 13,000 12,000 14,000 13,000
The present value computation of the repeated project B requires a two-step process. These are:
Step 1: you compute the present values at t = 0 and at t = 3 for the repeated project B.
Present value at time zero (t = 0) = (12,000)(0.909) + (14,000)(0.826)+(13,000)(0.751)
= Br. 32,235
Present value at time 3 (t = 3) = (12,000)(0.909) + (14,000)(0.826) + (13,000)(0.751)
= Br. 32,235
Step 2: Discount the present value of the repeated project at time 3 (t=3) to the present value at
time zero (t = 0).
That is, present value of repeated project B at time zero = (32,235)(0.751) = Br. 24,208
Then, add the present value of the first three years cash flows to the present value of the repeated
project after three years. That is:
Total present value = 32,235 + 24,208 = Br. 56,443.
Hence, the NPV of the repeated project B = 56,443 – 30,000 = Br. 26,443
The NPV of project A is calculated as follows.
Year Discount factor Cash flow present value
1 0.909 10,000 9,090
2 0.826 12,000 9,912
3 0.751 15,000 11,265
4 0.683 11,000 7,513
5 0.621 9,000 5,589
6 0.564 11,000 10,204
Present value of cash flows 49,573
Less. Present value of initial investment 40,000
NPV of project A 9,573
Therefore, using the NPV method for project comparison of the two projects, project B should be
selected.
Under the replacement chain approach of comparing projects with unequal lives, the least
common factor of the projects lives is used to find the common useful life. For instance, if the
life of project A is 5 years and that of project B is 3 years, project A is repeated 3 times and
project B is repeated 5 times because the least common factor for the two project lives (i.e 3 and
5) is 15 years.
Step 2: Find the equivalent annual annuity that has the same present value as the projects’
NPV.
Equivalent annual annuity can be calculated as follows.
For project A:
PV of cash flows = 49,573. By looking up in the present value of annuity table at n = 6 and
i=10%, the discount factor is 4.355.
Thus, PV of cash flows = cash flows x Discount factor
49,573 = (4.355) (x) where x is the equivalent annual annuity.
X = 49,573/4.355 = Br. 11,383
For project B:
NPV = PV of cash flows – PV of initial out lays
2,235 = PV of cash flows – 30,000
PV of cash flows = 2,235 + 30,000 = 32,235
By looking up in the present value of annuity table for the discount factor that corresponds to
n=3 and i=10% is 2.487. Hence
(y) = 32,235/2.487 where y represents the equivalent annual annuity amount for the project.
Solving for y we get.
Step 3: The project with the higher equivalent annual annuity will always have the higher NPV
when extended out to any common life. Therefore, project B’S equivalent annual
annuity (EAA) is larger than project A’S, project B would be chosen.
Capital Rationing
Capital rational is a situation in which a constraint is placed on the total size of the firm’s capital
budget. Capital ration is said to exist when we have profitable (positive NPV) investments
available but we can’t get the needed fund to undertake all of them. Two main reasons can be
mentioned. One is what is called soft rationing which is the situation that occurs when units are
allocated a certain amount of financing for capital budgeting. Such allocation is primarily a
means of controlling and keeping track of overall spending. Soft rationing doesn’t mean that the
business firm as a whole is not short of capital. The other reason is hard rationing. Hard
rationing is the situation that occurs when a business cannot raising finance or funds for a project
under any circumstances. A business firm with a sound financial status does not face hard
rationing.
1. The timing and magnitude of the cash flows of all projects (all project alternatives) are
known.
2. The cost of capital is known
3. All projects are strictly independent
4. The total investment outlay of all those projects that have a positive NPV exceeds the firm’s
budget constraints.
Taking these assumptions into account, the problem under capital rationing is how to choose a
subset of desirable projects in such a way that total investment does not exceed the budget. In
order to solve this problem, the sound procedures are as follows.
1. Rank all projects with positive NPVS in accordance with their profitability indeed.
2. Select projects from the top of the list (with the highest profitability index) until the fixed
budget is exhausted.
To illustrate suppose that a firm has a fixed capital budget of Br. 600,000 and has the following
investment alternatives.
To answer this question, first we have to rank these project based on the value of their
profitability index. Hence, their arrangement according to their profitability index is E-C-A-B-
D. Therefore, given the capital budge constraint of Br. 600,000, projects E, C and A are selected.
The initial capital requirements for these projects (i.e. 330,000 + 120,000 + 150,000 = 600,000).
So the total initial investment cost of the three projects is exactly equal to the total capital budget
of the firm. This implies that the rest of the project alternatives cannot be implemented because
of the lack of capital though they are all acceptable ones. The total net present value (NPV) of
the projects that were selected is 60,000 + 70,000 + 40,000 = Br. 170,000.
Up to this point, we have ignored risk in capital budgeting; that is we have discounted expected
cash flows back to their present values and ignored any uncertainty that might surround the
expected cash flows. In reality, the future cash flows associated with the introduction of a new
sales outlet or a new product are estimates of what is expected to happen in the future, not
necessarily what will happen in the future. But, these cash flows discounted to their present
values have only been our best estimate of the expected cash flows.
In this section, we will assume that under conditions of risk we do not know beforehand what
cash flows will actually result from the new project. However, we do have expectations
concerning the outcomes and are able to assign probabilities to these outcomes. Staled in another
way, although we do not know the exact cash flows resulting from the acceptance of a new
project, we can formulate the probability distributions from which the flows will be drawn. Risk,
here, is defined as the potential variability in the future cash flows.
Selecting the appropriate required rate of return involves subjective judgments. Given the
general patterns of managerial risk aversion, which shows the direct relationship between risk
and return, the following guidelines can be established.
1. The coefficient of variation can be used as the measure of risk per birr of return. As such,
it can be used to rank the riskiness of probability distributions of cash values.
2. The required rate of return can be set to the sum of the risk-free rate plus some additional
return to compensate for risk.
When a risky investment is to be evaluated on an accept or reject basis, the RANPV criterion
provides the following decision rule: Accept the risky project if its RANPV is positive or zero;
reject it if the project’s RANPV is negative.
To illustrate how to evaluate a project under a condition of risk (i.e. when the cash flows are not
certainly know rather given probability distributions under different state of the economy)
suppose a risky project that has a life of four years. The estimated risk adjusted rate of return is
10 percent. The initial investment of the project is Br. 29,000.
Compute the payback period for this risky project. What is the RANPV of the project? Compute
the IRR of the project. Calculate the profitability index of the project. Before we answer each
one of the questions, let us computed the expected cash flows for each year of the project life as
follows:
Year 1: (12,000) (0.20) + (10,000) (0.50) + (7,000) (0.30) = 9,500 birr
Year 2: (18,000) (0.10) + (15,000) (0.50) + (13,000) (0.40) = 14,500 birr
Year 3: (15,000) (0.30) + (14,000) (0.40) + (12,000) (0.30) = 13,700 birr
Year 4: (19,000) (0.30) + (16,000) (0.50) + (14,000) (0.20) = 16,500 birr
Using these expected cash flows for the project, the payback period can be computed as follows:
Year Expected Cash flows Cumulative cash flows
1 9,500 9,500
2 14,500 24,000
3 13,700 37,700
4 16,500 54,200
The payback period for this project is longer than 2 years and shorter than 3 years because the
initial investment of Br. 29,000 is greater than the cumulative cash flows at the end of year 2 of
Br. 24,000 and less than the cumulative cash flows at the end of year 3. If the expected cash
flows occur uniformly throughout the year, the payback period will be between 2 year and 3
years. The exact payback period is computed as follows.
The Risk adjusted Net present value (RANPV) of the project can be computed by using the
expected cash flows determined above. These expected cash flows are discounted at the risk
adjusted discounting rate of 10 percent. The initial investment amount is subtracted from the sum
of the discounted expected cash flows and difference is what is known as the risk adjusted net
present value (RANPV).
RANPV = (9500) (0.909) + (14,500) (0.826) + (13,700) (0.751) + (16,500) (0.683) – 29,000
= 8,635.50 + 11,977 + 10,288.70 + 11,269.50 – 29,000 = 42,170.70 – 29,000
= 13,170.70
The IRR of this project is determined through an iterative process because the expect cash flows
are not in an annuity form. To identify the starting point, we assign a weight, the highest weight
to the cash flows of the first year and the lowest weight to the cash flows of the last year in the
project life.
The estimated discount factor of 2.313 is near to the present value of annuity table value of
2.320, which is found in the 26 percent column in year 4 row. Hence, the first guess is 26
percent.
RANPV (29%) = (9,500) (0.775) + (14,500) (0.601) + (13700) (0.446) + (16,500) (0361) –
29,000
= 7,362.50 + 8,714.50 + (6384.20 + 5956.50 – 29,000 = 28,417.70 – 29,000
= Br. (582.30)
Since the Net present value at a discount rate of 29 percent is negative, the IRR for this project
must be less than 29 percent and greater than 26 percent. Hence, the IRR of this project can be
computed as follows.
Step 1: Compute the sum of the absolute values of the NPV's obtained:
The absolute sum of the NPVs = |1078.5| + |-528.3| = 1,669.8
Thus,
Pr esent Value of Smaller rate
IRR = Smaller rate + Absolute Sum of NPV (larger rate - smaller rate)
1,078.5
IRR = 26% + 1,669.8 (29 - 26) = 26% + 1.93 = 27.93% or
Pr esent Value of l arger rate
IRR = Larger rate - Absolute Sum of NPV (larger rate - smaller rate)
582.3
IRR = 29% - 1,669.8 (29 - 26) = 29% - 1.07 = 27.93%
Certainty Equivalent
1. While appraising projects, future cash flows are estimated using probability measures like
forecasting techniques. These measures do not give a true picture of future events. To
avoid uncertainty, convert expected future cash flows into certain cash flows. Certain
cash flows are cash flows obtained by multiplying uncertain cash flows with a
predetermined base known as certainty-equivalent coefficient. A certainty-equivalent
coefficient is factor that determines the risk associated with future cash flows. Risky
investments have a low certainty equivalent rating, hence they are avoided. This is
because the probability of netting the estimated cash flows is unlikely.
Sensitivity Analysis
Sensitivity analysis put in simple terms is a modeling technique which is used in Capital
Budgeting decisions which is used to study the impact of changes in the variables on the
outcome of the project. A project's return on investment is affected by factors such as sales,
investments, tax rate and cost of sales. Sensitivity analysis measures the extent to which the
project's cash flows change in response to changes in one of these factors. The sensitivity
analysis process involves identifying the factors that influence the project's cash flows,
establishing a mathematical relationship between these factors and analyzing how a change in
each of these factors affect the project's cash flows. If a project's cash flows are sensitive to
changes in any of the above-listed factors, it is considered risky and hence avoided.
Sensitivity analysis and Scenario analysis both help to understand the impact of the change in input
variable on the outcome of the project. However, there are certain basic differences between the two.
Sensitivity analysis calculates the impact of the change of a single input variable on the outcome of the
project viz., NPV or IRR. The sensitivity analysis thus enables to identify that single critical variable that
can impact the outcome in a huge way and the range of outcomes of the project given the change in the
input variable.
Scenario analysis, on the other hand, is based on a scenario. The scenario may be recession or a boom
wherein depending on the scenario, all input variables change. Scenario Analysis calculates the outcome
of the project considering this scenario where the variables have changed simultaneously. Similarly, the
outcome of the project would also be considered for the normal and recessionary situation.
The variability in the outcome under the three different scenarios would help the management to assess
the risk a project carries. Higher deviation in the outcome can be assessed as higher risk and lower to
medium deviation can be assessed accordingly.
Scenario analysis is far more complex than sensitivity analysis because in scenario analysis all inputs are
changed simultaneously considering the situation in hand while in sensitivity analysis only one input is
changed and others are kept constant.
//
For more, Refer
https://static.careers360.mobi/media/uploads/froala_editor/files/Risk-Analysis-in-Capital-
Budgeting.pdf https://static.careers360.mobi/media/uploads/froala_editor/files/Risk-Analysis-in-
Capital-Budgeting.pdf