METHODOLOGY
RatedPower
BOQ METHODOLOGY
Index
1 Glossary 3
2 Introduction 4
3 PV Plant Description 4
3.1.1 DC Side 4
3.1.2 AC Side 4
3.2.2 Foundations 5
3.3.1 Cables 7
3.3.5 Connectors 7
3.4 Miscellaneous 8
3.4.3 Buildings 8
4.1 Substation 9
4.1.5 Miscellaneous 12
Page 1
BOQ METHODOLOGY
5.1.1 Towers 13
5.1.2 Conductors 13
5.1.3 Insulators 13
5.2 Miscellaneous 14
Page 2
BOQ METHODOLOGY
1 Glossary
AC: Alternating Current.
PV: Photovoltaic.
Page 3
BOQ METHODOLOGY
2 Introduction
This document provides a brief explanation of how RatedPower calculates the different
parameters found in the Bill of Quantities (BOQ). The same file will present the plant and
substation’s bill of quantities in separate sheets. The parameters are divided into the same
sections of the BOQ sheet.
For simplicity, low voltage will be written as LV, medium voltage as MV and high voltage as HV.
3 PV Plant Description
3.1 Main Equipment
This section includes all the main equipment of the PV plant.
3.1.1 DC Side
● PV Modules: the total number of PV modules installed in the PV plant.
● Trackers or fixed structures: the total kWdc of structures.
● DC Electrical Box: the total number of level 1 string boxes.
● DC Electrical Box Level 2: the total number of level 2 boxes
3.1.2 AC Side
● Power Station: the total number of power stations.
● Inverter: the total number of inverters installed.
● Secondary inverter: the total number of secondary inverters.
Page 4
BOQ METHODOLOGY
● Road ditches: are used to channel water if needed (drainage). They have the same
length as the roads and are placed on one side of the road only.
3.2.2 Foundations
● Power Station foundation: equals the number of power stations in the PV plant.
The design of the foundation of the power stations tends to be foundation slab or
compacted terrain based on the terrain characteristics and the station supplier for power
stations.
The number of units of the five aforementioned points is the same. It is calculated by dividing the
total power carried by the trackers by the product of the power of one module and the number of
modules per tracker. The result is then multiplied by the number of poles per tracker. The same
procedure should be done in the case of fixed structures. The only difference, however, would be
multiplying the final result by 2 if bi-pole structures were selected.
1. LV cabling from strings to string boxes/DC Bus collectors/string inverters have been
designed laid in trays/raceways/messenger cables.
2. LV cabling from string combiner boxes/DC Bus collectors to inverters/L2 String boxes
have been laid directly buried in LV trenches:
a. The installation of LV cabling has been designed with a minimum depth of
700 mm.
b. The installation of LV cables has been designed having the cables in contact
(no distance between cables).
3. MV cabling from Power Stations to Substation / MV delivery point have been laid directly
buried in MV trenches:
Page 5
BOQ METHODOLOGY
● Earthing trench: is the trench that holds the earthing cable of the power station. This
trench extends around the perimeter of the foundation of the power station. The number
of cubic meters of earthing trench can be calculated by multiplying the perimeter of a
power station by the total number of power stations in the PV plant. The result is then
multiplied by the cross-section of the earthing trench which equals 0.75 x 0.3 m2.
● Ancillary services trench: is the trench that holds the auxiliary system cables. It has the
same length as the perimeter of the fence. The number of cubic meters of ancillary
services trench can be calculated by multiplying the perimeter of the fence by the cross-
section of the ancillary services trench which equals 0.5 x 0.3 m2.
● Manholes: are placed every 50 meters in each trench. This number differs from LV to MV.
To calculate the number of LV manholes, the total number of cubic meters of LV trenches
is divided by the cross-section area of the trench. If more than one trench type is used, this
value is calculated for each. The resulting values are summed up together and then divided
by 50. We then add the number of power stations multiplied by 2 to the previous result.
The same method should be done in the case of MV manholes with the only exception of
not multiplying by 2 in the final phase of the calculation.
Page 6
BOQ METHODOLOGY
● Video camera foundation: a video camera foundation is placed for every 100 meters of
the fence.
3.3.1 Cables
● Cables: in this section, the total length of each of the LV and MV cables of the PV plant is
represented. We apply a unification of the cable sizes which defines a maximum of two
cable sizes for each part of the electrical system.
3.3.5 Connectors
● DC male and female connectors: these connectors are MC4 or similar models and equal
two times the number of strings.
Page 7
BOQ METHODOLOGY
● MV connectors: is the total number of MV connectors in the PV plant and equals three
times the number of MV incomings and outgoings of each Power Station.
● DC Bus Connectors (Niled type or similar): is the total number of DC Bus connectors in
the PV plant and equals two times the number of strings.
3.4 Miscellaneous
This section includes the monitoring and security and control systems of the PV plant.
3.4.3 Buildings
● Control Room Building & Warehouse Building: both are always equal to 1 in the PV
plant.
Page 8
BOQ METHODOLOGY
The substation section represents the same categories and sub-categories found in the BOQ file.
The elements found in the bill of quantity correspond to the resulting type of substation.
● Power transformer: The power transformers’ total number installed in the substation.
The power transformer can be a two-winding or three-winding transformer.
● HV winding earthing: The total number of the power transformers’ primary winding
earthing
● MV winding: The total number of the power transformers’ secondary winding earthing
equipment.
● MV surge arrester: The total number of the MV surge arresters in the substation.
This section includes all the equipment in the high voltage side of the power transformer.
Output Circuit Bay: The total number of HV output bays of the substation, each bay includes:
● Surge arrester: The total number of surge arresters in the output bays of the substation
● Earthing disconnector: The total number of earthing disconnectors in the output bays of
the substation
● Current transformer: The total number of current transformers in the output bays of the
substation
● Voltage transformer: The total number of voltage transformers in the output bays of the
substation
● Circuit breaker: The total number of circuit breakers in the output bays of the substation
● Disconnector: The total number of disconnectors in the output bays of the substation. In
the case of a double bus bar substation, the number of this element for each bay is 2.
Transformer bay: the total number of the circuit bays before connecting to the bus bar(s). Each
bay includes:
● Surge arrester: The total number of surge arresters in the transformer bays of the
substation
Page 9
BOQ METHODOLOGY
● Current transformer: The total number of current transformers in the transformer bays
of the substation
● Circuit breaker: The total number of circuit breakers in the transformer bays of the
substation
● Disconnector: The total number of disconnectors in the transformer bays of the
substation. In the case of a double bus bar substation, the number of this element for
each bay is 2.
Bus bar: This sub-section represents the quantities of the bus conductor and the electrical
equipment of the bus bar, a circuit breaker, and a voltage transformer. In the case of a double
bus bar substation the total number of voltage transformers in the bus bar is 2.
● Conductor: The total length of the bus bar conductor. For a double bus bar, the total
length is the span length multiplied by the sum of the number of both input and output
bays and the span length of the bus coupler multiplied by each busbar then multiplied by
the 3 phases. For a single bus bar, the total length is the maximum number of bays
between the input and output bays multiplied by the span length and the 3 phases. The
same element is given per unit, each unit represents a span of a bus bar.
● Post-insulator: the total number of the post insulators in the bus bar. Each bus bar has 6
post insulators, so the total number depends on the number of the busbars.
● Voltage transformer: the number of the voltage transformers connected to the bus bar
of the substation. In the case of a double bus bar, the quantity is 2 (one for each busbar).
Bus coupler: When the arrangement is a double busbar, this element represents the total
number of circuit breakers (always 1) and disconnectors (always 2) in the bus coupler.
Input feeder MV cubicle: Total number of the MV input cubicles in the substation. This element
includes:
● Circuit breaker: Total number of circuit breakers in the input feeder cubicles.
● Earthing disconnector: Total number of earthing disconnectors in the input feeder
cubicles.
● Current transformer: Total number of current transformers in the input feeder cubicles.
Output feeder MV cubicle: Total number of output feeder cubicles each connected to
secondary winding. It includes:
● Circuit breaker: Total number of circuit breakers in the output feeder cubicles.
● Earthing disconnector: Total number of earthing disconnectors in the output feeder
cubicles.
● Current transformer: Total number of current transformers in the output feeder cubicles.
Page 10
BOQ METHODOLOGY
Metering MV cubicle: The total number of metering cubicles in the substation. Each MV
switchgear has 1 metering cubicle. It includes:
● Earthing disconnector: Total number of earthing disconnectors in the metering cubicles
● Voltage transformer: Total number of voltage transformers in the metering cubicles
Auxiliary MV cubicle: The number of auxiliary cubicles in the substation, which is always 1. The
cubicle includes:
● An earthing disconnector
● A fuse
● An auxiliary power transformer
Site conditions:This section presents the civil work done to the substation site. The perimeter
considered in the following calculations is not the one of the substation polygon from the
KML/KMZ file; however, it is calculated internally.
● Clearing and grubbing: consists of land preparation and cutting any undesirable
elements for proper construction. It is the area inside the perimeter of the fence.
● Topsoil and vegetation removal: consists of the removal of a layer of 20 cm depth in the
area inside the perimeter of the fence.
● Internal roads: the proposed road will be always designed with a default value of 4.0
meters width.
● Road ditches: are used to channel water if needed (drainage). They have the same
length as the roads and are placed on one side of the road only.
Buildings: The area of the control building of the substation. This area depends on the
substation capacity. If the capacity is less than 50MW, the area is 150m², if more the building will
have an area of 300m². When the arrangement is a line-to-transformer, the area is always 150m².
● Chain link fence: the total perimeter calculated of the fence. It is installed around the
whole substation. It has been proposed with at least 2 meters of height and 3 meters
between posts and at the corners.
● Access gate: Total access gates in the substation, always 2.
● Video camera foundations: The total number of security camera’s foundations, which is
for every 100 meters of fence. These posts have a height of 6 meters.
● Light pole foundation: The total number of light pole foundations, which are placed for
every 50 meters of fence. These posts have a height of 4 meters.
Page 11
BOQ METHODOLOGY
4.1.5 Miscellaneous
This section includes the monitoring and security systems of the substation.
Monitoring system: there is only one SCADA system for the whole substation. It is connected by
multimode fiber optics cables to all the power transformers. SCADA is the control and
monitoring system of the substation.
This section presents the elements of the switching and braking station in the bill of materials,
the following elements follow the order of the file.
Input feeder MV cubicle: Total number of input feeder cubicles in the station.
Output feeder MV cubicle: The total number of output feeder cubicles in the station. The total
number is always 1.
Protection MV cubicle: The total number of the protection cubicles in the station. The total
number is always 1.
Metering MV cubicle: The total number of metering cubicles in the station. The total number is
always 1.
Auxiliary MV cubicle: The total number of auxiliary cubicles. The total number is always 1.
The civil section of the switching and breaking station consists of the total number of stations.
The total number is always 1 station for each PV plant.
Page 12
BOQ METHODOLOGY
The main equipment sub-section refers to the designed equipment defining the overhead line.
5.1.1 Towers
Dead-end towers: The total number of the dead end towers of the line, this number is always 2.
The entry includes the maximum and minimum heights of the dead-end towers and the name of
the tower.
Suspension towers: The total number of the suspension towers of the line. The entry includes
the maximum and minimum heights of the line’s suspension towers and the name of the tower.
Angle towers :The total number of the angle towers of the line. The entry includes the
maximum and minimum heights of the line’s angle towers and the name of the tower.
5.1.2 Conductors
Phase conductor: the total length of the phase conductor in meters considering the number of
phases and the number of conductors per bundle. The entry also includes the designation of the
conductor and its cross-section.
Earth wire: the total length of the earth wire in meters considering the number of earth wires in
the line. The entry also includes the designation of the earth wire and its cross-section.
5.1.3 Insulators
Suspension insulator: the total number of suspension insulators in the line considering the
number of insulator sets per phase. The entry also includes the designation of the insulator and
its lightning impulse.
Tension insulator: the total number of tension insulators in the line considering the number of
insulator sets per phase. The entry also includes the designation of the insulator and its lightning
impulse.
Page 13
BOQ METHODOLOGY
5.2 Miscellaneous
Danger plates: the total number of electrical danger plates. Each tower is considered having two
danger plates.
Tower plates: the total number of the line’s informative plates that is calculated as one plate per
tower.