BCA - 17UBC4A4 Computer Based Optimization Techniques
BCA - 17UBC4A4 Computer Based Optimization Techniques
UNIT-1
4. Minimize Z = ______________
A. one of the constraint is redundant B. objective function is parallel to one of the constraints
10. Linear programming problem involving only two variables can be solved by
______________
UNIT-2
11. From the following methods ___________ is a method to obtain initial solution to
Transportation Problem.
12. The Penalty in VAM represents difference between _________ cost of respective row /
column.
13. Number of basic allocation in any row or column in Assignment Problem can be
A. top left corner B. top right corner C. both of them D. none of them
15. The ______________ method's solution for transportation problem is sometimes an optimal
solution itself.
16.If number of sources is not equal to number of destination in Assignment problem then it is
called ___________.
17. The _____ method used to obtain optimum solution of travelling salesman problem.
A. reduced matrix method B. MODI method C. Hungarian method D. none of the above
UNIT-3
21.EOQ means_____________
23. In____________, economic order quantity (EOQ) is the order quantity that minimizes the
total holding costs and ordering costs
24. There are __________types of costs that must be considered in setting inventorylevels
A.statisfy demand during period of replenishment B.carry reserve stocks to avoid shortage
28. if small orders are placed frequently (rather then placing large orders infrequently), then
total inventory cost is
A. unit cost only B. holding cost only C. re-order cost only D. all of the above
UNIT-4
33.A sequencing problem involving six jobs and three machines requires evaluatioin of
A. (6!+6!+6!) sequences
B.(6!)3 sequences
C.(6*6*6) sequences
D. (6+6+6)sequences
34. The general assumption which is not correct in solving a sequencing problem is that:
A. the time taken by different jobs in moving from one machine to another is negligible.
B. the processing times on various machines are independent of the order in which different jobs
are processed on them.
C. a job once started on a machine would be performed to the point of completion uninterrupted.
D. a machine can process more than one job at a given point of time.
36. In ‘n’ jobs and two machine (say A and B ) sequencing problems in which the order of
processing is AB
A. job having minimum time on machine B is processes first.
B. job having minimum time on machine A is processed last.
C. job having minimum time on machine B is processed in the last.
D. job having maximum time on machine B is processed in the last
37. ------------- time take a considerable amount of time to transport the items from one facility
to another.
A. Transportation
B. Maintenance crew
C. sequencing
D. processing
38.A machine may break down and operator may be absent or injured at work.
A. Machine breakdown
B. machine shortages
C. Expediting
D. overlap
UNIT-5
48. The time by which activity completion time can be delayed without affecting the start of
succeeding activities, is known as
A. duration
B. total flat
C. free float
D. interfering float.
49. For completion of a project, the critical path of the network represents
A. minimum time
B. maximum time
C. maximum cost
D. minimum cost.
50. In a certain project an activity C can only be started when activities A and B have been
completed, which have no bearing on each other and can be started independently. The correct
network for the activities, is
A. Activities A and B can be started independently
B. Activity C can be started only on completion of activity A
C. Activity D can be started only on completion of activity
D. all the above
KEY ANSWERS:
1.B 2.C 3.D 4.C 5.D 6.B 7.A 8.C 9.B 10.C
11.A 12.B 13.A 14.A 15.B 16.C 17.B 18.A 19.B 20.C
21.A 22.C 23.A 24.A 25.B 26.B 27.D 28.C 29.A 30.D
31.A 32.D 33.B 34.D 35.A 36.C 37.A 38.A 39.A 40. C
41.D 42.D 43.D 44.C 45.C 46.D 47.C 48.C 49.A 50.D
U.G. Department of Computer Applications
K3-Level Questions
1. Use the graphical method to solve the following LPP:
Minimize z = -x1 + 2x2 subject to the constraints:
-x1 + 3x2 ≤ 10, x1 + x2 ≤ 6, x1 - x2 ≤ 2 and x1 ≥ 0, x2 ≥ 0.
2. Rewrite in standard form the following LPP:
Minimize z = 2x1 + x2 + 4x3 subject to the constraints:
-2x1 + 4x2 ≤ 4, x1 + 2x2 + x3 ≥ 5, 2x1 + 3x3 ≤ 2, x1, x2 ≥ 0 and x3 unrestricted in sign.
3. Explain the advantages of linear program problem.
5. Obtain an initial basic feasible solution to the following T.P. using the matrix minima
method:
D1 D2 D3 D4 Capacity
O1 1 2 3 4 6
O2 4 3 2 0 8
O3 0 2 2 1 10
Demand 4 6 8 6
th th
where Oi and Dj denote i origin and j destination respectively.
6. Solve the assignment problem using Hungarian method. In this problem, 5 different jobs are to
be assigned to 5 different operators such that the total processing time is minimized. The matrix
entries represent processing times in hours. Find total processing time.
Operator
1 2 3 4 5
1 10 12 15 12 8
Job
2 7 16 14 14 11
3 13 14 7 9 9
4 12 10 11 13 10
5 8 13 15 11 15
7. Use Vogel’s approximation method to obtain an initial basic feasible solution
of the transportation problem
Distribution Supply
2 3 11 7 6
Sources 1 0 6 1 1
5 8 15 9 10
Demand 7 5 3 2
13. Determine the optimal sequence of jobs that minimizes the total elapsed time based on the
following information. Processing time on machines is given in hours and passing is not allowed:
Job: A B C D E F G
Machine M1: 3 8 7 4 9 8 7
Machine M2: 4 3 2 5 1 4 3
Machine M3: 6 7 5 11 5 6 12
14. Solve the sequencing problem when passing out is not allowed:
Machine (Processing time in hours)
Item
A B C D
I 15 5 4 15
II 12 2 10 12
III 16 3 5 16
IV 17 3 4 17
15. There are five jobs, each of which is to be processed through two machines
M1,M2 in the order M1,M2 processing hours are as follows:
Job 1 2 3 4 5
Machine A 3 8 5 7 4
Machine B 4 10 6 5 8
Determine the optimum sequence for the jobs, and minimum elapsed time.
Also, find the idle time of machines A and B.
16. Use graphical method to minimize the time need to process the following jobs
on the machines shown below, that is, for each machine find the job which
should be done first. Also, calculate the total time needed to complete both
the jobs.
Sequence of machines A B C D E
Job 1 Time (in hrs) 2 3 4 6 2
Sequence of machines C A D E B
Job 2 Time (in hrs) 4 5 3 2 6
K4-Level Questions.
1.Use simplex method to solve the following LPP:
Maximize z = 4x1 + 10x2 subject to the constraints:
2x1 + x2 ≤ 50, 2x1 + 5x2 ≤ 100, 2x1 + 3x2 ≤ 90 and x1 ≥ 0, x2 ≥ 0.
2. Consider the following LP model and solve it by using Big M method.
Minimize z = 2x1 + 3x2 subject to the constraints:
x1 + x2 ≥ 6, 7x1 + x2 ≥ 14 and x1 ≥ 0, x2 ≥ 0.
9.A company operating 50 weeks in a year is concerned about its stocks of copper cable. This
costs Rs. 240 a metre and there is a demand for 8,000 metres a week. Each replenishment costs
Rs. 1,050 for administration and Rs. 1,650 for delivery, while holding costs are estimated at 25
per cent of value held a year. Assuming no shortages are allowed, what is the optimal inventory
policy for the company? How would this analysis differ if the company wanted to maximize
profit rather than minimize cost? What is the gross profit if the company sells cable for Rs. 360 a
metre?
10. The demand for an item in a company is 18,000 units per year, and the company can produce
the items at a rate of 3,000 per month. The cost of one set-up is Rs. 500 and the holding cost of 1
unit per month is 15 paise. The shortage cost of one unit is Rs. 20 per month. Determine
i) Optimum production batch quantity and the number of strategies.
ii) Optimum cycle time and production time
iii) Maximum inventory level in the cycle
iv) Total associated cost per year if the cost of the item is Rs. 20 per unit.
11. The production department for a company requires 3,600 kg of raw material for
manufacturing a particular item per year. It has been estimated that cost of placing an order
is Rs.36 and the cost of carrying inventory is 25 per cent of the investment in the
inventories. The price is Rs.10 per Kg. The purchase manager wishes to determine an
ordering policy for the raw material.
12. A company operating 50 weeks in a year is concerned about its stocks of copper cable.
This costs Rs.240 a meter and there is a demand for 8,000 meters a week. Each
replenishment costs Rs.1,050 for administration and Rs.1,650 for delivery, while holding
costs are estimated at 25 per cent of value held a year. Assuming no shortages are
allowed, what is the optimal inventory policy for the company?
13. In a factory, there are six jobs to perform, each of which should go through two machines A
and B, in the order A, B. The processing timings (in hours) for the jobs are given here. You are
required to determine the sequence for performing the jobs that would minimize the total elapsed
time, T. What is the value of T?
Job: J1 J2 J3 J4 J5 J6
Machine A: 1 3 8 5 6 3
Machine B: 5 6 3 2 2 10
14. Using graphical method, calculate the minimum time needed to process job 1 and 2 on five
machines A, B, C, D and E, i.e., for each machine find the job which should be done first. Also
calculate the total time needed to complete both jobs.
Machines
Sequence: A B C D E
Job 1
Time (hours): 6 8 4 12 4
Sequence: B C A D E
Job 2
Time (hours): 10 8 6 4 12
15. Four jobs 1, 2, 3 and 4 are to be processed on each of the four machines A, B, C and D in
the order ABCD. The processing time in minutes are given in table. Find for no passing,
the minimum elapsed time.
machine/job A B C D
1 58 14 14 48
2 30 10 18 32
3 28 12 16 44
4 64 16 12 42
16. We have 4 jobs each of which has to go through the machines Mj (j=1, 2, ….,6) in the
order M1,M2,….. M6. Processing time (in hours) is given below:
Machines
M1 M2 M3 M4 M5 M6
Job A 18 8 7 2 10 25
Job B 17 6 9 6 8 19
Job C 11 5 8 5 7 15
Job D 20 4 3 4 8 12
17. A small project consists of seven activities for which the relevant data are given below:
Activity Preceding Activity Activity Duration (Days)
A - 4
B - 7
C - 6
D A,B 5
E A,B 7
F C,D,E 6
G C,D,E 5
20. Three time estimates (in months) of all activities of a project are as given below:
Activity : 1-2 2-3 2-4 3-4 4-5 5-6
a : 0.8 3.7 6.2 2.1 0.8 0.9
m : 1 5.6 6.6 2.7 3.4 3.4
b : 1.2 9.9 15.4 6.1 3.6 2.7