Chapter 4 - Traffic Signal Design
Chapter 4 - Traffic Signal Design
1
MUTCD, FHWA, 2003, p. 4B-1.
TRAFFIC DESIGN MANUAL 4-1 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
move traffic without compromising safety. The design and operation of traffic
signals shall take into consideration the needs of pedestrians as well as vehicular
traffic.2 The following design criteria set forth TDOT’s application of the traffic
signal design standards given in the MUTCD.
The key decisions affecting a traffic signal system design include:
Intersection geometrics (lanes, sight distance, grade, etc.)
Determination of traffic signal operational mode
Selection of left turn treatments
Selection of the traffic signal phasing plan
Determination of detection needs
Development of traffic signal timing parameters
Development of the timing plan(s) for arterial coordination
Determination of preemption needs
Location and configuration of all traffic signal displays
Location and configuration of the controller and cabinet
Selection of type and location of traffic signal support poles
Determination of necessary traffic signing
Location of stop lines and crosswalks
Determination of wiring, conduit and pull box needs
Future Intersection Expansion – Any planned or anticipated intersection
improvements or future phasing needs should be considered. The traffic signal
controller type, cabinet type, pole design and traffic signal cable are examples of
design features that may be affected by future improvements.
4.1.1 Intersection Geometrics – Intersection geometrics play a pivotal role in
designing a traffic signal. In particular, geometrics play just as important a
role as traffic volumes in evaluating turn phasing. For example, left turns
may be made from shared lanes yielding to the opposing thru traffic;
however, the capacity of a shared lane is somewhat limited. The Highway
Capacity Manual provides a procedure for assessing the capacity of both
shared and exclusive lanes under traffic signal control. The operational
advantage of an exclusive lane should be clear from a capacity
perspective. Exclusive left turn lanes are normally required when
protected left turn movements are provided in the traffic signal phasing.
When left turning volumes are high, multiple exclusive left turn lanes may
be required to provide adequate capacity. Dual left turn lanes should be
considered when a capacity analysis suggests that overall intersection
performance could be improved. Proper attention must be paid to
accommodating traffic in multiple left turn lanes as it leaves the
intersection. The exit roadway must have enough lanes to accommodate
the left turns and pedestrian crosswalks should be clearly marked.
Pedestrian signals should always be used for any crosswalk in which
pedestrians will encounter protected left turns.
4.1.2 Traffic Signal Movements – A typical four-leg intersection can have up to
eight separate movements requiring traffic signal phases (four thru and
four left turns). If right turn movements are signalized separately, they are
usually operated in conjunction with a protected side street left turn
2
MUTCD, FHWA, 2003, p. 4D-2.
TRAFFIC DESIGN MANUAL 4-2 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
movement and operated as an overlap Four phase cabinets
(concurrently with another phase). Four-leg should be used for
intersections can be operated with between intersections with 2
two and eight phases. Two phase operation to 4 phases and
would only provide phases for the two crossing eight phase cabinets
movements, while the eight phase operation should be used for
would provide separate phases for each those with 5 to 8.
movement. An intersection with two to four
vehicle phases should use a four phase cabinet facility. An intersection
with five to eight vehicle phases should use an eight phase cabinet facility.
Newer controllers allow up to 16 phases, but more than eight phases are
only used in unusual situations, such as running two intersections from
one controller or complex interchanges.
4.1.3 Traffic Signal Mode of Operation – A Traffic signals can operate
traffic signal may operate under two as an independent
basic modes of operation. It may intersection or as part of a
operate as a fixed time signal, in which coordinated system. The
basic timing intervals are constant, or traffic signals can be set up
as an actuated signal, where many of to operate in the fully or
the timing intervals are variable based semi-actuated mode, in
on demand. fixed time mode, or in a
Traffic signals may be operated as flashing mode of operation.
independent (or isolated intersections) How a signal is operated
or as part of a coordinated signal determines its effectiveness
system. Coordinated traffic signal in reducing delay and
systems are designed to minimize increasing safety. Signal
delay. An individual intersection operation also influences
operates most efficiently when it is public acceptance.
allowed to respond to traffic demand in
an actuated mode. Actuated operation allows the traffic signal to adjust
the cycle length and phase split times on a cycle-by-cycle basis. At all
intersections, vehicles tend to group into "platoons." Once a platoon is
established, delay can be reduced by keeping the platoon moving through
adjacent signals. The coordination of traffic signals (operating more than
one signal in a system) can provide smooth progression along an arterial.
Operating traffic signals in a coordinated mode does have some
drawbacks. The coordination of the system may further delay some minor
traffic movements.
4.1.4 Pre-Timed (Fixed Time) Operation – Pre- Pre-timed two-phase
timed operation is an infrequently used mode operation is often
of operation (except in downtown areas) in used in a central
which a traffic signal operates in a non- business district, but
actuated mode (no vehicle detectors) and in is infrequently used
which both the timing and phasing do not vary on major streets.
from cycle to cycle (see Figure 4.1).
Advantages to pre-timed operation include:
1. Simplicity of equipment
2. Easy to coordinate along a route or in a grid (like a CBD)
TRAFFIC DESIGN MANUAL 4-3 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
/ 4 O/ 3
O
/1
O /2
O /3
O /4
O
/2
O
/1
O
/1
O
/2
O LEGEND: VEHICLE MOVEMENT
PEDESTRIAN MOVEMENT
/ 3 O/ 4
O
FOUR-PHASE
PHASE 1 SPLIT
ALL
GREEN YEL. RED RED
PHASE 2 SPLIT
ALL
RED GREEN YEL. RED RED
PHASE 3 SPLIT
ALL
RED GREEN YEL. RED RED
PHASE 4 SPLIT
ALL
RED GREEN YEL. RED
/1
O /2
O /3
O /4
O
/2
O
/1
O
/1
O
/2
O LEGEND: VEHICLE MOVEMENT
PEDESTRIAN MOVEMENT
/ 3 O/ 4
O
* EACH GREEN INTERVAL VARIABLE FROM:
ALL
GREEN YEL. RED
RED
VARIABLE *
ALL
RED GREEN YEL. RED RED
VARIABLE *
ALL
RED GREEN YEL. RED RED
VARIABLE *
ALL
RED GREEN YEL. RED
4.1.8 Mode During System Control – Many fully-actuated traffic signals that
are in signal systems operate as both fully-actuated and semi-actuated
traffic signals. They can be fully-actuated during off peak hours when the
system may not running and all intersections to run free, but operate as
semi-actuated traffic signals when the system is running.
4.1.9 Dual Ring Controller Operation – A traffic actuated controller typically
employs a “dual ring concurrent” timing process. This concept is
illustrated in Figure 4.3. A dual-ring controller uses eight phases, each of
which controls a single traffic movement. The eight phases are required to
accommodate the eight movements (four thru and four left turns) at an
intersection. Any movements that do not have a separate protected
movement are not assigned phases and not used. Phases 1 through 4
are included in ring 1, and phases 5 through 8 are included in ring 2. The
two rings operate independently, except that their control must cross the
“barrier” at the same time.
The dual-ring concurrent
To avoid conflicts, all of the movements
operation of an isolated
from one street must be assigned to one
actuated traffic signal
side of the barrier. Similarly, all
can be the most efficient
movements from the other street must be
method of operation.
assigned to the other side. On both sides
of the barrier there are four phases (two thru and two left). One phase
from ring 1 and one phase from ring 2 may operate concurrently, however
the concurrent phases must be on the same side of the barrier (see Figure
4.3). Simultaneous phase operation in each ring is not permitted.
As an example, if phase 2 (in ring 1) is the EB thru movement, it may be
displayed concurrently with either phase 5 (EB left turn) or phase 6 (WB
thru), both of which are in ring 2. However, phase 2 can never be
displayed concurrently with any of the phases across the barrier (phases
3, 4, 7 or 8 – all side street phases). Any allowed combination of phases
may be skipped if there is no demand for that movement.
Four phase operation can be achieved using a dual ring controller by only
using phases 1-4. This type of controller can be used for pre-timed, semi-
actuated or fully-actuated operation. The majority of signalized
intersections now employ dual-ring traffic actuated controllers conforming
to NEMA standards. Eight phase dual-ring controllers are typically used in
all new installations.
/1
O /2
O /3
O /4
O
RING 1
(PHASES 1-4)
/5
O /6
O /7
O /8
O
RING 2
(PHASES 5-8)
/2
O
ANY STEP MAY BE SKIPPED
/4
O
IF NOT ON RECALL AND NO DEMAND
/5
O /7
O
/1
O /2
O /3
O /4
O
OR OR
/5
O /6
O /7
O /8
O
/1
O /3
O
/6
O /8
O
TIME
If the need for left turn phasing on an intersection approach has been
established, the guidelines in Section 4.2.3 should be used to select the type of
left turn phasing to provide. Care should be taken to avoid a “yellow trap” which
can occur in some combinations of the type and sequence of left turn movements
(see Section 4.2.5).
4.2.1 Need for Left Turn Protection – The primary factors to consider in the
need for protection are the left turn volume and the degree of difficulty in
executing the left turn through the opposing
traffic. The designer should be aware that The designer’s goal
left turn phases can sometimes significantly should be to
reduce the efficiency of an intersection. Left accommodate left turn
turn phasing should be considered on an movements adequately
approach with a peak hour left turn volume and safely while
of at least 100 vehicles and a capacity delaying the heavier
analysis showing that the overall operations thru traffic movements
are improved by the addition of the left turn as little as possible.
phase.
4.2.2 Left Turn Phase Warrants – The following warrants may be used in the
analysis of the need for the installation of separate left turn phases.
4.2.3 Types of Left Turn Phasing – Three general types of left turn phasing
are possible. Figure 4.4 displays the signal heads for various types of left
turn phasing.
A. Permissive Only Left Turn Mode – Left turns are allowed only
concurrently with the adjacent thru movement and must yield to
opposing traffic.
B. Protected/Permissive Left Turn Mode – This is the most common
and generally most efficient type of left turn operation. It allows left
turns to be made both on the left turn GREEN ARROW (when they
are protected) and on the CIRCULAR GREEN signal indication
(when they are permitted, but must yield to opposing traffic). It
should be considered when any of the following conditions exist:
Capacity – where intersection The preferred phasing
capacity is limited and method is protected/
maximum efficiency of the permissive unless one of
traffic operations is needed. the conditions exists
Left Turn Storage – where requiring protected only
left turn lanes are not present left turn phasing. It is
or left turn lanes are of generally more efficient
inadequate length to store the than protected only left
actual left turn traffic volumes. turn phasing.
Left Turn Accidents – where the left turn signal phase is not
justified by the left turn accident warrant described in Section
4.2.2.
3
Manual of Traffic Signal Design, ITE, 1998, p.32
4
Ibid. p. 32-33
TRAFFIC DESIGN MANUAL 4-11 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
LEFT TURN SIGNAL DISPLAYS
LEFT LEFT ON
GREEN
TURN ARROW
PROTECTED ONLY MODE SIGNAL
(ONE PER LEFT TURN LANE) OR ONLY
LEFT TURN
YIELD
ON GREEN
PROTECTED/
PERMISSIVE MODE
(SIGN OPTIONAL)
RIGHT RIGHT ON
GREEN
TURN ARROW
PROTECTED ONLY MODE SIGNAL
(ONE PER LEFT TURN LANE) OR ONLY
PROTECTED/ NO SIGN
PERMISSIVE MODE
5
Traffic Engineering Handbook, ITE, 1999, p. 477
6
Ibid.
TRAFFIC DESIGN MANUAL 4-13 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
SIGHT DISTANCE
7
Traffic Control Devices Handbook, ITE, 2001, p. 274
8
Traffic Engineering Handbook, ITE, 1999, p. 480.
TRAFFIC DESIGN MANUAL 4-15 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
Y
G
LEAD
Y
G
LEAD
LEFT
TURN
R
LEAD
SIGNAL
Y
G
OR
R
Y
SIMULTANEOUS LEADING LEFT-TURNS
G
WITH PROTECTED ONLY OPERATION
LEFT
TURN
R
SIGNAL
Y
LAG
G
OR
R
Y
SIMULTANEOUS LAGGING LEFT-TURNS
G
WITH PROTECTED ONLY OPERATION
R R
Y Y
G G
G G
LEAD LAG
SPLIT-PHASE LEFT-TURNS
Tennessee Department of Transportation
Traffic Design Manual
Typical Protected
Left Turn Sequencing Figure 4.7
C. Lagging Left Turn – This is a left Lagging left turn
turn signal phase that comes at the movements should be
end of the thru green phase. This used cautiously. They
type of sequence is not normally are not normally
expected by drivers. expected by drivers
and can lead to a
A “yellow trap” can occur when a “yellow trap” in certain
traffic signal controller with a situations.
protected/ permissive or protected
only lagging left turn initiates its lagging left turn phase (see Figure
4.8). The opposing left turn movement can experience a “yellow
trap” (see Section 4.2.5). For these reasons, this phasing sequence
is not recommended. Single lagging left turns should only be used
if the leading left turn movement is prohibited or is at a T-
intersection. Simultaneous lagging left turns should only be used if
they are protected only phases (see Figure 4.7)
OR
9
Traffic Engineering Handbook, ITE, 1999, p. 479
10
Ibid.
TRAFFIC DESIGN MANUAL 4-20 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
4.2.6 Right Turn Indication11 – Typical right turn Separate right turn
signal heads are shown in Figure 4.4.Separate signal indications
phasing is typically not defined for right turns, are typically used
but two types of indications may control right only when a
turning movements. Three parameters define separate right turn
the right turn treatment for each approach: lane exists.
Lane utilization (shared, exclusive or channelized)
Right turn on red (allowed or prohibited)
Right turn movement protection (permissive, protected or both)
11
MUTCD, FHWA, 2003. p. 4D-7.
TRAFFIC DESIGN MANUAL 4-21 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
N
/ 6 O/ 1
O
MINOR ST /
O 8
/
O 7 / 3
O
/
O 4
MAJOR ST
/ 5 O/ 2
O
NORTH-SOUTH AS
MAJOR STREET
FOR 8-PHASE CONTROLLER
N
/ 4 O/ 7
O
MAJOR ST /6
O
/5
O
/1
O
/2
O
MINOR ST
/ 3 O/ 8
O
EAST-WEST AS
MAJOR STREET
FOR 8-PHASE CONTROLLER
1
OL
O
/ MINOR ST
/4
MAJOR ST
O
MAJOR ST
/
O
4
MINOR ST
1
OL
O
/
/2
O
N
N
MINOR ST
MAJOR ST
OL
/
O 1
/2
O
/4
O
/4
O
/2
O
/1
O
MINOR ST
OL MAJOR ST
4.3.1 Locking vs. Non-Locking Memory – Traffic signal controllers have three
modes for detection memory: lock, non-lock and recall.
Protected/Permissive or Permissive
Left Turn Lane Stop Line Non-Locking
Only Phasing
Non-Locking (typical) or
Thru Lane Stop Line Thru Phase (On Recall)
Locking**
Protected/Permissive or Permissive
Right Turn Lane Stop Line Non-Locking
Only Phasing
* Consider using delay features on loop detector units to prevent cross traffic from placing a
vehicle call to the controller.
** Consider using delay features on loop detector units on side street combination thru/right turn
lanes where vehicles may turn right on red.
TO TRAFFIC SIGNAL
DETECTION AREAS
DETECTION AREAS
IN LOCKING MODE
2
X = SSD = rV + 0.5V /d
Some models transmit data over wireless RF link. Decreases pavement life.
Magnetometer Installation and maintenance require lane closure.
Small detection zones.
Can be used where loops are not feasible (e.g., Installation requires pavement cut or tunneling under
bridge decks). roadway.
Some models installed under roadway without need Cannot detect stopped vehicles.
Magnetic
for pavement cuts.
Less susceptible than loops to stresses of traffic.
Generally insensitive to inclement weather. Antenna beamwidth and transmitted waveform must
be suitable for the application.
Microwave Radar Direct measurement of speed.
Multiple lane operation available.
Active sensor transmits multiple beams for accurate Operation of active sensor may be affected by fog or
measurement of vehicle position, speed, and class. blowing snow.
Infrared Multizone passive sensors measure speed. Passive sensor may have reduced sensitivity to
vehicles in its field of view in rain and fog.
Multiple lane operation available.
Multiple lane operation available. Some conditions such as temperature change and
extreme air turbulence can affect performance.
Ultrasonic Large pulse repetition periods may degrade
occupancy measurement
Passive detection. Cold temperatures have been reported as affecting
data accuracy.
Insensitive to precipitation. Specific models are not recommended with slow
Acoustic
moving vehicles in stop and go traffic.
Multiple lane operation available.
Monitors multiple lanes and multiple zones/lane. Inclement weather, shadows, vehicle projection into
adjacent lanes, occlusion, day-to-night transition,
vehicle/road contrast, and water, salt grime, icicles, and
cobwebs on camera lens can affect performance.
Easy to add and modify detection zones. Requires 50- to 60-ft camera mounting height (in a
side-mounting configura-tion) for optimum presence
Video Image
detection and speed measurement.
Processor
Rich array of data available. Some models susceptible to camera motion caused
by strong winds.
Provides wide-area detection when information Generally cost-effective only if many detection zones
gathered at one camera location can be linked to are required within the field of view of the camera.
another.
Source: A Summary of Vehicle Detection and Surveillance Technologies used in Intelligent Transportation Systems, FHWA, 2000.
2 WIRES
4 WIRES 1 6’ TYP
PRESENCE
2 WIRES
ADVANCE LOOP SPACING 6’ TYP
APPROACH DISTANCE TO
6’ TYP 2
SPEED (MPH) STOP LINE (FT) THRU PHASE ON
35 185’ MIN RECALL OR ON
LOCKING MEMORY
40 230’
45 285’ 6” MIN
50 340’
2 OR 3
55 405’ SHIELDED CABLE(S)
60 475’ IN CONDUIT
PULL BOX
TO POLE BASE OR
SEE ADVANCE CONTROLLER CABINET
LOOP SPACING
CHART
2 WIRES
4 WIRES 1 6’ TYP
PRESENCE
2 WIRES
6’ TYP 15-20’ TYP
PRESENCE
2
PULL BOX
SHIELDED CABLE(S)
30 MPH OR LESS IN CONDUIT
TO POLE BASE OR
CONTROLLER CABINET
TEE TEES
EDGE OF
PAVEMENT
PREFORMED LOOP
CROSS-LINKED
POLYETHYLENE MATERIAL PREFORMED
QUADRAUPOLE
LOOP WIRE LOOP
TURNS
5/8”
PREFORMED LOOP
CROSS SECTION
4” TYP.
. .
. . . .
. . . .
. . . . .
. ..
. . . .
. .
. . . .
3” MIN.
. . .
.
. .
SURFACE COURSE
. . . . .
. . .
.. . .
. . . ASPHALT LAYERS
PREFORMED
LOOP SUPPORT PREFORMED
WITH CHAIR LOOP
DETECTION ZONES
10’ (PRESENCE DETECTION)
15’
CAMERA MOUNTING
BRACKET
STAINLESS STEEL
BANDING
VIDEO CABLE
DRIP LOOP
CAMERA
30 O
DETECTION
ZONES
4.4 Pedestrian Signal Interval – Pedestrian intervals are signal timing features
activated by pedestrian pushbuttons or internally generated recalls which allow
pedestrians to receive pedestrian signal displays and/or adequate signal time to
aid in crossing the street. Pedestrian phase timing parameters are detailed in
Section 4.5.7 and the pedestrian signal head requirements are discussed in
Section 4.9.11. Pedestrians are better controlled by pedestrian signal faces
rather than vehicular signal faces, therefore pedestrian signal heads should be
installed at any new intersections where pedestrian phasing is provided.
CROSS
ON CROSS
TO CROSS
ONLY
GREEN STREET ON
LIGHT PUSH BUTTON
WAIT FOR
ONLY GREEN LIGHT SIGNAL
TO CROSS TO CROSS
PUSH BUTTON PUSH BUTTON
Requirements for locations with and without pedestrian signal heads and
pushbuttons are listed in Table 4.3. The various signs required for the
different pedestrian actuation and indication scenarios are shown in Figure
4.17.
17
MUTCD, FHWA, 2003, p. 4E-6.
TRAFFIC DESIGN MANUAL 4-40 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
Table 4.3 Pedestrian Signal Head and Pushbutton Needs
Pedestrian Pedestrian
Requirements
Signal Heads Pushbuttons
Pedestrians use Vehicle Signals to cross
street
Recall for Vehicle Phases with concurrent
Pedestrian Movements
NOT
NO NO Minimum Green time for Vehicle Phases RECOMMEDED
must be greater than required Walk and
Pedestrian Clearance
18
“Accessible Pedestrian Signals”, U.S. Access Board, 1998.
19
MUTCD, FHWA, 2003, p. 4E-3.
20
Ibid, p. 4E-4.
TRAFFIC DESIGN MANUAL 4-42 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
ҏ4.4.5.1 Accessible WALK Indications – An accessible pedestrian signal
typically includes a signal device that provides either audible
indications or vibrotactile indications of the Walk Interval.
A. Audible Conformation – Audible pedestrian signal devices
supplement visual WALK indications and are designed to aid
visually impaired pedestrians. When verbal messages are
used to communicate the pedestrian interval, they provide a
message that the Walk Interval is in effect, as well as to
which crossing it applies. The verbal message is provided at
regular intervals throughout the timing of the Walk Interval.
B. Vibrotactile Confirmation – A vibrotactile pedestrian device
communicates information about pedestrian timing through a
vibrating surface by touch. Vibrotactile pedestrian devices
indicate that the Walk Interval is in effect, and for which
direction it applies, through the use of a vibrating directional
arrow or some other means. They are located adjacent to
the pushbutton.
5’ MAX.
SPAN WIRE
5’ MAX.
10’ MAX. (2’ MIN.)
.
IN
’M
10
CORNER WITH TWO RAMPS
LEGEND:
10
PUSHBUTTON
10’ MAX. (2’ MIN.) PEDESTRIAN PUSHBUTTON POST
WITH PUSHBUTTON
Preset Timing Intervals – phase timing intervals that are fixed and do
not change.
Fixed Time Plan – based on a fixed cycle length (see Figure 4.1 for
basic fixed time cycle schematic). Multiple timing plans may be
needed for different time periods.
4.5.2 Preset Timing Intervals – All traffic signal controllers have some preset
timing intervals. In non-actuated (pre-timed) control, all intervals are
preset. In semi-actuated or fully-actuated control, some intervals are also
preset and some are variable. Preset intervals found in both pre-timed
and actuated control include the following:
21
Traffic Control Devices Handbook, ITE, 2001, p. 352
TRAFFIC DESIGN MANUAL 4-45 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
cycle to cycle. In addition to the intervals listed in Section 4.5.2, the basic
timing parameters for a pre-timed controller are:
Cycle Length
Green Intervals (Splits) – Maximum Green on Recall
Number of Timing Plans
The total TVE left turn volume is then subtracted from the
inside (left) shared lane volume to determine the actual
number of thru vehicles in that lane. This actual number
of thru vehicles is added to the actual left turn volume
and assigned to the shared inside (left) lane. The actual
remaining traffic is then distributed equally to the
remaining approach lanes. The highest lane volume for
this approach is the critical lane volume for the approach.
Equation 4.1 22
1.5L 5
Optimal Cycle Length (C) =
1.0 ¦Yi
22
Northwestern University Traffic Institute, Traffic Actuated Control Workshop, November 2001.
TRAFFIC DESIGN MANUAL 4-47 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
4.5.3.3 Movement Timing – With solid state equipment the green time
for each phase is set on Maximum Recall because of the lack of
signal detection. This setting for each phase is based on the
average needs for that particular movement as determined by
traffic counts. Ideally, it should be long enough to service all the
vehicles and pedestrians accumulated during the Change
Interval.23 Two methods of calculating the Maximum Green time are
as follow:
ªV A º
G «V xC » CLR
¬ T ¼
Where: G = Green Interval for phase (sec.)
V A = Critical lane volume for phase (veh/hr.)
VT = Sum of critical lane volumes for all phases (veh/hr.)
C = Cycle Length
CLR = Clearance Interval for phase (sec.)
Minimum Green
Passage Time
Maximum Green
23
Traffic Engineering Handbook, ITE, 1999, p. 480
24
Northwestern University Traffic Institute, Traffic Actuated Control Workshop, November 2001.
TRAFFIC DESIGN MANUAL 4-48 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
Approach with Advance Detection Only – When an approach
has only advance detection, the Minimum Green shall be the
amount of time required to clear the stored vehicles between the
stop line and the detectors (see Section 4.5.3.3 for equation to
determine Minimum Green for advance detection).
Typical Passage Times are 2.0 to 3.0 seconds for stop bar loops,
with longer times for advance loops (3.5 to 6.0 seconds).
25
Manual of Traffic Signal Design, ITE,1998, p. 152
TRAFFIC DESIGN MANUAL 4-49 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
MAXIMUM GREEN
PASSAGE TIME OR
VEHICLE EXTENSION
(FIXED)
CONSTANT
MIN OR INITIAL GREEN EXTENSIONS
*
SUCCESSIVE ACTUATIONS
CONFLICTING *
CALL
DURING GREEN
*
*
*
*
TIME (SECONDS) *
*
YELLOW
*
DETECTOR ACTUATION ON
CONFLICTING PHASE
NOTE - IN THIS SCHEMATIC, THERE IS A DEMAND FOR ANOTHER PHASE AND THE PHASE GAPS OUT PRIOR TO REACHING MAX GREEN.
IF ACTUATIONS CONTINUE TO MAX GREEN, THE GREEN WILL END AT MAX GREEN TIME AND YELLOW WILL BEGIN AT THAT POINT.
IF THERE IS NO DEMAND FROM ANOTHER PHASE, THIS PHASE WILL REST IN GREEN AFTER REACHING MAX.
These features are typically used for approach speeds of greater than 30
mph and provide a Variable Initial green time as well as a variable “gap”
reduction feature.
Variable Initial – This feature increases the minimum assured green time
(Minimum Initial) so it will be long enough to serve the actual number of
vehicles waiting for the green between the stop line and the detector. This
TRAFFIC DESIGN MANUAL 4-51 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
interval is generally used on phases for higher speed approaches where
the detectors are placed quite a distance from the stop line (resulting in
unacceptably long Minimum Initial requirements). This feature allows the
Minimum Initial to be set low for light volumes. Vehicles crossing the
detector when the phase is red will add time to the minimum assured
green, so that when the phase is served, the minimum assured green will
be long enough to serve the actual number of vehicles waiting for the
green (see Figure 4.20).
Equation 4.3
MI (sec.) = 3 + 2n
Where: MI = Maximum Initial
n = max number of queued vehicles per lane (from stop line
to detector), calculated as the distance from stop line to
detector divided by 25 ft/vehicle
The maximum initial can not exceed the Maximum Green time for
the phase.
26
Traffic Control Devices Handbook, ITE, 2001, p. 329
TRAFFIC DESIGN MANUAL 4-52 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
MAX. INITIAL (SETTING)
CALCULATED VARIABLE INITIAL VARIABLE INITIAL
LESS THAN MIN GREEN - (SECONDS)
USE MIN GREEN TIME AS
VARIABLE INITIAL
MIN GREEN
(SETTING)
VEHICLE ACTUATIONS
DURING YELLOW
AND RED
RANGE
Equation 4.4
MI
Added Initial (sec./act.) =
n
4.5.5.4 Variable Initial – Variable Initial timing describes the initial green
used in a volume density phase before the extendable portion of
the phase starts. If the number of actuations during the clearance
and change intervals is small and the Added Initial time calculated
for these vehicles is less than the Minimum Green, the Variable
Initial is the Minimum Green. With heavy traffic, the Added Initial
increases the initial green beyond the Minimum Green to ensure
that vehicles between the stop line and the detector can clear the
intersection.
Gap Reduction – This feature reduces the Passage Time and as a result
reduces the allowable time gap between actuations that will cause the
green to remain on that approach (see Figure 4.21). When a phase is
green, the time between vehicles to terminate that phase starts out at the
amount of time set for the Passage Time. After the phase has been green
for some time, it becomes desirable to terminate the phase on smaller
distances between vehicles. (i.e., successive actuations must be closer
together than the Passage Time to extend the green).
27
Manual of Traffic Signal Design, ITE, 1998, p. 154
TRAFFIC DESIGN MANUAL 4-54 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
MAXIMUM GREEN (SETTING)
PASSAGE TIME
SETTING GAP REDUCTION
(INITIAL PRESET GAP) OCCURRING
MINIMUM GAP
(SETTING)
VAR.
*
*
*
CONFLICTING CALL *
SUCCESSIVE ACTUATIONS
* DURING GREEN
*
*
*
LEGEND
*
PASSAGE TIME (OR VEHICLE EXT)
*
UNEXPIRED PORTIONS OF PASSAGE TIME *
OR VEHICLE EXTENSION INTERVALS
*
*
DETECTOR ACTUATION ON *
CONFLICTING PHASE
*
*
DETECTOR ACTUATION ON PHASE
WITH RIGHT OF WAY
*
YELLOW
1. IN THIS SCHEMATIC, THERE IS A DEMAND FOR ANOTHER PHASE AND THE PHASE GAPS OUT PRIOR TO REACHING MAX GREEN.
IF ACTUATIONS CONTINUE TO MAX GREEN, THE GREEN WILL END AT MAX GREEN TIME AND YELLOW WILL BEGIN AT THAT POINT.
IF THERE IS NO DEMAND FROM ANOTHER PHASE, THIS PHASE WILL REST IN GREEN AFTER REACHING MAX.
2. SEE FIGURE 4.17 FOR VARIABLE INITIAL DETERMINATION.
D
Initial Gap (Passage Time) =
V
4.5.5.7 Time to Reduce (TTR) – The Time to Reduce setting is the time
over which the Initial Gap is reduced to the Minimum Gap and
assures that the phase will not be held by large gaps in traffic. It
begins after the Time Before Reduction is timed out. During the
Time to Reduce, there is a linear reduction in the allowable gap
from the Initial Gap (Passage Time) setting to the Minimum Gap
setting.
4.5.5.10 Listed below are some basic rules for volume density timing:
Min Green > Ped Walk + Ped Clearance
Min Green < Variable Initial < Max Initial
Max Initial < Max Green
TBR + TTR < Max Green
Passage Time > Min Gap
Table 4.4 lists some recommended volume density timing values for
different approach speeds.
Distance from
Approach Minimum Maximum Added Initial Gap Time Before Time to Time to Maximum
Stop Line to
Speed Green* Initial Initial (Passage Reduction Reduce Reduce Green
Advance
(MPH) (secs) (secs) (secs) Time) (secs) (secs) (secs) (secs) (secs)
Detector (feet)
1/3 Max 1/3 Max
35 185 10 18 2.4 3.6 2.0 35-70
Green Green
1/3 Max 1/3 Max
40 230 15 21 2.3 3.9 2.0 40-80
Green Green
1/3 Max 1/3 Max
45 285 15 26 2.3 4.3 2.0 45-90
Green Green
1/3 Max 1/3 Max
50 340 20 30 2.2 4.6 2.0 50-100
Green Green
1/3 Max 1/3 Max
55 405 20 35 2.2 5.0 2.0 55-110
Green Green
1/3 Max 1/3 Max
60 475 25 41 2.2 5.4 2.0 60-120
Green Green
1/3 Max 1/3 Max
65 550 25 47 2.1 5.8 2.0 60-120
Green Green
* If pedestrians are an issue for the approach, Minimum Green must be compared against pedestrian timing requirements.
Equation 4.6 29
V (w L)
CP t
2a V
4.5.6.2 All Red Clearance Interval – The All Red timing is an optional
part of the clearance interval and immediately follows a Yellow
Change Interval. It is used to provide additional timing (beyond that
needed to stop) for a vehicle to clear the intersection before the
display of a conflicting GREEN signal indication. It is calculated
using the third term in Equation 4.6 shown above (2.5 seconds
max).
Table 4.5 Recommended Yellow Change and All Red Clearance Interval Values
For typical intersections, a walking speed between 3.0 and 4.0 feet
per second shall be used. Where the crossing is routinely used by
young children, the elderly, the physically challenged or large
groups of pedestrians, a walking speed of 3.0 feet/second is
recommended. The pedestrian clearance time for the Pedestrian
Change Interval is calculated by Equation 4.7 shown below.
Equation 4.7
W
PED CLR
VP
Where: PED CLR = Pedestrian clearance time (sec.)
W = width of the street (curb line to the far side of the
traveled roadway) (ft.)
VP = pedestrian walking speed (3.0 to 4.0 ft./sec.)
30
MUTCD, FHWA, 2003, p. 4E-8
TRAFFIC DESIGN MANUAL 4-60 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
The Pedestrian Change Interval
(pedestrian clearance time) may On high speed approaches,
be entirely contained within the or when the intersection
vehicular Green Interval operates well below
(Equation 4.8), or may utilize capacity, the preferred
the time of both the vehicular method for displaying the
Green and Yellow Change Pedestrian Change Interval
Intervals (Equation 4.9) 31 is to have the pedestrian
Figure 4.22 displays the two clearance time entirely
Pedestrian Change Interval within the vehicular Green
timing alternatives. Interval.
Equation 4.8
Minimum Green (sec.) > Ped. Walk (sec.) + Ped. Clr. (sec.)
Where: Ped. Walk = Pedestrian Walk Interval
Ped. Clr. = Pedestrian clearance time (sec.)
Equation 4.9
Minimum Green (sec.) + Yellow Change (sec.) + All Red (sec.) >
Ped. Walk (sec.) + Ped. Clr. (sec.)
Where: Ped. Walk = Pedestrian Walk Interval
Ped. Clr. = Pedestrian clearance time (sec.)
31
MUTCD, FHWA, 2003, p. 4E-9.
32
Traffic Control Devices Handbook, ITE, 2001. p. 337
TRAFFIC DESIGN MANUAL 4-61 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
VEHICLE GREEN YELLOW ALL RED
RED
FLASHING
WALK STEADY DON’T WALK
DON’T WALK
1. A plan. Federal requirements now call for any agency that implements
any kind of signal coordination or intelligent transportation system to
eventually develop a citywide or regional architecture. The city will have to
determine not only the equipment requirements, but all stakeholders
involved in the plan.
Traffic signals that are within 1/2 mile of one another should be strongly
considered for coordination.33 The type of coordination utilized may be
dependent upon the maintenance capabilities of the maintaining agency.
4.6.2 Closed Loop Signal System – The most common signal system used for
coordination today is the “closed loop”
system. This is a distributive processing, A closed loop system
traffic responsive, control and monitoring utilizes on-street master
system. Access to the system from the controllers to monitor
office is usually made through a dial-up and manage local
modem. intersection controllers.
System Detectors
Local Controller Units
Controller-Master Communications
On-Street Master Controller
Master-Central Communications
Central Computer and Windows based Software
It is better to arrive too early than too late. Vehicles arriving a little bit early
wait a lot less time than vehicles arriving late. Early arrivals can avoid
stopping by adjusting their speed. Vehicles that are a bit late are tempted
to run the yellow light or increase their speed.
The timing plan of a system consists of three elements; cycle length, splits
and offsets. The splits must be determined for each individual intersection
in the system and may vary from intersection to intersection. The split is
the segment of the cycle length allocated to each phase or interval that
may occur (expressed in percent or seconds). In an actuated controller
unit, split is the time in the cycle allocated to a phase. However, the cycle
length for each traffic signal in a system must be the same or a multiple of
Another factor in the design of the individual intersection that may become
evident during the arterial analysis is that some intersectional cycle
lengths may not be compatible with the cycle length for the system during
some timing plans. These intersections should be designed to have
flexibility to operate fully-actuated during these time periods. The same
approach should be used for traffic signals that do not have programmed
flash where most of the other traffic signals in the system flash during
nighttime hours to reduce delay and improve traffic flow along the corridor.
4.7 Preemption and Priority Control of Traffic Signals – Traffic signals may be
designed and operated to respond to certain classes of approaching vehicles by
altering the normal signal timing and
phasing plan(s) during the approach and Preemption describes the
passage of those vehicles. The alternative transfer of normal operation
plan(s) may be as simple as extending a of a traffic signal to a special
currently displayed GREEN indication or as control mode of operation.
complex as replacing the entire set of signal Preemption control is
35
phases and timing. typically given to emergency
vehicles and trains.
Typical preemption examples are:
34
Traffic Control Devices Handbook, ITE, 2001, p. 335
35
MUTCD, FHWA, 2003, p. 4D-10.
TRAFFIC DESIGN MANUAL 4-66 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
Priority control is typically given to certain
Priority control describes a
non-emergency vehicles such as buses and
means by which the
light-rail vehicles. Priority Control describes
assignment of right-of-way
a means by which the assignment of right-of-
is obtained or modified
way is obtained or modified.
usually for transit vehicles.
Typical priority control examples are:
Special phasing to assist public transit vehicles in entering the travel stream
ahead of the platoon of traffic.
Railroad preemption is by far the most important and most complex type of
preemption. It is discussed in detail in Section 4.8.
G G
R
EMERGENCY VEHICLE
R 5 PROCEEDS
R THRU INTERSECTION
R R
R
TRAFFIC SIGNAL
3 CONTROLLER STOPS
OPPOSING TRAFFIC
4.7.7 Priority Control – Priority control systems are less common than
emergency vehicle preemption systems. While a priority control system
might benefit a transit system by keeping its vehicles on a tighter
schedule, it can lead to overall increased congestion at an intersection.
Benefits to transit operations must be weighed against the possible
increased delay for passenger vehicles. Some systems, such as the
optically activated priority control system can provide both preemption for
emergency vehicles and priority control for transit vehicles.
3 8
6
2
1
5
1
2
4 7
3
LEGEND:
1 OPTICAL DETECTOR 1
1 SIREN DETECTOR 1
EXAMPLE CHART TO
BE INCLUDED IN PLANS
PREEMPTION ASSIGNMENTS
DETECTOR 1 PREEMPT 1 /2
O AND /5
O
DETECTOR 2 PREEMPT 3 /1
O AND /6
O
DETECTOR 3 PREEMPT 3 /4
O AND /7
O
DETECTOR 4 PREEMPT 4 /3
O AND /8
O
2. However, 200 feet may not be sufficient for some locations. Where
the highway-rail grade crossing is located more than 200 feet from
the traffic signal, but traffic from the signal is anticipated to back up
across the railroad tracks, preemption should be used. Calculation
of the traffic backup is determined with approximately 95% certainty
using Equation 4.10 or 4.11. The traffic back up in the thru lanes
as well as turn lanes should be checked.
36
MUTCD, FHWA, 2003, p. 8D-7.
37
Northwestern University Traffic Institute, Railroad Grade Crossing Workshop. 2003.
38
Ibid.
TRAFFIC DESIGN MANUAL 4-72 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
4.8.2 Pre-Signals – A pre-signal provides a signal display on the near side of
the track, supplementing the normal head placement. This operates as
part of the highway intersection traffic signal, controlling traffic
approaching the highway-rail grade crossing
and signalized intersection. A pre-signal is a set of
supplemental traffic
Pre-signals should be considered when: signal faces located in
a position that controls
1. The highway intersection is less than
traffic approaching the
50 feet from the highway-rail crossing
highway-rail grade
(75 feet for a road that is regularly
crossing in advance of
used by multi-unit vehicles).
the intersection.
2. Where the clear storage distance
(CSD) is greater than 75 feet and an engineering study determines
the need39.
When the design vehicle cannot be safely stored in the CSD, or if no gates
are present, a NO TURN ON RED (R10-11) shall be installed on the
approach with the pre-signal to prevent trapping a vehicle42.
39
Guidance on Traffic Control Devices at Highway-Rail Grade Crossings, FHWA, 2002, p.24.
40
Traffic Control Devices Handbook, ITE, 2001, p. 392.
41
Guidance on Traffic Control Devices at Highway-Rail Grade Crossings, FHWA, 2002, p.24.
42
MUTCD FHWA, 2003. p. 8D-7.
TRAFFIC DESIGN MANUAL 4-73 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
3 PHASE PREEMPTION SEQUENCE WITH PRE-SIGNALS
PR
EE
MP
TIO
N CLEAR TRACK PREEMPTION
GREEN (CTG) HOLD INTERVAL
CLEAR
TRACK
R3-1
R3-1
CHANGE
NORMAL PREEMPTION (CTC)
R3-2
R3-2
PHASE
SEQUENCE
ION
MPT
EE
PR
CLEAR TRACK
NORMAL CHANGE (CTC)
PHASE
R3-2
R3-2
SEQUENCE
ION
MPT
EE
PR
PREE
ON
PTI
PR
N
M
IO
EE
EM
PTIO
PT
M
R3-1
M
PRE
PT
EE
IO
PR
N
NORMAL PHASE SEQUENCE
R3-2
R3-1
R3-1
R3-2
R3-2
R3-1 EXIT TO
NORMAL
OPERATION
R3-2
PR
N
ON
PRE
IO
EE
PT
MPTI
M
EMP
M
PT
EE
IO
PR
N
PREE
TIO
N
4.8.4 Railroad Preemption Warning Timing43 – The total time to transfer right-
of-way (including Pedestrian Change Intervals) plus the queue clearance
plus the separation time is the preemption time setting. This time should
be greater than the railroad warning time (the time for the circuit to
activate warning devices in advance of the train arrival).
4.8.5 Blank Out Signs – These types of signs display a blank face unless
internally illuminated upon activation for a specific circumstance. Such
signs displaying the message/symbol “NO LEFT TURN” or “NO RIGHT
TURN” are useful as part of the railroad preemption sequence at
signalized intersections immediately adjacent to grade crossing. At these
locations, turn prohibition blank out signs can prevent traffic from turning
into and occupying the limited storage area between the tracks and
intersection and eventually blocking the intersection itself. These signs
are activated upon initiation of the railroad preemption and deactivated
after the preemption is completed.
43
Preemption of Traffic Signals At or Near Railroad Grade Crossings with Active Warning Devices, ITE, 1997. p. 15
MUST BE OPTICALLY
3A AND 8A PROGRAMMED
3 8
EXAMPLE CHART TO
BE INCLUDED IN PLANS
CLEAR TRACK PHASES: 3A & 8A PREEMPTION HOLD INTERVALS: PHASES 2 & 5, PHASES 2 & 6, PHASE 7 EXIT PREEMPTION PHASES: 3A & 8A
R3-1 AND R3-2 F.O. SIGNS ACTIVE R3-1 AND R3-2 F.O. SIGNS ACTIVE R3-1 AND R3-2 F.O. SIGNS INACTIVE
O/ 4 O/ 7 O/ 4 O/ 7 O/ 4 O/ 7 O/ 4 O/ 7 O/ 4 O/ 7
O/ 6 O/ 6 O/ 6 O/ 6 O/ 6
O/ 1 O/ 1 O/ 1 O/ 1 O/ 1
O/ 5 O/ 5 O/ 5 O/ 5 O/ 5
O/ 2 O/ 2 O/ 2 O/ 2 O/ 2
O/ 3A O/ 8A O/ 3A O/ 8A O/ 3A O/ 8A O/ 3A O/ 8A O/ 3A O/ 8A
O/ 8 O/ 8 O/ 8 O/ 8 O/ 8
4.9.1 Lens Size and Type – Twelve inch (12”) All new signal
diameter lenses are required on all new signal heads should be
heads. Today, traffic signal indications and 12” diameter lenses
pedestrian indications are usually illuminated using LED lamps.
by light emitting diode (L.E.D.) lamps.
Conventional incandescent lamps consume up to 150 watts of power and
require routine maintenance due to filament burn out. The use of LED
lamps can conserve energy and reduce maintenance costs. An LED is a
current operated, semiconductor light source. Power requirements are
considerably less than incandescent lamps. The life expectancy of an LED
lamp is 45,000 hours or 10 years of operation.
4.9.3 Backplates – Signal backplates increase the contrast between the signal
indications and the signal background. A rising or setting sun or intensive
advertising signing can lead to visibility problems. Backplates shall be
used on all rural or high speed locations or
Backplates should be
urban locations where glare or other visual
installed at all rural,
distractions are present. Where used,
high speed or visually
backplates shall have a dull black finish.
distracting locations.
44
4.9.4 Number of Signal Faces
A. Major Movement – A minimum of two signal faces are to be
provided for the major movement on each approach, even if the
major movement is a turning movement.
B. Supplemental Face – If the signal faces are more than 180 feet
beyond the stop line, a supplemental near side signal face is
required.
C. Dual (or Multiple) Left Turns – Where two or more separate left
turn lanes are provided, a separate left turn face shall be provided
for each lane.
44
MUTCD, FHWA, 2003, p. 4D–12
TRAFFIC DESIGN MANUAL 4-78 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
HORIZONTAL SIGNAL HEAD PLACEMENT
SUPPLEMENTAL NEAR
SIDE SIGNAL HEAD
MAY BE BENEFICIAL
NO OVERHEAD
SIGNALS O
40
40’ *
24
HEIGHT ABOVE ROADWAY (FEET)
23
MAXIMUM MOUNTING
22 HEIGHT OF SIGNAL HEAD
21
20
19
18
MINIMUM SIGNAL HEAD CLEARANCE
17 (TO BOTTOM OF SIGNAL HEAD)
16.5
16
15
40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59
HORIZONTAL DISTANCE FROM STOP LINE (FEET)
4.9.6 Horizontal Placement – At least one, if not both, signal faces required in
paragraph 4.9.4.A above shall be placed in the area defined in Section
4D.15 of the MUTCD (see Figure 4.28).
C. Signal Faces – Left turn signals shall be the left most signal head
and right turn signals shall be the right most signal head in the
signal head arrangement for the approach (see typical examples in
Figures 4.29 thru 4.32).
4.9.7 Vertical Placement – The placement of the signal head over the roadway
shall be such as to provide a minimum 17.5
foot vertical clearance from the bottom of the Signal heads shall be
signal head to the roadway. Where this is mounted with a
impractical, the minimum clearance shall be minimum 16.5’ (17.5’
16.5 feet. RED signal indications should be preferred) vertical
approximately the same height. clearance.
A maximum mounting height to the top of the signal housing for overhead
signals is important to ensure visibility for signal heads that are near the
stop line. The maximum mounting height shall be determined from
Section 4D.15 of the MUTCD. In general, the maximum mounting height
for signals can be determined on a sliding scale of 21 feet for signal heads
40 feet from the stop line and 25.6 feet for signal heads 53 feet from the
stop line. For signal heads between 53 feet and 180 feet, the maximum
mounting height shall be 25.6 feet (see Figure 4.28).
A A B A E A
(SPLIT PHASE)
A A B A E A
(SPLIT PHASE)
R R
Y Y Y
G G G
A B G
E
W
W/2 (8’ MIN.)
R LEFT R R
TURN
Y Y SIGNAL Y OR Y
G G G G
C C A A
C C A A
R LEFT R R
TURN
Y SIGNAL Y OR Y
G G G
F B F E A
16’ 16’
F A F E A A F E A
16’ 16’
D A H OR G* F A H OR G*
* USE 5-SECTION
IF RT TURN OVERLAP
R R
R Y R Y
Y Y G Y Y G
G G G G G G
A B E F G H
Tennessee Department of Transportation
Traffic Design Manual
Signal Head Placement
(Split Phase Operation) Figure 4.32
4.9.9 Left Turn Signals – Three types of left turn signal heads are commonly
used:
A. Three Section heads (R, mY, mG with sign) and (mR, mY, mG)
– Three section left turn heads are used for “protected only” left turn
operation when there exists a separate left turn lane.
B. Four Section Heads (R, Y, G, mG) – Four section left turn heads
are used where the left turn is part of a split phase operation and
also at the top of some “T” intersections.
C. Five Section Heads (R, Y, G, mY, mG) – Five section left turn
signal heads are used both with and without a separate left turn
lane, and where the left turn operation is “protected/permissive” .
4.9.10 Right Turn Signals – Right turn signals are normally provided only where
there is a separate right turn lane accompanied by a right turn signal
overlap with a compatible cross street left turn signal phase. Typically, a
five section head (R, Y, G, Yo, Go) is used.
Meaning – Walk
Color – White
Size – The symbol shall be approximately 12” tall.
Location – Integral with and to the right of the upraised hand
symbol.
Meaning
Flashing – Pedestrian Clearance
Steady – Don’t Walk
Color – Portland Orange
Size – The symbol shall be approximately 12” tall.
Location – Integral with and to the left of the walking person
symbol.
46
MUTCD, FHWA, 2003, p. 4E-1.
TRAFFIC DESIGN MANUAL 4-85 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
POLE MOUNTED
SIGNAL
12” PED
10’ 0”
HEAD
2 ½” PEDESTRIAN
PUSH BUTTON
8’ 0”
POST
4” DIA.
PEDESTAL
POLE
PEDESTRIAN
SIGN
PEDESTRIAN
PUSHBUTTON
3’ 6”
PUSHBUTTON POST
PEDESTAL POLES
4.11 Traffic Signal Supports – The two basic types of traffic signal supports are
strain poles and mast arm poles.
Strain Pole – A strain pole is a pole to which span wire is attached for the
purpose of supporting the signal wiring and signal heads (see Figure 4.34).
Mast Arm Pole – A mast arm pole is a cantilever structure that permits the
overhead installation of the signal heads without overhead messenger cables
and signal wiring, which is run inside the arm structure (see Figure 4.35)
Traffic signal supports, including steel strain poles, concrete strain poles and
mast arm poles, shall be in accordance with TDOT specifications. Adjacent utility
poles shall not be used for traffic signal supports in new installations unless
physical conditions preclude the installation of separate traffic signal supports.
TETHER WIRE
MAXIMUM MOUNTING
HEIGHT
16’ 6” MIN. VERTICAL PER M.U.T.C.D.
POLE MOUNTED CLEARANCE 21’ TO 25’6”
SIGNAL HEAD (17’ 6” TYP.)
(WHERE REQD.)
PEDESTRIAN
PUSHBUTTON AND
SIGN (WHERE REQD.)
FOUNDATION
PEDESTRIAN
SIGNAL
10’ TYP. (WHERE REQD.)
(8’ MIN.)
PEDESTRIAN
VAR. PUSHBUTTON AND
(2’ MIN.) SIGN (WHERE REQD.)
FOUNDATION
Z-SPAN
(WITH CURBED MEDIAN)
Z Span Disadvantages:49
1. On divided roadways, it places traffic signal poles in median
areas where they are more likely to be struck by vehicles.
Check clear zone requirements.
2. On divided roadways, additional pedestal poles may be
needed if pedestrian signals and detectors are required.
3. On divided roadways, pedestrians cannot see the parallel
signal indications once they get to the median area.
49
Traffic Engineering Handbook, ITE, 1999, p. 507.
TRAFFIC DESIGN MANUAL 4-94 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
area. Consideration must be made to ensure an adequate pole
length is specified in such a situation.
Equation 4.12
PH = 2 + LsS + c + H + d
Where two span wires attach to the same strain pole, the
pole height will be determined by using the longer of the two
span wires. Pole heights shall be rounded up where
necessary to be specified in even number feet (26, 28, 30,
etc.).
50
MUTCD, FHWA, p. 4D-20.
TRAFFIC DESIGN MANUAL 4-95 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
4.11.3 Mast Arm Poles – Mast arm supports provide a more rigid mounting for
signal heads and overhead signs than do span wire installations.51
Accordingly they are particularly applicable where programmed visibility
signal heads are used. They also require less maintenance in regards to
turned signal heads and signs. Mast arm installations are more
aesthetically pleasing than span wire
installations since there is no overhead Mast arm supports
span wire or signal wiring. should be considered
when they would match
Very long mast arms can be extremely adjacent signals, when
costly. Generally, mast arms greater than utilities are underground,
65 feet long become unrealistic. Mast when they would result in
arm installations are more expensive then fewer overall poles or
strain poles because they require boring when aesthetics are a
and jacking under the roadway to get primary concern.
signal and detector cables to the
controller cabinet.
Advantages:
1. Provides the required minimum 40 feet distance between the
signal heads and the stop line of all approaches.
2. Provides good far side signal head visibility for pedestrians.
3. Provides locations for pedestrian signal indications and
pedestrian detectors where needed.
Disadvantages:
1. Requires four mast arm poles and foundations for a typical
four leg intersection.
Advantages:
1. Uses fewer poles than a strain pole or single mast arm
arrangement.
2. Provides good signal head placement for offset
intersections.
Disadvantages:
1. Additional traffic signal poles may be needed if pedestrian
signals and detectors are required.
2. Sight lines to the signal heads may be obscured.
51
Traffic Engineering Handbook. 1999. p. 508
TRAFFIC DESIGN MANUAL 4-96 DECEMBER 2003
CHAPTER 4 – TRAFFIC SIGNAL DESIGN
SINGLE MAST ARMS DUAL MAST ARMS
LEGEND:
SIGNAL HEAD
MAST ARM SIGNAL POLE
4.12 Signal Wiring – All conductors shall be run inside conduit except loop
conductors in the pavement, cables run along messenger or span wire, or cables
run inside poles. All new cable runs shall be continuous and free of splices. All
signal cable shall meet the applicable requirements of IMSA and National Electric
Code.
4.12.1 Signal Control Cable – All signal control cable shall conform to
applicable IMSA Specification No. 19-1 or 20-1. Stranded cable color
coded AWG No. 14 shall be used for all signal and accessory circuits.
4.12.4 Inductive Loop Wire – Conductors for traffic loops and home runs shall
be continuous cross-linked polyethylene insulated AWG No. 14 wire,
conforming to IMSA Specification No. 51-1 or 51-3, to the detector
terminals or spliced with shielded detector cable within a pull box, condulet
or pole base.
4.12.5 Loop Detector Lead-In (Shielded Cable) – Loop detector lead-in cable
wire shall be continuous AWG No. 14 wire conforming to the requirements
of IMSA Specification No. 50-2, polyethylene insulated, polyethylene
jacketed shielded cable.
4.12.8 Cable Sizing for Conduit – After the signal head and signal detector
arrangements/placements have been determined, the necessary signal
wiring required involves the following steps:
A. Signal Head Requirements – The typical wiring requirement of
each individual signal head may be determined by using Figure
4.38.
B. Mast Arm/Span Wire Runs – Determine the length of wiring
required for the signal heads depending on whether span wire or
mast arms are used.
C. Detectors, Power and Interconnect Cable – Determine the wiring
required for detectors, power, and interconnect cables where
applicable.
D. Sizing Conduit – Combine the wiring requirements in 4.12.1 and
4.12.3 above and size the conduit needed for each wiring run using
Table 4.7.
4.13 Conduit – All underground signal wiring shall be encased in conduit to protect
the cables or conductors and facilitate maintenance. All signal wiring above
ground shall be installed in conduit (risers), unless the wiring is inside of a pole or
attached to a span wire or a messenger cable. Conduit used for traffic signal
installation shall have the following characteristics:
TO GREEN (GREEN) P2 P2
7C to ped. Displays
5C to ped. PB P4
P4
TO GREEN ARROW (BLUE)
TO YELLOW ARROW (BLACK) 7C
SPARE (WHITE/BLACK) V3 V1
(Split phase)
(Prot.)
(Perm/prot.)
V4
4-SECTION SIGNAL HEAD (TYPE 140A1)
V2
NEUTRAL (WHITE) V1
V3
TO RED (RED) 5C V1 V1
7 CONDUCTOR
CABLE 7C
TO YELLOW (ORANGE) (Perm.) 7C
V1 V1
TO GREEN (GREEN)
7C
TO GREEN ARROW (BLUE) P1
SPARE (BLACK) 5C to ped. Displays
P3
3C to ped. PB
SPARE (WHITE/BLACK)
TYPICAL WIRING SCHEMATIC
(DEPICTING VARIOUS LEFT TURN TREATMENTS)
3-SECTION SIGNAL HEAD
(LEFT TURN-TYPE 130A2 OR 130A3)
NEUTRAL (WHITE)
V4
TO RED (RED) LEGEND
5 CONDUCTOR
CABLE
TO YELLOW ARROW (ORANGE) CONTROLLER
SPARE (BLACK)
* 8C AND 9C MAY BE SUBSTITUTED FOR 7C CABLE
AWG 14 AWG 16
Number of Outside Diameter 2 Number of Outside Diameter 2
Area (in ) Area (in )
Conductors (inches) Conductors (inches)
4.13.3 Depth Installed (Underground) – Conduit is placed 18” to 36” below the
finished grade. Typically, conduit below sidewalk is placed 18” deep.
Typical traffic signal conduit shall be 2” diameter and detector loop conduit
1” diameter, unless otherwise indicated. Conduits smaller than 1”
diameter shall not be used unless otherwise specified, except grounding
conductors at service points shall be enclosed in 3/4”diameter conduit. No
reducing couplings will be permitted. The conduit between a saw cut and
a pull box for loop lead-ins shall be 1” diameter and not be measured for
separate payment, but will be absorbed in other conduit items.
4.13.7 Bored and Jacked Conduit – All bored and jacked conduit shall be rigid
(RGS). The estimation of the amount of boring is critical. Care should be
taken for a realistic estimate (overestimation is preferred).
4.13.8 Conduit Radii – All conduit bends shall be large radius to facilitate cable
pulling (6” minimum radius).
4.13.9 Spare Conduit – Spare conduit stubs for future use shall always be
installed in all new controller cabinet bases and pole foundations. These
stubs shall not be measured for separate payment, but will be absorbed in
other conduit items.
4.13.10 Conduit for Road Widening Projects – Conduit and pull boxes should
be considered for installation on collector and arterial street widening
projects where there is a potential for future interconnect needs.
4.14.2 Type/Size/Use – Figure 4.39 shows the various size pull boxes and their
normal application or use. Type A Pull Boxes shall be used exclusively for
splicing loop wires to shielded cable only. Type B Pull Boxes shall be
used for all other traffic signal cable applications.
Pull boxes for fiber optic cable must be larger than standard pull boxes
due to the large bending requirements of fiber optic cable.
4.14.3 Spacing – Pull boxes shall be located at 150 foot intervals for signal cable
and detector cable runs. Pull boxes for copper interconnect cable runs
shall be located at 300 foot intervals. Fiber optic pull boxes should be
located every 1,000 feet for fiber optic cable runs.
4.14.4 Material – Pull boxes and covers are to be of load bearing design in
accordance with TDOT standard specifications. In general, all pull boxes
shall be traffic load bearing.
TRAFFIC
DEPTH OF
SIGNAL PULLBOX
12”
MIN. DIMENSIONS
TYPE
LENGTH WIDTH DEPTH
A 12” 12” 6” Type “A” Pull Boxes are used for splicing loop lead-ins.
B 28” 16” 12” Type “B” Pull Boxes are used for all signal cable routing.
3”
3”
12”
6” for trenched conduit
0” for directional bored conduit
4.15.2 Design – Where used on mast arms or strain poles, the street light
support must be designed integral with the traffic signal support. The pole
manufacturer must provide an acceptable design for review by TDOT.
4.15.3 Mounting Height – Typically 30 foot minimum above roadway. The actual
mounting height shall be determined by the luminaire photometrics.
The type of flash used (all-red or yellow-red) must be considered carefully. Driver
expectation is an important factor. Drivers are conditioned to react to situations
through their experiences. Mixing the types of flash can confuse drivers if they
are accustomed to the all-red flash. The benefits of operating a mixed color flash
must be weighed against the disadvantages. Violation of driver expectation can
be a disadvantage of a mixed color flash.
A. All Red Flash – This type of flashing operation flashes red to all
intersection approaches. It may be used under the following
conditions:
4.17 Stop Signs at Signalized Intersections – The MUTCD prescribes that STOP
signs shall not be used in conjunction with any traffic signal operation, except
when:
4.18 Signal Control for Driveways within Signalized Intersections – Traffic signal
control for a driveway should be provided only if the driveway serves a
commercial or multi-residential development. Signal control may also be
provided for driveways serving non-profit land uses with significant traffic
generation such as churches. Split-phase operation for these low volume
driveways should be considered and detection should always be provided for the
approach to avoid unnecessary delays for other approaches.
The following steps are recommended for the activation of a new traffic signal:
4.20.1 Advance Flash Period – A new traffic signal installation should be put on
flash operation for a period of seven weekdays prior to the activation of
normal “stop and go” operation, so as to make motorists aware of its
presence.
4.20.2 Publicity – The date and time of the activation of “stop and go” operation
should be advertised in both the local newspaper and on local radio
stations both prior to and on the date of activation.
4.20.3 Activation – The actual activation of normal “stop and go” operation
should be made during an off peak traffic period.
4.20.4 Technical Support – The contractor shall be on-hand for all new traffic
signal activations to immediately trouble shoot or fix any problems that
arise.
4.20.5 Signing Adjustments – Once the traffic signal is turned on normal “stop
and go” operation, remove the stop signs that the traffic signal replaces.
4.20.7 School Crossing – Should the intersection include a school crossing with
a crossing guard, the crossing guard should be familiarized with the
operation of the new traffic signal.
4.20.8 Fine Tuning – Shortly after the traffic signal is turned on, the engineer
should observe the signal’s operation during both peak and off peak
periods to assure the adequacy of the signal’s timing parameters.