Baren Report 06
Baren Report 06
1
PROGRESS REPORT No. 06.
PROJECT INFORMATION;
1.0 CONTRACT PARTICULARS;
2
PROGRESS REPORT No. 06.
Completed
e) Steel fixing 100% 100% 100%
Completed
C) Concrete
100% 100% 100% Completed
works Completed
100% Completed
D) Staircase 100% 100% Completed
formworks
E) Staircase In progress
100% 100% 100% In progress
steel fixing
F) Staircase
concrete 100% Not started
100% 100% Not started
works
G) Beams and
slabs 50% 50% In progress
50% In progress
formworks
H) Beams and
50% 50% In progress
slabs steel 50% In progress
fixing
I) Beams and
slabs
100% Not started
concrete 100% 100% Not started
4
PROGRESS REPORT No. 06.
works
5
PROGRESS REPORT No. 06.
2.1.2 Labors
Section Skilled Unskilled Remarks
Steel fixes 8 Varies due to site
demand
Carpenter 06 Varies due to site
demand
Mason 4 4 Varies due to site
demand
Laborer’s 16 Varies due to site
demand
Welders 01 Varies due to site
demand
Angle grander 03
Hand saws 6
Hammers 8
Circular saws 2
6
PROGRESS REPORT No. 06.
4. MATERIALS ON
SITE
The following materials have been collected during this period.
No. Description Unity Received Used Remaining
01 Aggregates cum 575.53 494 80
02 Sand Cum 604 450 54
03 Reinforcements Ton 42.2 42.2 0
04 Cement Ton 177.35 177.35 0
05 Timber No 880 880 0
6. WEATHER RECORDS
Weather condition on construction site is ideal for working,
Therefore;
Rain interrupts site works from time to time around 20 days have
been recorded as lost (Non working) days due to rainfall
interruptions.
7
PROGRESS REPORT No. 06.
APPENDIXES
8
PROGRESS REPORT No. 06.
9
PROGRESS REPORT No. 06.
10
PROGRESS REPORT No. 06.
11
PROGRESS REPORT No. 06.
12
PROGRESS REPORT No. 06.
13
PROGRESS REPORT No. 06.
14
PROGRESS REPORT No. 06.
Fig.04(b). backfilling
15
PROGRESS REPORT No. 06.
Fig.04(c). backfilling
16
PROGRESS REPORT No. 06.
17
PROGRESS REPORT No. 06.
18
PROGRESS REPORT No. 06.
19
PROGRESS REPORT No. 06.