Baren Report 06

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 20

PROGRESS REPORT No. 06.

COMPANY: BAREN ENTERPRISES COMPANY LIMITED P.O.BOX 2792, MBEYA.


PROJECT: PROPOSED CONSTRUCTION OF ADMINISTRATION BUILDING
OFFICE TO BE BUILT AT VWAWA (MBOZI) DISTRICT COUNCIL
PHASE ONE.

1
PROGRESS REPORT No. 06.

PROJECT INFORMATION;
1.0 CONTRACT PARTICULARS;

CONTRACT NO: 78J6/2023/2024/W/01

CONTRACT AMOUNT (PHASE I): Tshs 988,409,772.00

VARIATION Tsh 293,000,000

REVISED CONTRACT AMOUNT Tsh 1,281,409,772

AMOUNT PAID TO DATE : Tshs 425,000,000


COMMENCEMENT DATE: 2ndJUNE 2023

WORKS SUSPENDED DUE TO DESIGN ISSUES: 4 MONTHS

ORIGINAL COMPLETION DATE: 1st February 2024

REVISED COMPLETION DATE: 30th JUNE 2024

ORIGINAL CONTRACT DURATION: 8 Months

TIME SPENT TO DATE: 4 Months


TIME LEFT: 5 Months
DEFECTS LIABILITY PERIOD: 365 Days
OVERALL WORK PROGRESS 75%

CLIENT: DISTRICT EXECUTIVE DIRECTOR,


MOMBA DISTRICT COUNCIL,
P.O.BOX 273,
TUNDUMA-MOMBA.

CONSULTANT: TANZANIA BUILDING AGENCY,


P.O.BOX 94,
DODOMA.

REP-CONSULTANT REGIONAL MANAGER,


TANZANIA BUILDING AGENCY,
P.O.BOX 137,
SONGWE.

MAIN CONTRACTOR: BAREN ENTERPRISES COMPANY LIMITED,


P.O.BOX 2792,
MBEYA.

2
PROGRESS REPORT No. 06.

1.1 GENERAL INTRODUCTION


The following is the March/April monthly Progress Report for the PROPOSED
CONSTRUCTION OF ADMINISTRATION BUILDING OFFICE TO BE BUILT AT
VWAWA (MBOZI) DISTRICT COUNCIL PHASE ONE, the report is prepared so
as to inform about activities conducted on site on month March/April 2024.
Description of works;
Works comprise;
1. SUBSTRUCTURE WORKS WHICH INCLUDE; (EXCAVATIONS,
SETTING OUT, SAND FILL, BLINDING CONCRETE FOR PAD
FOOTINGS, STRIP FOUNDATIONS, FOUNDATION WALLING
AND HAULING OF SELECTED FILL MATERIALS) = Done 100%
2. SUPERSTRUCTURE WORKS WHICH INCLUDE; (STEEI FIXING
FOR COIUMNS AND BEAMS, FORMWORKS (for columns, beams
and slabs + strong room), CONCRETE WORKS FOR COIUMNS,
STRONG ROOM, BEAMS, STAIRCASE AND SIABS,
EXCAVATION AND CONSTRUCTION OF WASTE WATER PITS
(Septic and soaking pits) AND ROOFING WORKS), = Done 50%

1.1.1 General progress


- Substructure works progress is 100% completed

- Substructure works progress is 50% completed

- The overall project progress is approximated to be


75% complete based on executed works.

1.1.2 Specific progress of works


The specific progress as attained on site for the t h i s
building structure
See the table below
Activity Progra Progress Target Status Remarks
m Currently next four
planned weeks

MOBILIZATION 100% 100% 100% In progress as Good progress


per works
execution
demand
SUBSTRUCTURE;
a) Excavation and
earthworks for 100% 100% 100% Completed Completed
Ramp and stairs
3
PROGRESS REPORT No. 06.

b) Blinding work 100% 100% 100% Completed Completed


and
foundation walling.
c) Haulage of Completed Completed
100% 100% 100%
proposed fill
materials to site
d) Backfilling 100% 100% 100% Completed Completed

Completed
e) Steel fixing 100% 100% 100%
Completed

f) Formwork 100% 100% 100% Completed


&Concrete Completed
work
SUPERSTRUCTURE;
A) Columns 100% Completed
100% 100% Completed
steel fixing
B) Formworks 100% Completed
100% 100% Completed

C) Concrete
100% 100% 100% Completed
works Completed

100% Completed
D) Staircase 100% 100% Completed
formworks
E) Staircase In progress
100% 100% 100% In progress
steel fixing
F) Staircase
concrete 100% Not started
100% 100% Not started
works
G) Beams and
slabs 50% 50% In progress
50% In progress
formworks
H) Beams and
50% 50% In progress
slabs steel 50% In progress
fixing
I) Beams and
slabs
100% Not started
concrete 100% 100% Not started

4
PROGRESS REPORT No. 06.

works

5
PROGRESS REPORT No. 06.

2.0 Manpower on site;

2.1 Project key personnel;

POSITION NAME COMPANY

SITE ENGINEER EZEKIEL O. MAHINYILA BAREN ENT. CO. LTD-


MBEYA.

ASSISTANT SITE IDD MNEMA MAULID BAREN ENT. CO. LTD-


ENGINEER MBEYA.

TECHNICIAN GERALD D. MHAGAMA BAREN ENT. CO. LTD-


MBEYA.

2.1.2 Labors
Section Skilled Unskilled Remarks
Steel fixes 8 Varies due to site
demand
Carpenter 06 Varies due to site
demand
Mason 4 4 Varies due to site
demand
Laborer’s 16 Varies due to site
demand
Welders 01 Varies due to site
demand

3. Equipment and Hand tools on site


EQUIPMENT and HAND TOOLS QTY

Angle grander 03

Hand saws 6

Hammers 8

Circular saws 2

6
PROGRESS REPORT No. 06.

4. MATERIALS ON
SITE
The following materials have been collected during this period.
No. Description Unity Received Used Remaining
01 Aggregates cum 575.53 494 80
02 Sand Cum 604 450 54
03 Reinforcements Ton 42.2 42.2 0
04 Cement Ton 177.35 177.35 0
05 Timber No 880 880 0

06 Marine boards 18mm thick No 200 200 0

07 Blocks No 13,000 13400 0

5. Incidents and accidents


No accident and Health and safety incident which has occurred on site over the last 3
Months.

S/N Incident/injury Date Time Location No. of victims


occurred
0
1 NIL

6. WEATHER RECORDS
Weather condition on construction site is ideal for working,
Therefore;
Rain interrupts site works from time to time around 20 days have
been recorded as lost (Non working) days due to rainfall
interruptions.

7
PROGRESS REPORT No. 06.

APPENDIXES

8
PROGRESS REPORT No. 06.

SITE PROGRESS PHOTOs.

Fig.01 (a). Casting concrete for stub columns

9
PROGRESS REPORT No. 06.

Fig.01 (b). Block walling (Foundation walls)

10
PROGRESS REPORT No. 06.

Fig.02 (a). Block walling (Foundation walls) –in progress

11
PROGRESS REPORT No. 06.

Fig 02 (b). Hauling of selected fill materials

12
PROGRESS REPORT No. 06.

Fig.03(a). Selected fill stockpiled for foundation backfill

13
PROGRESS REPORT No. 06.

Fig.04(a). In the process of backfilling

14
PROGRESS REPORT No. 06.

Fig.04(b). backfilling

15
PROGRESS REPORT No. 06.

Fig.04(c). backfilling

16
PROGRESS REPORT No. 06.

Fig.04(d). Hardcore placing

17
PROGRESS REPORT No. 06.

Fig.05(d). Casting oversite concrete

18
PROGRESS REPORT No. 06.

Fig.06(d). Casting oversite concrete

19
PROGRESS REPORT No. 06.

Fig.07(d). Soil sterilization


20