Shimizu Bim For Construction 20190515

Download as pdf or txt
Download as pdf or txt
You are on page 1of 79

SHIMIZU CORPORATION

SHIMIZU VIETNAM

Application of in construction
SHIMIZU CORPORATION
SHIMIZU VN BIM

DESIGN TENDER CONSTRUCTION OPERATION

1 2a 2b 3 4

OWNER

E.P.Cm Design Tender Construction Facility


Management Management

Movie ASME
BoQ
B.I.M
Perspective Coordinate

3D Model Master Construct.


4D Schedule Approach

Design
Drawing
Construct. Shop drawing
Clashing Method &BBS
feedback
SHIMIZU CORPORATION

Application of in construction
SHIMIZU CORPORATION
 TEMPORARY PLAN
SHIMIZU CORPORATION
 TEMPORARY PLAN

Scaffolding Schedule
Scaffolding Erection Sequence
Scaffolding Plan Elevation
SHIMIZU CORPORATION
 CONSTRUCTION SEQUENCE
SHIMIZU CORPORATION
 4D MASTER SCHEDULE
SHIMIZU CORPORATION
 4D MASTER SCHEDULE
SHIMIZU CORPORATION
 4D DAILY Real time schedule control
SHIMIZU CORPORATION
 REBAR CONTRONL - BAR BENDING SCHEDULE

Cut and bend on site. Order from factory

A lot of Wastage Less cut and bend on site , less wastage

Conventional Process BIM Process


SHIMIZU CORPORATION
 REBAR CONTRONL - BAR BENDING SCHEDULE

Assembly rebar at site Order from factory

Preassembly rebar

Conventional Process BIM Process – Bar Bending Schedule


SHIMIZU CORPORATION
 REBAR CONTRONL - BAR BENDING SCHEDULE

BAR BENDING SCHEDULE (BBS) contains


• Plans , sections of rebar
• Schedule, quantity of rebar
• To use for rebar fabrication
purpose
• Optimum solution for
reduce wasted loss
SHIMIZU CORPORATION
 PROJECT COORDINATION

A
3D coordination model
= A+S+MEP

S MEP
SHIMIZU CORPORATION
 PROJECT COORDINATION
SHIMIZU CORPORATION
 SHOP DRAWING

S
STR model

Structural
Shop Drawing
(by Revit)

A
AR model

Finishing
Shop Drawing
(by Revit)

MEP model

MEP M&E
Shop Drawing
(by Revit)
SHIMIZU CORPORATION

SAMPLE PROJECT
SHIMIZU CORPORATION

ÁP DỤNG BIM CHO DỰ ÁN TRONG GIAI ĐOẠN THI CÔNG


ÁP DỤNG BIM CHO DỰ ÁN TRONG GIAI ĐOẠN THI CÔNG

Aqua Central Project


CONTENTS:
Sample Room

BEP (BIM Execution Plan- kế hoạch triển khai BIM )

Sample Singapore project BIM implement


SAMPLE ROOM
SAMPLE ROOM
SAMPLE ROOM
CONTENTS:
Sample Room

BEP (BIM Execution Plan- kế hoạch triển khai BIM )

Sample Singapore project BIM implement

Conclusion
BEP(BIM Execution Plan- kế hoạch triển khai BIM )
FOR
Aqua Central Project
BEP(BIM Execution Plan- kế hoạch triển khai BIM )
FOR
Aqua Central Project

BEP(BIM Project Execution Plan) Overview


Section A: Project Information
Section B: Project member
Section C: Project goals
Section D: Scope During Construction stage
Section E: Project Deliverables
Section F: Model element for deliverable
Section G: Process for BIM creation AND Collaboration
Section H: Technological requirement
Appendix A: Clash detection report
Appendix B: BIM and CAD standard
Appendix C: Coordinate system
Appendix D : BEP Update Record
BEP(BIM Project Execution Plan) Overview

To successfully implement Building Information Modeling (BIM) on a project, the project


team has developed this detailed BEP(BIM Project Execution Plan) (BEP). The
BEP(BIM Project Execution Plan) defines uses for BIM on the project, along with a
detailed design of the process for executing BIM throughout the project lifecycle.

By developing a BIM Execution Plan (BEP), the project and project team members can:
• clearly understand the strategic goals for implementing BIM on the project;
• understand their roles and responsibilities for model creation, maintenance and
• collaboration at different stages of the project;
• design a suitable process to participate in the implementation;
• define the content, level of detail and by when the model is to be delivered to
meet which objectives;
• benchmark the effectiveness of process with previous and future projects
• define contract language to ensure all project members fulfil their obligations
• provide a baseline plan to measure progress throughout the project
Section A: Project Information
1.Project Owner: Hanoi Water Tower JSC.,
2.Project Name: HANOI AQUA CENTRAL PROJECT
3.Project Location and Address:44 Yen Phu Street, Hanoi
4.Building's purpose : Multi-Purpose building includes : Commercial center, Residential
apartment, Hotel block for long-term lease
5.Project Numbers: VN51-16
Section A: Project Information NAME LEVEL
(STRUCTURE)

B3 -17.10
B2 -9.50
B1 -4.65
1FL 0.00
2FL 6.70
3FL 12.70
4FL 19.00
5FL 22.20
6FL 25.40
7FL 28.60
8FL 31.80
9FL 35.00
10FL 38.20
11FL 41.40
12FL 44.60
13FL 47.80
14FL 51.00
15FL 54.20
16FL 57.40
17FL 60.60
18FL 63.80
19FL 67.00
20FL 70.20
21FL 73.40
22FL 76.50
TUM 79.55
RFL 82.55
Section B: Project member
1.BIM PROJECT MEMBER:
ROLE ORGANIZATION CONTACT NAME LOCATION E-MAIL PHONE
Site office/
BIM Manager Shimizu P.T.Giang [email protected] 0906244086
HN office
BIM Site office/
Shimizu N.T.Duong [email protected]
Coordinator(A&S) HN office
BIM Site office/
Shimizu N.D.Thai [email protected]
Coordinator(M&E) HN office
BIM Coordinator
(sub-con A)
BIM Coordinator
(sub-con S)
BIM Coordinator
(sub-con M&E)
Section B: Project member
1.BIM PROJECT MEMBER CSA:

BIM MANAGER (CSA)

BIM COORDINATOR BIM COORDINATOR


(ARC) (STRUC)

BIM BIM BIM BIM MODELER BIM MODELER BIM BIM MODELER BIM MODELER BIM
MODELER 1 MODELER 2 MODELER 3 MODELER 6 MODELER 3
(ARC) (ARC) (ARC) 4 (ARC) 5 (ARC) (ARC) 1 (STRUC) 2 (STRUC) (STRUC)

BIM BIM
MODELER 7 MODELER 8
(ARC) (ARC)

9 STAFFS 4 STAFFS
Section B: Project member
1.BIM PROJECT MEMBER MEP:

BIM MANAGER (MEP)

BIM COORDINATOR
(MECHANICAL) BIM COORDINATOR (ELECTRICAL)

BIM MODELER 1 BIM MODELER 2


BIM MODELER 1 BIM MODELER 3 BIM MODELER (ELECTRICAL)
(PUMB) (FIRE FITING) 4 (ACMV) (ELECTRICAL)

BIM MODELER 2 BIM MODELER


(PUMB) 5 (ACMV)

6 STAFFS 3 STAFFS
Section B: Project member
2.BIM ROLES AND RESPONSIBILITIES:
ROLE RESPONSIBILITIES IN MODEL MANAGEMENT BIM RESPONSIBILITIES

Coordinate BIM use on project, determine Schedule of use, sharing - Oversight


BIM Manager
activities, quality control, modelling responsibilities and document in - Management execution
(Contractor)
BIM Execution Plan. - Model exchange

- Coordinate with design team


BIM
Receives or create BIM for constructability study and field use. and subcontractors
Coordinator
Determine interference checking responsibilities - Model user & review
(Contractor)
- Model exchange

- Coordinate with design team


Develop 2D/3D models during design and construction
BIM Modeller and subcontractors
Check and verify Revit model and drawings
(Contractor) - Model user & review
Work and coordinates with BIM team members on collaboration

- Coordinate with main


BIM coordinator Develop 2D/3D models during design and construction. contractor
(Sub-con) - Model user & review
- Model exchange
Section B: Project member
3.BIM USE ORGANIZATION CHART:
Information OWNER
exchange by BIM ARCHITECT
(HN AQUA CENTRAL)
(CPG)
Information
exchange by other method

STRUCTURAL M&E
DESIGNER DESIGNER
(CPG) (CPG)

DWG,PDF
STR CONTRACTOR

MODEL STR FOR CHECK


CLASHING ONLY BIM
Manager
(SHIMZ-VN)
SUB-CON
SANITARY
STR
BIM coordinator
SUB-CON
Modeler ACMV
M&E BIM
coordinator BIM
RVT

BIM Modeler
Modeler
2D
AR SUB-CON Drafter
coordinator SUB-CON
LIFT, ESCALATOR
FIRE

SUB-CON BIM SUB-CON


2D ELECT
AR Modeler
Drafter
UNDER SHIMIZU
Section C: BIM Goals
BIM GOALS/ OBJECTIVE:
POTENTIAL BIM
GOAL DESCRIPTION
USES
Finding and resolving most of the conflicts before
3D coordination
construction start.
Increase quality of shop drawing. Shop drawing

4.BIM USES:
- DESIGN REVIEWS
- 3D COORDINATION
- SHOP DRAWING
- RECORD MODELING (AS-BUILT)
Section D: Scope During Construction stage
BIM USE ORGANIZATION CHART:
Scope During Construction stage AUTHOR USER

Quality: BIM element is modeled with fabrication and assembly details where applicable or useful for
construction works; otherwise, details may be represented in 2D CAD drawings to complement the Detailed
Design models
Essential: Produce Construction Models from Architectural, Structural and MEP
Main
Expected Deliverables : ALL
Contractor
 Construction Models with Key Services Coordinated.
Essential: Produce schedules of materials, areas and quantities from the BIM databases for
contractors’ reference
Main
Expected Deliverables ALL
Contractor
 Schedules of materials, areas and quantities
Note: Schedule of material and quantity will be indicated in only selected shop drawing
Essential: Sub-contractors and specialist sub-contractors will generate documents based
on the Construction Models
Expected Deliverables
Main
 Shop drawings (A&M&E) ALL
Contractor
 Fabrication models and drawings
 Combined Services Drawings (CSD)
 Single Services Drawings (SSD)
Essential: Contractors should provide the latest record model and drawings to the
consultant if the consultant is required to do an amendment submission.
Expected Deliverables Main
ALL
 Record model Contractor
 Record model-generated drawings
Other non-BIM deliverables
Section E: Project Deliverables
1.FILE FORMAT:
BIM SUBMITTAL ITEM FORMAT NOTES
Design DWG&PDF From CPG
Model A for shop drawing REVIT version 2017(.RVT)export to DWG,PDF
Model S for Coordinator REVIT version 2017(.RVT)
Model M&E for Coordinator REVIT version 2017(.RVT)
Combined coordination model Navisworks 2014 (nwf or nwd)
Clash Detection Report Navisworks (html), PDF

2. FILE NAMING CONVENTION:


1 2 3 4
Area
Company code PROJECT CODE Trade code
(user define)
(2-4 letters) (MAX 4 letters)
SVN AQUA A 1F
… … S 1F~2F
ACMV …
FIRE
SANI
ELEC
CORD

Sample: SVN-AQUA_A_1F
Section E: Project Deliverables
3.MODEL OVER VIEW

BIM model is divided by trades of work. (Architectural, Structural, and Mechanical-


Electrical-Plumbing)
Due to the big amounts of information to be inputted in BIM model, BIM model for each
trade of work is separated into small files with the maximum target file size at 100 MB.
Model separation plans are shown in the next pages.

Coordination Shop drawing

Coordination Coordination
Section E: Project Deliverables
4.MODEL STRUCTURE
Structural model is divided into 5 Model 4
models. 21F~RF

Model for coordination with


ARCHITECTURAL & MEP only
Model 6
(shopdrawing by structure 13F~20F
contractor)
1/SVN-AQUA_S_B3~1FL
2/SVN-AQUA_S_2FL~4FL Model 5
10F~12F
3/SVN-AQUA_S_5FL~6F
4/SVN-AQUA_S_7FL~9F Model 4
7F~9F
5/SVN-AQUA_S_10FL~12F
Model 3
6/SVN-AQUA_S_13FL~20F 5F~6F
7/SVN-AQUA_S_21FL~RFL
Model 2
2FL-4FL

Model 1
B3~1FL
Section E: Project Deliverables
4.MODEL STRUCTURAL
Model FILE NAME FLOOR 3D file
1 SVN-AQUA_S_B3~1FL B3~1FL Structural model
2 SVN-AQUA_S_2FL~4FL 2FL~4FL Structural model
3-6 SVN-AQUA_S_5FL~20FL 5FL~6FL Structural model
7 SVN-AQUA_S_21FL~RFL 21FL~RFL Structural model

Worksets for Structural model Concrete material to be assigned in model


Model 1 to 4, worksets to be separated by floor refers to the concrete grade design
Tread Floor requirement.
S_ B3
S_ 1FL
…..
S_ RFL
Model 5 (Corewall /Staircase),
worksets to be separated by block
Tread Block
S_ BLKA
S_ BLKB (REVIT material LIB)
Section E: Project Deliverables
4.MODEL STRUCTURAL (FOR COORDINATION)
7/SVN-AQUA_S_21FL~RFL
Section E: Project Deliverables
5.MODEL ARCHITECTURAL
ARCHITECTURAL model is
divided into 10 models. Model 4
21F~RF
Model for coordination with
Structural & MEP and product
shopdrawing
Model 3
5F~20F
1/SVN-AQUA_A_B3~1FL
2/SVN-AQUA_A_2FL~4FL
3.1/SVN-AQUA_A_5FL~6FL
3.2/SVN-AQUA_A_7FL~9FL
3.3/SVN-AQUA_A_10FL~12FL
3.4/SVN-AQUA_A_13FL~19FL
3.5/SVN-AQUA_A_20FL
4/SVN-AQUA_A_21FL~RFL
Model 2
2FL-4FL

Model 1
B3~1FL
Section E: Project Deliverables
5.MODEL ARCHITECTURAL (FOR GENERATE SHOP DRAWING)
1/SVN-AQUA_A_B3~1FL

Generate shop drawing


Section E: Project Deliverables
5.MODEL ARCHITECTURAL
ARCHITECTURAL model is
divided into 10 models.
Model for coordination with
Structural & MEP and product
shopdrawing

Model 5_Unit BLK A


(Multiple files)

Model 6_ Residential lobby


(Multiple models)
Model 7_ Unit BLK B
(Multiple files)
Model 8_ Hotel lobby
(Multiple models)

Model 9_ Stair case


(Multiple models)

Model 10_ Toilet


(Multiple models)
Section E: Project Deliverables
5.MODEL ARCHITECTURAL (FOR GENERATE SHOP DRAWING)
Model 5_Unit BLK A (Multiple files)

Generate shop drawing


Section E: Project Deliverables
5.MODEL ARCHITECTURAL (FOR GENERATE SHOP DRAWING)
Model 5_Unit BLK A (Multiple files)
Section E: Project Deliverables
5.BIM FOR RFI
Section E: Project Deliverables
5.BIM FOR RFI
Section E: Project Deliverables
6.BIM FOR CLIENT MEETING
Section E: Project Deliverables
6.BIM FOR CLIENT MEETING
Section E: Project Deliverables
5.MODEL ARCHITECTURAL
5.1/SVN-AQUA_A_U-A1 8/SVN-AQUA_A_HLL
5.2/SVN-AQUA_A_U-A2-1,A2-2
5.3/SVN-AQUA_A_U-A3 9.1/SVN-AQUA_A_STA1
5.4/SVN-AQUA_A_U-A4 9.2/SVN-AQUA_A_STA2
5.5/SVN-AQUA_A_U-A5 9.3/SVN-AQUA_A_STA3
5.6/SVN-AQUA_A_U-A6
5.7/SVN-AQUA_A_U-A7(SAME A2) 10./SVN-AQUA_A_1FL~3FL-TOI

6/SVN-AQUA_A_RLL

7.1/SVN-AQUA_A_U-B1
7.2/SVN-AQUA_A_U-B2-1,B2-2
7.3/SVN-AQUA_A_U-B3
7.4/SVN-AQUA_A_U-B4
7.5/SVN-AQUA_A_U-B5
7.6/SVN-AQUA_A_U-B6
7.7/SVN-AQUA_A_U-B7
7.8/SVN-AQUA_A_U-B8
7.9/SVN-AQUA_A_U-B9
7.10/SVN-AQUA_A_U-B10
7.11/SVN-AQUA_A_U-B11
Section E: Project Deliverables
5.MODEL ARCHITECTURAL
FLOOR 2D drawings generating from
Model FILE NAME
3D file
1 SVN-AQUA_A_ B3~1FL B3~1FL GFP, RCP
2 SVN-AQUA_A_2FL~4FL 2FL~4FL GFP, RCP, ELEVATIONS
3.1 SVN-AQUA_A_5FL~6FL 5FL~6FL GFP, RCP
3.2 SVN-AQUA_A_7FL~9FL 7FL~9FL GFP, RCP
3.3 SVN-AQUA_A_10FL~12FL 10FL~12FL GFP, RCP
3.4 SVN-AQUA_A_13FL~19FL 13FL~19FL GFP, RCP
3.5 SVN-AQUA_A_20FL 20FL GFP, RCP
4 SVN-AQUA_A_21FL~RFL 21FL~RFL GFP, RCP
5 SVN-AQUA_A_UBLKA -XX-XX Varies GFP, RCP,UNIT
6 SVN-AQUA_A_RLL-XX-XX Varies GFP, RCP, ELEVATIONS
7 SVN-AQUA_A_ UBLKB -XX-XX Varies GFP, RCP,UNIT
8 SVN-AQUA_A_HLL-XX-XX Varies GFP, RCP, ELEVATIONS
9 SVN-AQUA_A_STA-XX-XX Varies GFP, RCP,
10 SVN-AQUA_A_TOI-XX-XX Varies GFP, RCP,
Worksets
Tread Block
A_ BRICKWALL
A_ FINISHING
A_ DOOR&WINDOW
A_ FURNITURE
A_ SANITARY
A_ CEILING
Section E: Project Deliverables
6.MODEL MEP
Model FILE NAME FLOOR 3D file
1 SVN-AQUA_ME_B3~1FL B3~1FL M&E model
2 SVN-AQUA_ME_2FL~4FL 2FL~4FL M&E model
3 SVN-AQUA_ME_5FL~20FL 5FL~20FL M&E model
4 SVN-AQUA_ME_21FL~RFL 21FL~RFL M&E model
5 SVN-AQUA_ME_LIFT LOBBY All M&E model

M&E MODEL WILL BE CREATED SYSTEM BY SYSTEM:

1. ACMV SYSTEM.
2. PUMB SYSTEM.
3. FIRE FITING SYSTEM.
4. ELECTRICAL SYSTEM.
5. COMBINE
SECTION F:MODEL ELEMENT DELIVERABLE

MODEL ELEMENT

GRADE 1 GRADE 2 GRADE 3


SECTION F:MODEL ELEMENT DELIVERABLE
1. ARCHITECTURAL BIM ELEMENTS
BIM Elements Geometry Component
type grade

Elements 3D 2D
Site Model Site infrastructure within site boundary ⃝ 2
(roads, pavements, car park spaces, access and parking arrangements and surrounding land use)
Surface drainage (only indication of locations necessary) ⃝
External drainage & underground drainage ⃝ 2
Hard landscaped areas within site boundary ⃝ 2
Planter boxes including sub-soil drainage systems ⃝
Rooms /Spaces Room spaces ⃝ 2
Walls and Interior / Exterior walls / Non-structural walls / Blockwork walls (Including finishes to identify if tiled / painted / ⃝ 2
Curtain Walls plastered)
Studs* and individual layers of drywall ⃝
Curtain wall with mullions and window glazing units including shading devices ⃝ 2
Doors, Windows and Interior / Exterior doors ⃝ 2
Louvers Interior / Exterior windows ⃝ 2
Louvers ⃝ 2
Ironmongery (handles, locks*, hinges* etc) ⃝
Roofs Roofs with overall thickness (including finishes & insulation) ⃝ 2
Ceilings Ceilings (without support sub-frames) including module arrangement, materials. ⃝ 2
Hangars and sub-frames for ceilings* ⃝
Floors Horizontal floors ⃝ 2
Sloped floors and ramps ⃝ 2
Raised floor (without support) ⃝ 2
Vertical Steps & stairs including risers, threads and railings including headroom clearance requirements ⃝ 2
Circulation Elevator shafts (without fit-out installations by lift contractor) ⃝ 2
Escalators & moving walkways, not including motorized equipment inside. ⃝ 2
Access ladders and catwalks ⃝ 2
Architectural Specialties Building Maintenance Units (BMU) ⃝ 1
and Casework
Fixtures and Equipment* Casework & cabinets ⃝ 2
(with input from interior Appliances such as in kitchen equipment ⃝ 2
designers, specialist sub- Toilet fixtures, plumbing faucets ⃝ 2
contractors, etc) Irrigation pipe ⃝
Signage ⃝
* These elements may cause BIM models to become too big and unmanageable.
SECTION F:MODEL ELEMENT DELIVERABLE
2. STRUCTURAL BIM ELEMENTS
(ii) Structural BIM ElementBIM Elements Geometry Component
type grade
s
3D 2D
Foundations ⃝ 2
Beams ⃝ 2
Columns ⃝ 2
Walls ⃝ 2
Slabs including recesses, kurbs, and major penetrations ⃝ 2
Stairs (steps, risers, threads, landings): all framing members and openings ⃝ 2
Shafts and Pits (and openings) ⃝ 2
Concrete reinforcement details (Rebar), imbeds and cast-ins* ⃝
Steel frame structures ⃝ 2
Base plates, bolts, clip angles, fixings, etc.* ⃝
Connection details of structural steel members* ⃝

* These elements may cause BIM models to become too big and unmanageable.
SECTION F:MODEL ELEMENT DELIVERABLE
3.1. ACMV BIM ELEMENTS
(ElementBIM Elements Geometry type

Elements 3D 2D
ACMV Equipment Air Handling unit ⃝ 2

Chiller unit ⃝ 2
Variable refrigerant unit ⃝ 2
Cooling Tower ⃝ 2
Exhaust or extract air fans ⃝ 2
Fresh air fans ⃝ 2
Other fans such as jet fans ⃝ 2
Heat Exchanges for projects with District Cooling ⃝ 2
ACMV Distribution Exhaust air ducts (excluding hangars) ⃝ 2
Fresh air ducts (excluding hangars) ⃝ 2
Supply air ducts (excluding hangars) ⃝ 2
Return air ducts (excluding hangars) ⃝ 2
Transfer air ducts (excluding hangars) ⃝ 2
Diffusers, air-boots, air grilles, air filters, registers ⃝ 2
Fire dampers, motorized dampers, volume control dampers, CO2 sensors, CO sensors ⃝ 2
Mechanical Piping Chilled water supply pipes including connections, fittings & valves ⃝ 2
Chilled water return pipes including connections, fittings & valves ⃝ 2
Condensate drain pipes including connections, fittings & valves ⃝ 2
Others Switch boards, control, BMS & DDC panels, BMS control & monitoring modules ⃝ 2
Fan Coil unit ⃝ 2
Engineering Smoke Extract System (e.g. smoke curtains, ductless fans) ⃝ 2
SECTION F:MODEL ELEMENT DELIVERABLE
3.2. PLUMBING AND SANITARY BIM ELEMENTS
(ElementBIM Elements Geometry type

Elements 3D 2D
General Pipe supports and brackets * ⃝

Pumps ⃝ 2
Control panels, monitoring and control sensors ⃝ 2
Plumbing BIM Elements Fresh water piping, fittings, valves including hot & cold water pipe work with all plumbing ⃝ 2
only equipment, sinks
Water meters ⃝ 2
Storage, water holding tanks, pressure vessels ⃝ 2
Underground Public Utilities for water supply ⃝ 2
Underground Public Utilities for drainage ⃝ 2
Grey water systems ⃝ 2
Pool filtration equipment ⃝ 2
Sanitary BIM Elements Foul drainage, kitchen waste pipe work including floor drains, open trapped gullies, sealed ⃝ 2
only trapped gullies and clean outs, vents and manholes
Grease and sand traps ⃝ 2
Sump and sewage pits ⃝ 2

* These elements may cause BIM models to become too big and unmanageable.
SECTION F:MODEL ELEMENT DELIVERABLE
3.3. FIRE PROTECTION BIM ELEMENTS
(ElementBIM Elements Geometry type

3D 2D
System piping, droppers, fittings, valves and sprinkler heads, sprinkler inlets, sprinkler control valve set, ⃝ 2
subsidiary valves, flow switches
Pipe supports and brackets * ⃝
Fire alarm gongs & break glass unit ⃝ 2
Fire sprinkler pumps ⃝ 2
Sprinkler tanks ⃝ 2
Hydrants and hose reels (location of street fire hydrant determined by architects) ⃝ 2
Gas piping for suppression systems ⃝ 2
Heat or smoke detectors, control panels, monitoring and control sensors, pump panels, check meter ⃝ 2
positions
Fire extinguishers ⃝ 2
Fire shutters & hoods above ⃝ 2
Smoke Curtains ⃝ 2

* These elements may cause BIM models to become too big and unmanageable.
SECTION F:MODEL ELEMENT DELIVERABLE
3.4. ELECTRICAL BIM ELEMENTS
Geometry Component
((ElementBIM Elements type grade

3D 2D
Cable trays, trunking & cable containment, Electrical risers, conduit, Busduct, power feeds, ⃝ 2

Outlets, panels, wall switches, circuiting to devices, security devices, card access and “plug moulds” (socket ⃝ 2
points)
HV & LV switch boards, switchgear, MCCB boards, MCB boards ⃝ 2
Transformers ⃝ 2
Light fittings & fixtures & housings for light fixtures ⃝ 2
Conduit associated with access, data communication, security systems and electrical equipment * ⃝ 2
Telecom equipment and computer racks ⃝ 2
Generators and exhaust flues including acoustic treatments ⃝ 2
Diesel tanks & fuel pipes ⃝ 2
Security system including CCTV camera, smart card system, door monitoring system ⃝ 2
Car park control system, barrier gates ⃝ 2
Equipment and associated installations maintained by public utility companies (Including manholes / drawpits ⃝ 2
for the Power Grid)
Earthing and lighting protection system ⃝ 2
Lifts, PA systems, BMS equipments including display panels (e.g. power consumption display) ⃝ 2

* These elements may cause BIM models to become too big and unmanageable.
SECTION G: PROCESS FOR BIM CREATION AND COLLABORATION

4. QUALITY CONTROL:
Validation
Sheets from the BIM shall be published to DWF (preferred), PDF or other non -editable format, where they can be
checked, approved, issued and archived as traditional documents.
Validation of the BIM data prior to sharing shall check that:
1) Model file has been audited, purged and compressed;
2) File format and naming conventions follow BIM execution plan,
3) Model files are up-to-date.
4) Model files are detached from central file,
5) Any linked reference files have been removed and any other associated data required to load the model file
is made available,
6) Model is correctly assembled through visual inspection,
7) Any changes since the last issue are communicated to the project team.
Data Security & Saving
1) Staff access to BIM project data held on the network servers shall be through controlled access permissions.
2) Maximum number of Revit back-ups shall be set to 3.
3) Revit LOCAL files shall be saved back to CENTRAL hourly.
4) Revit save reminder interval shall be set to 30mins. A 'Splash Page' is included in the associated templates .
These shall be retained and the file information completed. The note may be discarded or replaced with
project-specific information if required.
Reviewing BIM data
Untrained users shall not open Revit models directly. Instead, the model shall be exported as a 3D DWF and review
freely available Autodesk Design Review software shall be used for interrogation and mark -up.
Modelling Methodology
Follow Singapore BIM Guide Version 2.
SECTION G: PROCESS FOR BIM CREATION AND COLLABORATION

4. QUALITY CONTROL:
RESPONSIBLE SOFTWARE FREQUENC
CHECKS DEFINITION
PARTY PROGRAM(S) Y

Ensure there are no unintended model MONTHLY


VISUAL CHECK components and the design intent has CONSULTANT Revit (3rd week of
been followed the month)

Detect problems in the model where MONTHLY


INTERFERENCE BIM MANAGER Navisworks,
two building components are clashing (3rd week of
CHECK (Contractor) Revit
including soft and hard the month)

Ensure that the BIM and AEC CADD


MONTHLY
STANDARDS Standard have been followed (fonts,
BIM Modeler Revit (3rd week of
CHECK dimensions, line styles, levels/layers,
the month)
etc)

Model Accuracy and Tolerances:


PHASE DISCIPLINE TOLERANCE
CONSTRUCTION ARCH, STRC, MEP ACCURATE TO ±5mm OF ACTUAL SIZE AND LOCATION
Section H:Technological requirement
1. SOFTWARE:
BIM USE DISCIPLINE SOFTWARE VERSION
Autodesk Design
Design Review ARCH, STR, MEP 2017
Review
Coordination ,
ARCH, STR, MEP Navisworks 2014
clash detection
Moderler and Coordination ARCH, STR, MEP Revit 2017

2.COMPUTERS/ HARDWARE:
OWNER OF
BIM USE HARDWARE SPECIFICATIONS
HARDWARE
Equivalent or higher,
DESIGN AUTHORING SHIMIZU Intel® Xeon® W5590 (8M Cache, 3.33 GHz,
Desktop PC
Level 1 Simple model VIETNAM 6.40 GT/s Intel® QPI, 4 Cores)4GB of RAM
1.5G - NVIDIA Quadro FX 4800
Equivalent or higher
DESIGN AUTHORING
SHIMIZU Intel® Core™ i7-2720QM (6M Cache, 2.20
Level 2 Complex Laptop PC
VIETNAM GHz)16GB of RAM
model
2.0G - NVIDIA Quadro 2000M GDDR3
Coordination
SHIMIZU Intel Core i7-4900MQ Processor32 GB of RAM 4
Clash detection Laptop PC
VIETNAM GB NVIDIA Quadro K4100M
Technical meeting
Appendix A: Clash detection report
Export REVIT model to NAVISWORKS format (**.NWC) including the link file by using the following setting.

In NAVISWORKS, model’s colors shall be changed to


follow the trade color setting below.
 Architecture model : White
 Structural model : Dark gray
 Mechanical model : Cyan
 Electrical : Yellow
 Plumbing & Sanitary : Purple
 Fire Protection : Magenta
Appendix A: Clash detection report
Clash detection criteria
Each clash detection report shall be done between 2 trades of work. Lists below are the criteria for
clash detection.
Note: 3 mm. shall be used for tolerance of clash detection to avoid touch surface element clashing.
CDR (1) – Architectural and Structural model
Architectural model Structural model Checking type Remark
Ceiling Structural member (all) Hard

Floor Beam and slab Clearance (less than 2 meters)

CDR (2) – MEP and Structural model


MEP model Structural model Checking type Remark
MEP (all trade) Structural member (all) Hard

CDR (3) – Architectural and MEP model


Architectural model MEP model Checking type Remark
Ceiling MEP (all trade) Hard

CDR (4) – MEP model and MEP model


MEP model MEP model Checking type Remark
MEP (all trade) MEP (all trade) Hard
Appendix A: Clash detection report
VISUAL CHECK BY REVIT:
Appendix C: Coordinate system
Appendix C: Coordinate system
ARC+STR+MEP COMBINATION
1. BLOCK A - MECHANICAL TECHNICAL ROOM
1. MAKE MODEL.
2. CHECK CLASHING.
3. EXPORT SHOPDRAWING.
4. REQUEST BUILDER
WORKS.(REQUEST OPENING)
ARC+STR+MEP COMBINATION
1. BLOCK B - MECHANICAL TECHNICAL ROOM
ARC+STR+MEP COMBINATION
3. TYPICAL UNIT

UNIT A1
ARC+STR+MEP COMBINATION
3. TRANSFORMER & MSB ROOM AT BASEMENT 1.
1. MAKE MODEL.
2. CHECK CLASHING.
3. EXPORT SHOPDRAWING.
4. REQUEST BUILDER WORKS.
Requires changing the door height to
transport and install transformers
ARC+STR+MEP COMBINATION
3. PUMB ROOM AT BASEMENT 1

FIRE FIGHTING PUMB


ARC+STR+MEP COMBINATION
3. PUMB ROOM AT BASEMENT 1

FIRE FIGHTING PUMB


ARC+STR+MEP COMBINATION
3. ASMEP COMBINENATION - BASEMENT 1
ARC+STR+MEP COMBINATION
3. ASMEP COMBINENATION – B3 TO 2FL
ARC+STR+MEP COMBINATION
3. BOOTER PUMB ON ROOF
CONTENTS:
Sample Room

BEP (BIM Execution Plan- kế hoạch triển khai BIM )

Sample Singapore project BIM implement


SAMPLE Singapore project (BIM implement)

NATIONAL CANCER CENTRE SINGAPORE

24 storeys
4 basements

1. BIM at Big Project Implementation


2. Mockup room
3. Construction Site visit