10th Prefabrication Modular Construction Asia Summit 2018
10th Prefabrication Modular Construction Asia Summit 2018
10th Prefabrication Modular Construction Asia Summit 2018
• Modularization concept
• Modularization: decision-making and drivers
• Module types
• Modularization design – a constructability approach
• Advantages and limitations of modularization
• 3 case studies
• Questions
Who is AG&P?
• AG&P has grown from a leading local construction company in
the Philippines to a global industrial infrastructure company
with world-leading credentials across three lines of business:
• Gas Logistics: LNG supply chain design, development
and marketing
• Modular Construction
• FieldCOM: Manpower services and site works
million cumulative man-hours with only one minor LTI, setting another
83 first for the global infrastructure industry (@ August 2018)
5
Modularization Concept
• Modular fabrication refers to the process of building and constructing equipment off-site in a
fabrication facility
• The completed product is delivered to the worksite and quickly installed and integrated into
field operations
• This differs from on-site construction in which the equipment or system is fully built at the
worksite
• Modular fabrication offers significant benefits over field construction: efficiency, speed, safety,
quality, economy, and convenience
• Modern day mantra: “Do more faster and with fewer resources”
Development in Module Design
Process
module
3rd Generation
Module
Equipment (divide the
2nd Generation project into
skid Modules process
(Equipment, blocks)
Pre-assembled
Units)
First
Generation
Modules (Pipe
Racks or PAR)
Pipe rack
Site envelope requirement for the plant is reducing
with modular design development
Modularization Allows Parallel Activities
Modularization – Decision Making
No
Technical
Start Stick built Project
Feasibility
Yes
Site Survey (Site Module Yard No
Develop Schedule Specific restriction Survey for Develop module
for Stick-built and and opportunities) productivity and definition & index
Modular cost Is
modularizat
Develop execution ion better
strategies and option
Modularization execution strength
Drivers
Yes
Develop definitive
cost estimate
Develop scope of Develop size of
modularization modules
Modularize the
Project
Modularization Drivers
• Cost Reduction
• Shifting of labour intensive work to low cost countries
• Reduce indirect costs (camp, construction supervisions, consumables etc. at site rates)
• Improved productivity (weather, flexible workforce, site accessibility etc.)
• Improved quality hence lower COQ.
• Schedule Reduction
• Shifting of labour intensive work to low cost countries
• Reduce indirect costs (camp, construction supervisions, consumables etc. at site rates)
• Risk Reduction
• Risk of labour strikes and arranging manpower resource is reduced
• Political risk exposure duration is reduced
• Exposure to working in difficult geographies is reduced
• Safety risk is reduced due to reduced onsite work hours
Questions to Ak
Piping Pre-fabrication Man-hour/dia-inch 1–2 2–4 Mix of size of joints, type of material, wall thickness
Pipe Support
Man-hour/tons 90 – 100 130 – 150 Mix of light, medium and heavy steel
Fabrication
Pipe Support Erection Man-hour/tons 60 – 70 120 – 140 Mix of light, medium and heavy steel, accessibility to welder
Pipe Pressure Testing Man-hour/linear meter 0.4 - 0.5 0.75 – 1.5 Test packs preparation
Structural Erection Man-hour/ton 50 – 60 90 – 100 Mix of light, medium and heavy steel
Instrumentation Man-hour/ea 5 11
Commissioning
Commissioning
Module Types
Equipment Skids:
Pre-Assembled Manifold (PAM) Modules: Complete equipment package, easily
Fully assembled manifold modules includes majorly transportable with support frames and
valves, piping, steel structures, tagged E&I, cable structures. Process equipment, piping, E&I
trays, fireproofing and insulation bulks. High fabrication quality is maintained
vis-a-vis stick built
Stability in Design
• Modularization logistics costs are relatively • Modularization reduces the foot print
high • Savings on cable and piping quantity
• Cost of freight is added • Quality control in singular location
• Effort and costs for loading, unloading and • Early production schedule in controlled
transportation to site environment
• Parallel work-fronts/construction are
engaged to accelerate project schedule
• All stages of project are done in-house to
reduce third-party vendor liability issues,
ensuring our commitment to schedule
• Pragmatic approach to reduce burden on
project owner
• Interchangeability is improved in case of
defect or damage
Modular Construction Limitations
Substation 2 1,683
LER 15 9,950
LIR 9 4,824
Stair Tower 3 58
Total 29 16,515
Yard 1 Facilities Overview
25
Pipe Fabrication in Yard 1
17 Hectares of Available Material Laydown Area Automated Layout & Cutting of Pipe Supports
27
Pipe Fabrication in Yard 1 (cont’d)
Blasting & Painting at Automated & Manual Paint In-house Procedure for Preservation of Prefabricated
Shops Pipe Spools
AG&P has 3 automatic blasting lines (plates, sections
and pipes) to blast and prime the pipe spools and
supports
28
260,000-m2 Heavy Modularization Area
Load bearing capacity: Up to 50 MT/m2
29
Yard 2 facilities overview
Direct access to Batangas International Port
Office
Fabrication
shops
Warehouse Warehouse
30
State-of-the-art Production Shops
• Yard 2 utilizes the latest
automated machinery and
equipment including band saw,
beveling machine, CNC drilling
machine, CNC plasma cutting
machine, pipe coasters and pipe
rotators
• Fabrication shops: 17,600 m2
• Blast & paint shops: 1,980 m2
• Warehouse: 8,000 m2
31
Blasting and Painting Shop – Yard 2
Equipment:
Dust Collector
Dehumidifier
8 Blasting Nozzle each
287,000-m2 Heavy Modularization Area
Load bearing capacity: 10 – 30 MT/m2
33
Methodology
Construction & Load-Out Methodology
1. Fabrication of all steel members and assemble sub panels at fabrication shop
2. Transport all steel members and assembled panels to galvanizing prior to delivery to assembly
area
Fabrication Shop
Preparation of GT-204 EO
Concentrator for installation
Upending of GT-204 EO
Concentrator
Goro Nickel Mining Project
Crane – 01 Load Data
Equipment WT. 363.50 Mt
Crane Hook Wt. (600mt) / WT. 16.00 Mt
Weight Of Shackles 0.63 Mt
Weight Of Slings 0.92 Mt
Weight Of Spreader Beam 2.03 Mt
Total Lift Weight 383.08 Mt
Dynamic Amplification Factor -- %
Total Lift Weight W/ DAF 383.08 Mt
Crane Data: Terex Cc6800 SSL
Boom In Use Main
Track Centers 9.60 Meter
Car Body Counterweight 250.00 Mt
Main Boom Length -- Meter
Jib Boom Length 102.00 Meter
Super Lift C/W @ 24 Meter 450 Mt
Working Radius 24.00 Meter
Lifting Capacity 441.00 Mt
Crane Efficiency: 383.08 / 441.00 X 100 =
86.86%